HomeMy WebLinkAbout1976-12-15MINUTES
HUNTINGTON BEACH BOARD OF ZONING ADJUSTMENTS
Room B-8 - Civic Center
2000 Main Street
Huntington Beach, California
WEDNESDAY, DECEMBER 15, 1976 - 1:15 PM
BOARD MEMBERS PRESENT: PALIN, CROSBY, SPENCER
CITY STAFF PRESENT: CHUCK BURNEY, FIRE DEPARTMENT
MINUTES: ON MOTION BY PALIN AND SECOND BY SPENCER THE MINUTES
OF THE REGULAR MEETING OF NOVEMBER 10, 1976, WERE APPROVED AS
TRANSCRIBED, BY THE FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
REGULAR AGENDA ITEMS:
USE PERMIT NO. 76-51 (Cont. from 9-15-76)
Applicant: W. Sterling Buck & Associates_
To permit the construction of a six (6) unit apartment building
pursuant to Section 9162.3.2 of the Huntington Beach Ordinance
Code, located on the west side of Torrey Lane approximately 500
feet north of Heil Avenue in an R2, Medium Density Residential
District.
Chairman Crosby informed the Board that this request is covered
by Negative Declaration No. 76-14, adopted by the Planning Commis-
sion on approval of TT8698.
The Chairman opened the public hearing. Paul La Point was present
to represent the application. There being no other persons to
address the Board in regard to this project, the public hearing
was closed.
The Board discussed the phasing of the structures and timing of
street improvements with the applicant.
ON MOTION BY PALIN AND SECOND BY CROSBY THE BOARD ADOPTED NEGA-
TIVE DECLARATION No. 76-14, BY THE FOLLOWING VOTE:
AYES: PALIN, CROSBY SPENCER
NOES: NONE
ABSENT: NONE
Minutes, H.B Board of Zoning Adjustments
December 15 1976
Page 2
ON MOTION BY PALIN AND SECOND BY SPENCER USE PERMIT NO. 76-51
WAS APPROVED WITH THE FOLLOWING FINDINGS AND CONDITIONS, BY THE
FOLLOWING VOTE:
FINDINGS OF THE BOARD:
1. The establishment, maintenance, and operation of the use will
not be detrimental to:
a. The general welfare of persons residing or working in the
vicinity;
b. Property and improvements in the vicinity of such use or
building.
2. The granting of a Use Permit will not adversely affect the
Master Plan of the City of Huntington Beach.
3. The proposal is consistent with the City's General Plan of
Land Use.
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO ISSUANCE OF BUILDING PERMITS:
1. The conceptual plot plan and elevations received September 1, 1976
shall be the approved layout.
In its approval action, the Board of Zoning Adjustments considered the
following issues relating to the conceptual plan:
Traffic circulation and drives;
Parking layout;
Lot area;
Lot width and lot depth;
Type of use and its relation to property and improvements in the
immediate vicinity;
Past administrative action regarding this property.
2. A landscape and irrigation plan complying with Article 979 of the
Huntington Beach Ordinance Code and landscaping specifications
on file in the Department of Public Works shall be submitted
to the Department of Building and Community Development.
3. Soil and compaction reports shall be submitted by a certified
soils engineer. Said reports shall be submitted to the
Department of Building and Community Development and shall be
subject to approval by that Department.
12-15-76 Page 2
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 3
4. Fire protection system,:, includinq automatic sprinkler
systems, standpipe systems, fire hydrants, fire alarm
systems, and any other_ required fire proL-ecLLori and detection
devices or systems shall comply with the specifications of
the Huntington Beach Fire Code. Plans for such systems and
devices shall be submitted to the Fire Department and shall
be subject to approval by the Departments of Fire and Public
Works.
5. All applicable fees shall be paid prior to issuance of
building permits.
B. GENERAL CONDITIONS:
1. An instrument shall be recorded granting reciprocal ingress
and egress privileges over and between this lot and the lot to
the east for access to both parcels.
2. If the developer proposes to provide air conditioning, the
insulation in ceilings and exterior walls shall be a minimum
of R-19 and R-11, respectively. If no air conditioning is
to be provided, the insulation in ceilings and exterior
walls shall be a minimum of R-13 and R-7, respectively.
3. All building spoils, such as unusable lumber, wire, pipe,
and other surplus or unusable material, shall be disposed
of at an offsite facility equipped to handle them.
4. Natural aas and 220V electrical shall be stubbed in at the
location of clothes dryers, and natural gas shall be stubbed
in at the locations of cooking facilities, water heaters,
and central heating units.
5. The structures on subject property, whether attached or det-
ached, shall be constructed in compliance with the State
acoustical standards set forth for all units that lie within
the 60 CNEL contours of the property.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
TENTATIVE PARCEL MAP NO. 76-30 (In Conj./AR 76-105)
Applicant: George Bach
To permit the creation of a legal parcel per a previously recorded
record of survey pursuant to Section 9930.2 of the Huntington
Beach Ordinance Code, located on the north side of Pacific Coast
Highway approximately 180 feet northwest of Anderson Street in a
C2, Community Business District.
BZA 12-15-76 P&ge 3
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 4
No one was present to represent the application.
Secretary Palin reviewed the history of this application for
the Board's information. Applicant has not been able to submit
the necessary documentation on the creation of the parcel with
proof of how said parcel was segregated originally.
ON MOTION BY SPENCER AND SECOND BY CROSBY TENTATIVE PARCEL MAP 76-30
WAS DENIED WITHOUT PREJUDICE, BY THE FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
ADMINISTRATIVE REVIEW NO. 76-105 (In Conj./TPM 76-30)
Applicant: Frank Gonzales & Associates
To permit the construction of a 4,000 square foot automobile ser-
vice center pursuant to Section 9430.5 of the Huntington Beach
Ordinance Code, located on the north side of Pacific Coast Highway
approximately 180 feet northwest of Anderson Street in a C2,
Community Business District.
Chairman Crosby informed the Board that this request is covered by
Negative Declaration No. 76-69.
Secretary Palin informed the Board that, in view of the denial of
the tentative parcel map for subject project, it will be necessary
to deny the administrative review request as well, pending appli-
cant's submittal of proof that the property constitutes a legal
building site.
ON MOTION BY SPENCER AND SECOND BY CROSBY ADMINISTRATIVE REVIEW
NO. 76-105 WAS DENIED WITHOUT PREJUDICE, BY THE FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
TENTATIVE PARCEL MAP NO. 76-38 (Cont. from 11-17-76)
Applicant: Glenn Busby
To permit the separation of one (1) parcel into seven (7) parcels
for commercial purposes pursuant to Section 9921 of the Hunting-
ton Beach Ordinance Code, located on the southeast corner of
Goldenwest Street and Edinger Avenue in a C4, Highway Commercial
District.
Chairman Crosby informed the Board that this request is covered
by Negative Declaration No. 76-84, adopted by the Board on Septem-
ber 15, 1976, upon approval of Use Permit No. 76-52.
1
BZA 12-15-76 Page 4
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 5
George Ritzau was present to represent the application and indi-
cated his receipt of and concurrence with the suggested conditions
of approval.
Bruce Crosby discussed vehicular access rights to the parcels and
a portion of the property not presently dedicated as a public
easement but which is presently a part of the flood control channel.
He requested that this portion be shown.as a public easement on
the parcel map. Jim Palin further informed the applicant that it
will be necessary to submit a copy of the recorded ingress -egress
easements to the Planning Department; the applicant agreed to each
of the above additions to the conditions of approval previously
sent to the developer.
ON MOTION BY CROSBY AND SECOND BY PALIN TENTATIVE PARCEL MAP NO.
76-38 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOWING
VOTE:
CONDITIONS OF APPROVAL:
A. To
be completed prior to use or occupancy of said parcels for
any
purpose:
1.
The tentative parcel map received by the Planning Department
November 9, 1976 shall be the approved layout.
2.
A parcel. map shall be filed with, and approved by, the
Department of Public Works, and recorded with the Orange
County Recorder.
3.
Edinger Avenue and Goldenwest Street shall be dedicated and
improved to City standards at the time said parcels are
developed.
4.
Water supply shall be through the City of Huntington Beach's
water system at the time said parcels are developed.
5.
Sewage disposal shall be through the City of Huntington
Beach's sewage system at the time said parcels are developed.
6.
All utilities shall be installed underground at the time
said parcels are developed.
7.
Compliance with all applicable City Ordinances.
8.
The flood control channel shall be fenced to Flood Control
District standards and City standards at the time said
parcels are developed.
9.
The property shall participate in the local drainage
assessment district at the time said parcels are developed. —_
(Contact the Department of Public Works for additional
information.)
BZA 12-15-76 Page 5
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 6
10. A copy of the recorded parcel map shall be filed with the
Planning Department.
11. Vehicular access rights shall be dedicated to the City
of Huntington Beach except at locations to be approved by the
Board of Zoning Adjustments.
12. A copy of the recorded agreement for ingress and egress
and parking and any restrictions to be set forth shall
be submitted to the Planning Department prior to the
occupancy of the first structure upon the first parcel.
13. The portion of the flood control channel which has not
been shown as a public easement shall be dedicated to the
City of Huntington Beach on a parcel map as a public
easement for such purpose.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
OIL WELL ACTIVATION PEIUIIT NO. 76-7 (Cont. from 12-8-76)
Applicant: W. M. Elliott
To permit an oil well activation pursuant to Section 15.40.020(B)
of the Huntington Beach Municipal Code, located on the east side
of Huntington Street approximately 500 feet south of Yorktown
Avenue in an R2-0, Medium Density Residential combined with Oil
Production District.
Chairman Crosby informed the Board that this request is covered
by Negative Declaration No. 76-102, adopted by the Board on Novem-
ber 24, 1976, upon approval of QWA 76-6.
Mr. Elliott was present at the meeting and discussed the time and
economic constraints under which he is attempting to process this
request.
The Board again reviewed the possible effects of future street
realignment and park negotiations on this project.
ON MOTION BY PALIN AND SECOND BY CROSBY OIL WELL ACTIVATION PERMIT
NO. 76-7 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOW-
ING VOTE:
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO ISSUANCE OF PERMITS:
1. The plot plan received and dated November 8, 1976, shall
be the approved layout in conjunction with the recommenda-
tions of the Oil Field Supervisor, subject to the following:
a. Before subject well is put on production the City shall
analyze the street alignment on subject property. If a
BZA 12-15-76 Page 6
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 7
new alignment is not deemed desirable and the existing
street terminated as a cul-de-sac, said well shall not be
put on production and the reactivation permit shall become
null and void.
b. Should the well be put on production and become a suc-
cessful operation, the proponent shall agree and shall
submit such agreement to the City in writing that said
production will not be the basis for any increase in
value of the property over its current value should the
City desire to purchase the property for park purposes in
the future.
2. The applicant shall comply with all requirements of the
Huntington Beach Oil Code.
3. Should the applicant propose to use internal combustion
engines, said engines shall be muffled to a level to assure
that there will be no interference with surrounding resi-
dential uses. Otherwise, electrical motors shall be
utilized.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
CONDITIONAL EXCEPTION NO. 76-65 (Cont. from 12-8-76)
Applicant: Glamour Awning
To permit an 18-inch encroachment into the required three (3)
foot side yard setback per Section 9242.8(c) of the Huntington
Beach Ordinance Code, located at the southwest corner of Newland
Street and Ellis Avenue in an MH. Mobilehome District.
Chairman Crosby informed the Board that this request is a Categ-
orical Exemption, Class V, California Environmental Quality Act,
1970.
The Chairman opened the public hearing. Bill Fugate was present
to represent the application and reported to the Board that the
future tenant on the abutting lot (Lot 122) is also going to be
installing a two -car covered parking facility. There being no
other persons to address the Board in regard to the proposal, the
public hearing was closed.
The Board reviewed the request with the applicant and discussed
discrepancies between the plot plan he has presented and the re-
vised plan submitted for the park by the applicants on December
13, 1976. Secretary Palin noted that other residents in the park
are complying with code requirements without benefit of a variance
and that in his opinion granting of this request would constitute
granting of special privilege not available to other owners within
the park. After further discussion it was the consensus among
Board members and the applicant to continue the request to permit
field investigation, consideration of alternative methods of
BZA 12-15-76 Page 7
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 8
providing covered parking for this particular lot and the ad-
joining space, and review of State codes and Division 9 require-
ments. The applicant was instructed to meet with the park developer
to resolve the configuration of the subject property.
ON MOTION BY PALIN A14D SECOND BY SPENCER CONDITIONAL EXCEPTION
NO. 76-65 WAS CONTINUED, WITH THE CONCURRENCE OF THE. APPLICANT,
TO THE REGULAR MEETING OF JANUARY 5, 1977, BY THE FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
USE PERMIT NO. 76-75 (In Conj./AR 76-176) (Cont. from 12-8-76)
Applicant: Michael Janes
To permit the construction of six (6) fourplexes and one (1)
triplex abutting an arterial street pursuant to Section 9164.4 of
the Huntington Beach Ordinance Code, located on the west side of
Bolsa Chica Street approximately 200 feet north of Pearce Street
in an R2, Medium Density Residential District.
Chairman Crosby informed the Board that this request is a Categ-
orical Exemption, Class III, California Environmental Quality
Act, 1970.
The Chairman opened the public hearing. George Alvarez was
present and displayed revised, colored elevations for the units
facing the arterial. There being no other persons present to
address the Board on this request, the public hearing was closed.
Board review found the treatment presented to be in compliance
with the intent of the Planning Commission for the street scene
on arterials.
ON MOTION BY PALIN AND SECOND BY SPENCER USE PERMIT NO. 76-75
WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOWING VOTE:
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO ISSUANCE OF BUILDING PERMITS:
1. The revised elevations received and dated December 14, 1976,
shall be the approved elevations for the street scene along
Bolsa Chica Street.
In its approval action, the Board of Zoning Adjustments considered
the following issues relating to the conceptual plan:
• Type of use and its relation to property and improvements in
the immediate vicinity;
• Past administrative action regarding this.property.
AYES: PALIN,
NOES: NONE
ABSENT: NONE
CROSBY, SPENCER
BZA 12-15-76 Page 8
1
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 9
USE PERMIT NO. 76-76 (In Conj./AR 76-177) (Cont. from 12-8-76)
Applicant: Dunn Properties
To permit truck and loading facilities to face a public street
pursuant to Section 9518(a) of the Huntington Beach Ordinance
Code, located at the southwest corner of Graham Street and Com-
mercial Drive in a 100-M1-A-20,000, Restricted Manufacturing
District.
Chairman Crosby informed the Board that this request is covered
by EIR 73-16, adopted by the City Council on March 18, 1974.
The Chairman opened the public hearing. No one was present to
speak for or against the proposed project; the public hearing
was closed.
Secretary Palin reported that a request for continuance has been
received.
ON MOTION BY PALIN AND SECOND BY SPENCER USE PERMIT NO. 76-76
WAS CONTINUED AT THE REQUEST OF THE APPLICANT, TO THE REGULAR
MEETING OF DECEMBER 29, 1976, BY THE. FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
ADMINISTRATIVE REVIEW NO. 76-177 (In Conj.UP 76-76) (Cont. from
Applicant: Dunn Properties 12-8-76)
To permit the construction of a 9,000 square foot industrial
building pursuant to Section 9511 of the Huntington Beach Ordin-
ance Code, located on the southwest corner of Graham Street and
Commercial Drive in a 100-M1-A-20,000, Restricted Manufacturing
District.
Chairman Crosby informed the Board that this request is covered
by EIR 73-16, adopted by the City Council on March 18, 1974.
Sec^etary Palin reported that a request for continuance has been
received.
ON MOTION BY PALIN AND SECOND BY SPENCER ADMINISTRATIVE REVIEW
NO. 76-177 WAS CONTINUED, AT THE REQUEST OF THE APPLICANT, TO THE
REGULAR MEETING OF DECEMBER 29, 1976, BY THE FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
BZA 12-15-76
Page 9
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 10
TENTATIVE PARCEI, MAP 11O. 76-62
,�2plicant: Michael Gesler & Associates
To permit a two (2) lot division of land pursuant to Section 9921
of the Huntington Beach Ordinance Code, located on the west side
of Brookhurst Street approximately 792 feet south of Garfield Ave-
nue in a C2, Community Business District.
Chairman Crosby informed the Board that this request is covered by
Negative Declaration 76-105, adopted by the Board on December 8,
1976, upon approval of A.R. 76-171.
Michael Geslef was present at the meeting and indicated that he
had received and does concur with the suggested conditions of ap-
proval.
The Board reviewed the request with the applicant. Bruce Crosby
noted that the parcel map to the north of this property has not
been recorded which will require that this map be amended or that
it be conditioned not to record prior to the TPM 76-24 on the ad-
joining property.
ON MOTION BY PALIN AND SECOND BY CROSBY TENTATIVE PARCEL MAP NO.
76-62 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOWING
VOTE:
CONDITIONS OF APPROVAL
A. To be completed prior to use or occupancy of said parcels for
any purpose:
1. The tentative parcel map received by the Planning Department
on December 3, 1976 shall be the approved layout with the
amendments as noted thereon.
2. A parcel map shall be filed with, and approved by, the
Department of Public Works, and recorded with the Orange
County Recorder.
3. Brookhurst Street shall be dedicated and improved to City
standards at the time said parcels are developed.
4. Water supply shall be through the City of Huntington Beach's
water system at the time said parcels are developed.
5. Sewage disposal shall be through the City of Huntington Beach'
sewage system at the time said parcels are developed.
6. All utilities shall be installed underground at the time said
parcels are developed.
7. Compliance with all applicable City Ordinances.
BZA
12-15-76
Page 10
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 11
8. The flood control channel shall be fenced to Flood Control
District and City standards at the time said parcels are
developed.
9. The property shall participate in the local drainage assess-
ment district at the time said parcels are developed.
10. A copy of the recorded parcel map shall be filed with the
Planning Department.
11. Tentative Parcel Map No. 76-24 shall be recorded prior to
the recordation of subject map and/or subject map shall be
amended to incorporate the 70 foot parcel to the north along
with 30 feet to create a 100 foot parcel for the Forrest
Olson Realty office, creating two additional parcels for
an overall three parcels on this parcel map.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
TENTATIVE PARCEL MAP NO. 76-63
Applicant: Emerald Engineering
To permit one (1) lot division of land pursuant to Section 9921
of the Huntington Beach Ordinance Code, located on the north side
of Los Patos Avenue approximately 110 feet east of Sims Street in
an R1, Low Density Residential District.
Chairman Crosby informed the Board that this request is a Categori-
cal Exemption, Class V(a), California Environmental Quality Act,
1970.
Don Baker was present at the meeting to represent the application
and indicated his receipt'of and concurrence with the suggested
conditions of approval. The Board reviewed the legal description
and boundaries of the project with the applicant.
ON MOTION BY CROSBY AND SECOND BY SPENCER TENTATIVE PARCEL MAP
NO. 76-63 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOW-
ING VOTE:
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO USE OR OCCUPANCY OF SAID PARCEL
FOR ANY PURPOSE:
1. The tentative parcel map received.by the Planning Department
on December 7, 1976, shall be the approved layout.
2. A parcel map shall be filed with, and approved by, the
Department of Public Works, and recorded with the Orange
County Recorder.
,:)7p_ 7 2-15-76 Page 11
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 12
3. Los Patos Avenue shall be dedicated and improved to City
standards at the time said parcel is developed.
4. Water supply shall be through the City of Huntington Beach's
water system at the time said parcel is developed.
5. Sewage disposal shall be through the City of Huntington
Beach's sewage system at the time said parcel is developed.
6. All utilities shall be installed underground at the time
said parcel is developed.
7. Compliance with all applicable City ordinances.
8. The property shall participate in the local drainage
assessment district at the time said parcel is developed.
9. A copy of the recorded parcel map shall be filed with the
Planning Department.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
ADMINISTRATIVE. REVIEW NO. 76-130
Applicant: Circle T Corporation
To permit the construction of a triplex apartment building pursuant
to Section 9384.16 of the Huntington Beach Ordinance Code, located
on the west side of 17th Street approximately 50 feet north of
Walnut Avenue in the Townlot Specific Plan, Area One B.
Chairman Crosby informed the Board that this request is a Categori-
cal Exemption, Class III, California Environmental Quality Act, 1970.
No one was present to represent the application.
The Board reviewed the plan submitted and found it to comply with
code requirements.
ON MOTION BY CROSBY AND SECOND BY SPENCER ADMINISTRATIVE REVIEW
NO. 76-130 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOW-
ING VOTE:
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO ISSUANCE OF BUILDING PERMITS:
1. The revised plot plan received and dated December 15, 1976,
shall be the approved layout.
In its approval action, the Board of Zoning Adjustments considered
the following issues in relation to the conceptual plan:
'?-15-76 Page 12
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 13
. Traffic circulation and drives;
. Parking layout;
. Lot area;
Lot width and lot depth;
Type of use and its relation to property and improvements in the
immediate vicinity;
Past administrative action regarding this property.
2. A landscape and irrigation plan shall be submitted to the
Department of Building and Community Development. Said plan
shall comply with Article 979 of the Huntington Beach Ordin-
ance Code and landscaping specifications on file in the
Department of Public Works.
3. In accordance with the City's standards and requirements, an
additional two and one-half (2-1/2) feet of additional right-
of-way on the alley shall be dedicated.
4.
Soil and compaction reports shall be submitted by a
certified soils engineer. Said reports shall be submitted
to the Department of Bui..l(ling and Community Development and
shall be subject to approval by that Department.
5.
Fire protection systems, including automatic sprinkler systems,
standpipe systems, fire hydrants, fire alarm systems, and any
other required fire protection devices or systems shall comply
with the specifications of the Huntington Beach Fire Code.
Plans for such systems and devices shall be submitted to the
Fire Department and shall be subject to approval by the
Departments of Fire and Public Works.
6.
The developer shall participate in the local drainage assess-
ment district.
7.
All applicable fees shall be paid prior to issuance of
building permits.
B. TO BE COMPLETED PRIOR TO FINAL INSPECTION:
1. Seventeenth Street and the alley shall be improved to the
centerlines of such rights -of -way. Said improvements shall
include curbs, gutters, sidewalks, paving, street trees,
street lights, street signs, street drainage, and sewer and
water main extensions, in full compliance with the City of
Huntington Beach street standards and requirements.
C. GENERAL CONDITIONS:
1. A parcel map shall be filed and recorded to eradicate the
property line between Lots 5 and 7 and to consolidate those
lots as a single legal building site. A copy of said recorded
map shall be filed in the Planning Department.
AYES: PALIN, CROSBY, SPENCER
DOES: NONE
ABSENT: NONE
BZA 12--15-76 Page 13
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 14
ADMINISTRATIVE REVIEW NO. 76-182
Applicant: Gerald A. Jones
To permit the construction of a 17,000 square foot industrial
building pursuant to Section 9511 of the Huntington Beach Ordinance
Code, located on the east side of Redondo Circle approximately 330
feet south of Talbert Avenue in an Ml-A, Restricted Manufacturing
District.
Chairman Crosby informed the Board that this request is covered by
Exemption Declaration No. 74-169, adopted by the Board upon approval
of Division of Land 74-42 (which established the industrial subdiv-
ision in which subject project is located) on January 29, 1975.
The Board reviewed the current application for compliance with the
original exemption declaration request.
ON MOTION BY PALIN AND SECOND BY CROSBY THE BOARD READOPTED EXEMP-
TION DECLARATION NO. 74-169 BY THE FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
Gerald Jones was present at the meeting. The Board reivewed the
request, discussing easement lines and setbacks therefrom.
ON MOTION BY PALIN AND SECOND BY SPENCER ADMINISTRATIVE REVIEW
NO. 76-182 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOW-
ING VOTE:
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO ISSUANCE OF BUILDING PERMITS:
1. The plot plan received and dated December 7, 1976, shall be
the approved layout, subject to the modification described
herein:
a. The plan submitted to the Department of Building and Com-
munity Development upon application for building permits
shall reflect the landscaping as required by the M1-A
District as well as showing a fifteen (15) foot setback
from curb line for all structures.
In its approval action, the Board of Zoning Adjustments considered
the following issues relating to the conceptual plan:
Traffic circulation and drives;
Parking layout;
Lot area;
. Lot width and lot depth;
Type of use and its relation to property and improvements in the
immediate vicinity;
Past administrative action regarding this property.
':�7Z 1 9-7 5-76 Pace 14
1
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 15
2. The following plans shall be submitted to the Department
of Building and Community Development:
a. Landscape and irrigation plan complying with Article
979 of the Huntington Beach Ordinance Code and land-
scaping specifications on file -in the Department of
Public Works.
b. Rooftop mechanical equipment screening plan, if applicable.
Said plan shall indicate screening of all rooftop mechani-
cal equipment and shall delineate the type of material
proposed to screen said equipment.
3. Soil and compaction reports shall be submitted by a certified
soils engineer. Said reports shall be submitted to the De-
partment of Building and Community Development and shall be
subject to approval by that Department.
4. Fire protection systems, including automatic sprinkler systems,
standpipe systems, a fire hydrant on -site, fire alarm systems,
and any other required fire protection and detection devices
or systems shall comply with the specifications of the Hunting-
ton Beach Fire Code. Plans for such systems and devices shall
be submitted to the Fire Department and shall be subject
to approval by the Departments of Fire and Public Works.
5. The developer shall participate in the local drainage assess-
ment district.
6. The developer shall participate in the Orange County Sanita-
tion District 43 Sewer Annex District.
7. All applicable fees shall be paid prior to issuance of
building permits.
B. GENERAL CONDITIONS:
1. A copy of the recorded reciprocal agreement for vehicular
ingress -egress shall be submitted to the City at the time
of application for building permits.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
ADMINISTRATIVE REVIEW NO. 76-183
Applicant: William R. Burke
To permit the construction of four (4) industrial buildings (total-
ing 47,800 square feet) pursuant to Section 9511 of the Huntington
Beach Ordinance Code, located between McFadden Avenue and Commercial
Drive approximately,280 feet west of Graham Street in a 100-M1-A-
20,000, Restricted Manufacturing District.
BZA 12-1-576 Page 15
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 16
Chairman Crosby informed the Board that this request is covered
by EIR 73-16, adopted by the City Council on March 18, 1974.
John Hawkins was present to represent the application.
The Board review included discussion of parking and reciprocal
easements, setbacks from arterials and property lines, and the
development on abutting parcels.
ON MOTION BY PALIN AND SECOND BY SPENCER ADMINISTRATIVE REVIEW
NO. 76-183 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOL-
LOWING VOTE:
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO ISSUANCE OF BUILDING PERMITS:
1. The plot plan received December 7, 1976, shall be the
approved layout.
In its approval action, the Board of Zoning Adjustments considered
the following issues relating to the conceptual plan:
. Traffic circulation and drives;
Par_kinq layout;
Lot area;
. Lot width and lot depth;
Type of use and its relation to property and improvements in the
immediate vicinity;
Past administrative action regarding this property.
2. The following plans shall be submitted to the Department of
Building and Community Development:
a. Landscape and irrigation plan complying with Article 979
of the Huntington Beach Ordinance Code and landscaping
specifications on file in the Department of Public Works.
b. Rooftop mechanical equipment screeing plan, if applicable.
Said plan shall indicate screening of all rooftop mech-
anical equipment and shall delineate the type of material
proposed to screen said equipment.
3. Soil and compaction reports shall be submitted by a certified
soils engineer. Said reports shall be submitted to the
Department of Building and Community Development and shall
be subject to approval by that Department.
4. Fire protection systems, including automatic sprinkler sys-
tems, standpipe systems, fire hydrants, fire alarm systems,
and any other required fire protection and detection devices
BZA 12-15-76 Page 16
1
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 17
or systems shall comply with the specifications of the Iiunt-
incgton Leach Fire Code. Plans for such systems and devices
;hall b0 submitted to the fire Department and shall be subject
to approval by the Departments of fire and Public Works.
5. All applicable fees shall be paid prior to issuance of
building permits.
B. TO BE COMPLETED PRIOR TO FINAL INSPECTION:
1. Street improvements shall be installed subject to the stand-
ards of the Department of Public Works, and shall include
installation of street trees as originally conditioned upon
approval of Tentative Tract 6948.
C. GENERAL CONDITIONS:
1. A copy of the reciprocal agreement for ingress -egress, turning
radius, and parking shall he submitted to the Department of
Building and Community Development prior to occupancy of any
structure on subject site.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
ADMINISTRATIVE REVIEW No. 76-186
Applicant: Rodney F. Emery
To permit the construction of a 14,000 square foot industrial build-
ing pursuant to Section 9511 of the Huntington Beach Ordinance
Code, located on the east side of Computer Lane approximately 420
feet south of McFadden Avenue in a 100-M1-A-20,000, Restricted Manu-
facturing District.
Chairman Crosby informedthe Board that this request is covered by
EIR 73-16, adopted by the City Council on March 18, 1974.
Rodney Emery was present at the meeting.
BoarO review ensued, taking into consideration the nature of the use
and proposed outside storage areas, setbacks from property lines,
and the prior consolidation of three lots into two parcels upon one
of which subject building is to be constructed.
ON MOTION BY PALIN AND SECO14D BY CROSBY ADMINISTRATIVE REVIEW NO.
76-186 WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOWING
VOTE:
7)7? 11 *')-1, G,-71-, 'D, CAP. " 7
Minutes, H.A. Board of Zoning Adjustments
December 15, 1976
Page 18
CONDITIONS OF APPROVAL:
A. TO BE COMPLETED PRIOR TO ISSUANCE OF BUILDING PERMITS:
1. The plot plan received and dated December 9,,1976, shall
be the approved layout.
In its approval action, the Board of Zoning Adjustments considered
the following issues relating to the conceptual plan:
. Traffic circulation and drives;
Parking layout;
Lot area;
Lot width and lot depth;
. Type of use and its relation to property and improvements in the
immediate vicinity;
Past administrative action regarding this property.
2. The following plans shall be submitted to the Department
of Building and Community Development:
a. Landscape and irrigation plan complying with Article 979
of the Huntington Beach Ordinance Code and landscaping
specifications on file in the Department of Public Works.
b. Rooftop mechanical equipment screening plan. Said plan
shall indicate screening of all rooftop mechanical equip-
ment and shall delineate the type of material proposed to
screen said equipment.
3. Soil and compaction reports shall be submitted by a certi-
fied soils engineer. Said reports shall be submitted to
the Department of Building and Community Development and
shall be subject to approval by that Department.
5. Fire protection systems, including automatic sprinkler sys-
tems, standpipe systems, fire hydrants, fire alarm systems,
and any other required fire protection and detection devices
or systems shall comply with the specifications of the
Iuntington Beach Fire Code. Plans for such systems and dev-
ices shall be submitted to the Fire Department and shall be
subject to approval by the Departments of Fire and Public
Works.
6. All applicable fees shall be paid prior to issuance of
building permits.
7. The plan submitted to the Building Department in conjunction
with application for building permits shall reflect antici-
pated future storage areas.
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 19
B. TO BE COMPLETED PRIOR TO FINAL INSPECTION:
1. Street trees shall be installed in accordance with the
conditions of approval originally imposed upon Tract 6948.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE.
MISCELLANEOUS AGENDA ITEMS:
TENTATIVE PARCEL MAP NO. 76-58
Applicant: Robert F. Maguire III
A request to permit delay in dedication of Anderson Street to a
future date, on a previously approved project located at Pacific
Coast Highway north of Anderson Street.
The Board reviewed the proposal and concurred with the request for
temporary waiver of dedication of Anderson Street on the condition
that dedication shall occur as stipulated in applicant's letter of
December 3, 1976, at the time of determination of alignment.
ON MOTION BY CROSBY AND SECOND BY PALIN, THE REQUEST FOR DELAY
OF DEDICATION ON TENTATIVE PARCEL MAP NO. 76-58 WAS APPROVED BY
THE FOLLOWING VOTE:
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
SIGN REQUESTS:
SIGN REQUEST NO. 10608
Applicant: World Oil Company
To permit installation of one (1) major identification sign of
40 square feet, two (2) detached price signs of 30 square feet
each, and a trademark logo on a service station building located at
8972 Adams Avenue.
The requested signs were found by the Board to comply with code.
ON MOTION BY PALIN AND SECOND BY CROSBY SIGN REQUEST 170. 10101
WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOWING VOTE:
CONDITIONS OF APPROVAL:
1. The sign plan submitted with the application on December 14,
1976, shall be the approved layout.
BZA 12-15-76 Page 19
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 20
2. The applicant shall comply with all requirements of Article
976 of the Huntington Beach Ordinance Code.
AYES: PALIN, CROSBY SPENCER
NOES: NONE
ABSENT: NONE
SIGN REQUEST NO. 10607
Applicant: World Oil Company
To permit temporary banners, an identification sign, and temporary
price sign for a grand opening event at a service station located
at 8972 Adams Avenue.
The proposed signing was reviewed by the Board.
ON MOTION BY PALIN AND SECOND BY SPENCER SIGN REQUEST NO. 10607
WAS APPROVED WITH THE FOLLOWING CONDITIONS, BY THE FOLLOWING VOTE:
CONDITIONS OF APPROVAL:
1. The sign plan received December 13, 1976, shall be the approved
layout.
2. The applicant shall comply with all requirements of Article 976
of the Huntington Beach Ordinance Code.
3. Said approval shall terminate on January 3, 1977.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
SIGN REQUEST: NO. 10658
Applicant: Home of Pacific Boats
To permit installation of temporary banners for promotional sale
event located at 16401 Beach Boulevard.
The proposed signing was reviewed by the Board.
ON MOTION BY PALIN AND SECOND BY SPENCER SIGN REQUEST NO. 10568
WAS APPROVED WITH THE'FOLLOWING CONDITIONS BY THE FOLLOWING VOTE:
CONDITIONS OF APPROVAL:
1. The sign plan received December 15, 1976, shall be the approved
layout.
2. The applicant shall comply with all requirements of Article
976 of the Huntington Beach Ordinance Code.
BZA 12-15z-65 Page 20
Minutes, H.B. Board of Zoning Adjustments
December 15, 1976
Page 21
3. Said approval shall terminate on January 14, 1977.
AYES: PALIN, CROSBY, SPENCER
NOES: NONE
ABSENT: NONE
THERE BEING NO FURTHER BUSINESS, THE MEETING WAS ADJOURNED.
'Jd es W. Palin, Secretary
Board of Zoning Adjustments
:df
1
7
�J
BZA 12-15-76 Page 21