HomeMy WebLinkAboutAdministrative Reviews ARX1973159 - Supporting Documents0
September 26, 1973
Re: ED 73-163 (AR 73-159)
Mr. Charles Hermanson
517 16th Street
Huntington Beach, California
Dear Mr. Hermanson:
P.O. BOX 190 - 92648
This is to advise you that the 10 day posting
period has expired for ED 73-163 pertaining to:
Six 4-unit apart:o: ,ts
escrip ion
22nd Street, Huntington Beach
ocation
and the Environmental Review Board has granted
the exemption.
It is recommended that you now proceed with the
processing of your project through appropriate
City channels as established prior to E . I. it,
requirements.
Cordi ally,
Carol Schwartz, Secretary
Environmental Review Board
Ef E TAL RVIEW BOARD
CITY OF HUNTINGTON BEACH • CALIFORNIA
W
ED 73163
FINDINGS
POSITIVE EFFECTS FROM THE PROJECT:
1. Improvements will be made in landscaping a presently uncared-
for lot.
2. Property tax income to be increased to the City.
NEGATIVE EFFECTS FROM THE PROJECT:
1. Loads on schools, utilities, streets and public facilities
,will be increased.
MITIGATING MEASURES:
1. The project shall be constructed with full insulation of all
exterior walls and ceilings to reduce the burden on heating
and cooling systems.
2. Building spoils , such as unusable lumber, wire, pipe, and
other surplus or unusable material shall' be dumped at on off--
site facility equipped to handle them.
3. Both natural gas and electricity shall be stubbed in for
clothes dryers , cooking facilities , water heaters , and refrig-
eration ,units to alleviate the possible drain on any one
energy source.
CONCLUSION:
The Board -finds that with the mitigating measures contained herein
the proposed project will not have a significa; t adverse effect
upon the physical enviro nment. li ,
ai L PLUMBING CO.* 517 • 161h STREET o
r ,D o/= o' J J „(G,
0 (714 ) 536.6663
HUNTINGTON BEACH, CALIFORNIA 9264L
Apo) U-5 lm
Gf ,`'7'/4',L:
U !nr G A cA G /--z-! f-o
741 1 14 tl. 13
'l -7
Mir 9
-4,., I'.
.t'/ 7 el, leek ?-'1J7,
Minutes: H. B. Board of Zoning Adjustments
Wednesday, September, 26, 1973
Page 2
information in the form of a recordable document on the parking
spaces, and"fgr this reason he recommendd°"that this application
be continued to -0et.ober 3, 1973.
ON MOTION BY EADIE AND SECONDEY",SPENCER ADMINISTRATIVE REVIEW
NO. 73-165 WAS CONTINUED,"T'.O`OCTOBER` s,,_„1073 BY THE FOLLOWING VOTE:
AYES: Gerarderl., Spencer, Eadie
NOES: None,-
ABSENT: None
r'rREGUJ''7CR AGENDA ITEMS:
ADMINISTRATIVE REVIEW NO. 73-159 (Continued from .9/12/73)
A licant: John D. King
To permit the construction of a 4 unit apartment building pursuant
to S. 9201.2 of the Huntington Beach Ordinance Code located on the
east side of 22nd Street, approximately 50 feet north of Orange
Avenue in an R-3, medium-high density residential district
John D. King., the applicant, was present.
The Acting Secretary outlined that the Environmental Review Board
approved Exemption Declaration No. 73-163 on September 25, 1973
with no stipulations.
The Board discussed the revised plan with. applicant and conditions
of approval were discussed.
Mr. King pointed out that he has resolved the cut on the stairway
and that the change as accepted by the structural plan check of the
Department of Building and Community.Development..
ON MOTION BY GERARDEN AND SECOND BY EADIE ADMINISTRATIVE REVIEW
NO 73-159 WAS APPROVED,WITH THE FOLLOWIN3 CONDITIONS AND BY THE
FOLLOWING VOTE:
A. TO, BE COMPLETED PRIOR TO ISSUANCE OF h-t"-rLDING PERMITS:
1. Tie revised plot plan received' gip- ,?i )'ar 26, 1973 shall
be the approved layout. Clear a %,' x."obstructed turning
radius for parking shall be provided.
271=iii Street and al ley shall be dedicated to City
standards at the time each parcel is. developed.
Minutes: 11. B. Board of Zoning Adjustments
Wednesday, September 26, 1973
Page 3
3. Elevations of the proposed plan received August 20, 1973
for review and approval action shall be the approved
elevations.
4. The water, sewer, and fire hydrant system shall be
approved by the Department of Public Works and'Fire
Department.
5. All buildings on lots abutting a City easement shall be
set back five (5) feet from the edge of such , easement.
'6. Soil and compaction reports as required by the Building
Department and the Department of Public Works shall be
submitted to the City.
B. TO BE COMPLETED PRIOR TO FRAMING INSPECTION:
1. Fire alarm system conduit and appurtenances shall be
installed by the developer at locations and to specifi-
cations provided, by the Fire Department.
C. TOLE COMPLETED PRIOR TO FINAL INSPECTION:
1. 22nd Street and alley shall be fully improved including
street trees, street signs, street lights, fire
hydrants, sewer and water main extensions.
2. All utilities shall be installed underground.
3. Off-street parking facilities shall conform to Article
979
D. TO B`E COMPLETED PRIOR TO ISSUANCE OF CERTIFICATE OF OCCUPANCY:
1. Water supply shall,be through the City of Huntington
Beach's water supply system.
2. Sewage disposal shall be through the City of Huntington
Beach's sewage s ystem.
3. Basements for utilities or walkways shall be provided
to Department of Public Works standards.
4. The property shall participate in the local drainage
assessment district.
5. No structures, other than those shown on the approved
plot plan, shall be constructed within the project.
All. applicable City Ordinances shall be complied with.