,Subject:.Administrative Review No. 72-3
Applicant: Cambro Manufacturiflg Co.
Your application was acted ,, upon by the Huntington Beach
Board of Zoning Ad3usstments and your''
request was.
Approved
Approved with conditions XXX (see attached)
Disapproved
Continued until
Under the provisions of the Huntington Beach Ordinance
Code , the action taken by the B oard of Zoni ng Adjustments
is final unless an appeal is filed to the Planning Commis -
sicn by you or an interested party. Said appeal must be
it writing and must set forth in detail the action and
grounds by and upon which the applicant or interested
party deem :; himse lf aggrieved. Said appeal must be ac-
companied by afili ng fee of seventy -five ($75,,00) dollars
and submitted to the Secretary to the, Planning Commission
within ten (10) days of the date of the Board 's decision.
In your case, the
the filing fee is
last day for filing an appeal and. paying
February 18, 1972
Provisions of the Huntington Beach Ordinance Code are
such that any application becomes null: and void one (1)
.year after final approval , unless actual `construction
has started.
REQUIREMENTS OF THE H.B. ORDINANCE CODE and
CONDITIONS OF APPROVAL
ADmiriistrative Review No. 72-3
Applicant: Cambro Manufacturing Co.
1. The plot plan received February 7, 1972 shall be the
approved ;1,ayout .
2. Huntington Ave, and Clay St. shall be'dedicated and
fully improved to City standards at the time each
parcel is developed. Improvements shall include street
trees, street signs; streetlights, fire hydrants,
sewer and water main extensions.
3. Water supply shall be through the.r`ty of Huntington
Beach's water system.
4. Sewage disposal shall be through tie City of Huntington
'Beach's sewage system.
5. The water, sewer, and fire hydrant system shall be
approved by the Department of Public Works and Fire
Department .
6. The property shall participate in the local drainage
assessment district.
Soil reports as required by the Building Department
and the Department of Public Works shall be submitted
to the City prior to issuance of building permits.
8. All utilities shall be installed underground.
9. Off-street parking facilities ; shall -conform to
Article 979.
10. No structures, other.' than those shown on the approved,
plot plan, shall be constructed within the project.
All applicable City Ordinances shall be complied with.