HomeMy WebLinkAbout1958-08-25Council Chamber, City Hall
Huntington Beach, California
Monday, August 25th, 1958
Pursuant to adjournment of the City
Council of the meeting of August 18, 19589 Mayor Irby called
the regular adjourned meeting to order at 5:30 o'clock P.M.
Councilman present: Lambert, Bryant, Terry, Irby.
Councilman absent: Waite (Councilman Waite arrived at
6:50 o'clock P.M.)
Hummell & Clutter Mayor Irby referred the request of Harvey
Hummell and Verne Clutter for a lease agreement option for a
sportfishing barge lease from October 1, 1958 to February 27,
1959 to the Beach and Pier Committee for study and report.
M & H Oil Corp. to On motion by Terry seconded by Bryant the
bread curb
request of Fred R. Mulker, Engineer for
the M and H Oil Corporation for permission to break the curb
on the 22nd Street side of Lot 12, Block 221, Huntington Beach
Tract, for the purpose of constructing a sixteen foot wide
driveway, and said work to be under the supervision- of the City
Engineer, be approved. Motion carried.
Artesia Growers The Clerk read a report from the Secretary
Association --
Performance bond of the Planning Commission and recommenda-
tions relative to the $5,000.00 performance bond to be furnished
by the Artesia Growers Association pursuant to Condition No. 5
of their use variance granted by the City Council. The Secre-
tary reports that the bonding companies cannot write a $5,000.00
performance bond but will insure performance bond in the amount
of $500.00 and the recommendations to the City and the Secre-
tary of the Planning Commission that the $500.00 bond would be
adequate to protect the City and not adversely handicap the
Association, and request the City Council to amend Condition
No. 5 of the Use Variance to read $500.00 performance bond in-
stead of $5000.00 performance bond.
On motion by Bryant seconded by Lambert
Condition No. 5 of the Use Variance granted to the Artesia
'rowers Association in October, 1957, be amended to read:
12
Page #2 -Minutes, August 25th, 1958
" 5. To furnish a performance bond
in the amount of $500.00" ,
be approved. Motion carried.
Agrmt. - Hamilton The Clerk reported the County of Orange had
Street Bridge
crossing returned the agreement between the County of
Orange and the City of Huntington Beach relative to the construct-
ion of the West approach to the Hamilton Street bridge crossing at
the Santa Ana River, and that Section 6B of the agreement had been
changed to read 10% of the City's contribution instead of 10% of
the total construction cost, as requested by the City Council.
On motion by Terry seconded by Bryant the
Mayor and the City Clerk be authorized to execute on behalf of the
City the agreement between the County of Orange and the City of
Huntington Beach for the construction of the West approach to the
bridge to be constructed over the Santa Ana River at Hamilton
Street, be approved. Motion carried.
Terry -Finance Comm. Mayor Irby appointed Councilman Terry to act
on the Finance Committee in the absence of Councilman Waite.
Culvert under The Clerk reported that the City Engineer
Talbert Ave. &
Goldenwest Sidney Lowry, had returned the draft of the
agreement between the City of Huntington Beach and the County of
Orange relative to the installation of a 36 inch C.M.P. culvert
under Talbert Avenue approximately 367 feet east of the center
line of Goldenwest Street adjacent to and immediately north of the
County's Disposal Station No. 10, and whereby the City of Hunt-
ington Beach shall pay for the construction of the project and
the following recommendations made by the City Engineers
1. It appears that the County dump property is the principal
benefactor if this proposed culvert is constructed.(
2. Under normal conditions, the City would probably assess at
cost a part of the construction cost against the benefiting
property.
3. Recommend that the City return the agreement with the suggest-
ion that the City will offer to pay the full cost for pro-
viding the 36" C.M. Pipe across the Talbert Avenue roadway
as its share of the cost of the project and the County to pay
2.
Page #3 - Minutest August 25th, 1958
installation and engineering costs.
Agrmt. - County of On motion by Bryant seconded by Lambert
Orange, culvert
in accordance with the recommendations and
the suggestions of the City Engineer the draft agreement be-
tween the City of Huntington Beach and the County of Orange be
returned to the County of Orange stipulating that the City will
agree to providing the 36 inch C.M.P. pipe across the Talbert
Avenue roadway as its share of the cost of the project and the
County to pay the installation and engineering costs, be approved.
Motion carried.
CP#106 - So.Calif. The Clerk read the transmittal received
Edison Co., heating
station from the Planning Commission relative to
conditional permit CP#106 filed by the Southern California
Edison Company of 309 Main Street, Huntington Beach, to permit
a landscaped heating station to be built on an approximate 120
feet by 200 feet site in an A-1 zoning district as was adopted
by an Interim Ordinance No. 668, the location approximately
1202 feet west of Springdale Street on the north side of
Wintersburg Avenue, the legal description being the south 237
feet of the west 120 feet of the east half of the southeast
quarter of Section 21, Township 5 south, Range 11 west, in
the Rancho Bolsa Chica, except the south 30 feet thereof, and
that a public hearing was held by the Planning Commission on
August 19, 1958, to consider the petitioner's request and the
required legal public notice was properly given prior to the
hearing, and after due discussion on the Conditional Permit
` CP#106, the following motion was made and carried by a roll
call vote, to recommend approval with the following conditions:
1. All appurtenant accessory features of the main structures
such as towers and exhaust stacks shall not be greater
than 43 feet in height.
2. All landscaping as indicated in the submitted plot plane,
shall be planted as a fulfillment of this condition.
****(SEE BEIOW-Page #15)
Councilman Waite Councilman. Waite arrived at 6:50 o'clock P.M.
arrived
3.
14
Page #4 -.Minutes, August 25th, 1958
Proposed contract Mayor Irby opened the discussion of the
for collection of
trash proposal of the Rainbow Disposal Company to
contract for the collection of waste and refuse in the City of
Huntington Beach.
Price & Rainbow Mr. Price of Price Disposal Company and Mr.
Disposal Companies_
Loumena, representative of Rainbow Disposal
Company were present and indicated their desire to bid for the
collection of waste and refuse in the City of Huntington Beach,
and that it would help them in making an offer if the City could
furnish them with the approximate units to be serviced in the
City.
Trash Survey Following the discussion Mayor Irby appointed
Committee
appointed a committee comprised of the Mayor, Street
Superintendent Wm. Lewis, Mr., Price of Price Disposal Company and
Wm. Loumena of Rainbow Disposal Company to meet on Thursday
morning and cover the City within the boundaries as existed prior
to August 1, 1957, and to make an actual count of the units of
the City to be served.
On motion by Bryant seconded by Terry that a
count be made of the actual unit trash pickups required within the
City limits ae't he City limits existed prior to August 19 19579
and the survey committee appointed by Mayor Irby compile the
actual count of units existing and report to the City Council at
the regular meeting of September 2, 19589 be approved. Motion
carried.
Dr. Kowitt - On motion by Lambert seconded by Bryant the
restricted park-
in
€ zone request of Dr. S. N. Kowitt, 307 Main Street,
for a restricted parking zone for emergency vehicles in front of
his office at 307 Main Street, be granted. Motion carried.
Removal of trees On motion by Waite seconded by Terry the
Street Superintendent be instructed to remove trees in the follow-
ing locations:
I Eucalyptus on 13th Street between Crest and Main
l,Pine tree on Crest between 13th and 14th Streets
1 Eucalyptus on Acacia at loth and Main Street
2 Palms at the southwest corner of Indianapolis and Delaware
4•
Page #5 — Minutes, August 25th, 1958
SS�
and the Street Superintendent be instructed to replace with
appropriate trees, be approved. Motion carried.
Demands On motion by Bryant seconded by Terry the
demands as approved by the Finance Committee be ordered paid.
Motion carried.
On motion by Terry seconded by Bryant the ad-
journed meeting of the City Council adjourn.
City Clerk and ex--officio Clem
of the City Council of the City
of Huntington Beach, California
ATTEST: Mayor
City Clerk
** On motion by Bryant seconded by Terry in
accordance with the recommendations of the Planning Commission
Conditional Permit No. 105 filed by the Southern California
Edison Company for a heating station to be built at a location
approximately 1202 feet west of Springdale Street on the north
side of Wintersburg Avenue subject to the conditions requested
to be imposed, be granted. ]notion carried.
ATTEST:
City Clerk
5.