HomeMy WebLinkAbout1991-10-0911
MINUTES
HUNTINGTON BEACH OFFICE OF ZONING ADMINISTRATOR
Room B-6 - Civic Center
2000 Main Street
Huntington Beach, California
WEDNESDAY, OCTOBER 9, 1991 - 1:30 P.M.
ZONING ADMINISTRATOR: Scott Hess
STAFF MEMBERS:
MINUTES•
REGULAR AGENDA ITEMS:
Mike Connor, Tiffany Allevato
The Minutes of the September 25, 1991
and October 2, 1991 Zoning
Administrator Meetings were approved
with changes.
ITEM 1: COASTAL DEVELOPMENT PERMIT NO, 91-32
Applicant: Howard Stein
3541 Sagamore Drive
Huntington Beach, CA 92649
Request: To permit a 670 square foot second story addition
to an existing two (2) story residence pursuant to
Section 989.5.2 of the Huntington Beach Ordinance
Code.
Location:
3541 Sagamore
Mike Connor, Staff Planner, reported that the proposed addition would
be constructed over the garage. Staff advised that the request meets
Code requirements and would not have an impact on coastal views or
access. Mr. Connor concluded by recommending approval with findings
and suggested conditions of approval.
THE PUBLIC HEARING WAS OPENED.
John Cowles, representing the applicant, was present and provided an
authorization letter from the Homeowners Association.
There were no other persons -present to speak for or against the
request and the public hearing was closed.
COASTAL DEVELOPMENT PERMIT NO. 91-32 WAS APPROVED BY THE ZONING
ADMINISTRATOR WITH THE FOLLOWING FINDINGS AND CONDITIONS OF
APPROVAL. HE STATED THAT ALL ACTIONS TAKEN BY THE ZONING
ADMINISTRATOR CAN BE APPEALED TO THE PLANNING COMMISSION WITHIN TEN
CALENDAR (10) DAYS AND ANOTHER TEN WORKING (10) DAYS TO THE COASTAL
COMMISSION.
FINDINGS FOR APPROVAL/COASTAL DEVELOPMENT PERMIT NO, 91-32:
1. The request to permit the remodel and addition to an existing
two-story single family residence conforms with the plans,
policies, requirements and standards of The Coastal Element of
the General Plan. The proposed addition will have no impact
upon coastal views or access.
2. Coastal Development Permit No. 91-32 is consistent with the CZ
suffix zoning requirements, the R1 Zoning District, as well as
other provisions of the Huntington Beach Ordinance Code
applicable to the property. The proposed addition meets all
aspects of code.
3. At the time of occupancy, the proposed remodel and addition to
an existing two-story single family residence will be provided
with infrastructure in a manner that is consistent with the
Coastal Element of the General Plan. All necessary
infrastructure is currently in place.
4. The proposed remodel and addition to an existing two story
single family residence conforms with the public access and
public recreation policies of Chapter 3 of the California
Coastal Act. The proposed addition will have no impact upon
coastal views or access.
SPECIAL CONDITIONS OF APPROVAL:
1. The site plan, floor plans, and elevations received and dated
September 30, 1991 shall be the conceptually approved layout:
2. The Zoning Administrator shall be notified in writing if any
changes in building height, floor area, setbacks, building
elevations or open space are proposed as a result of the plan
check process. Building permits shall not be issued until the
Zoning Administrator has reviewed and approved the proposed
changes. The Zoning Administrator reserves the right to
require that an amendment to the original entitlement be
processed if the proposed changes are of a substantial nature.
3. All proposed dock and ramp improvements shall require separate
permits for the improvements located within the public
waterways.
4. All proposed cantilevered deck improvements require separate
permits for the improvements.
ZA Minutes - 10/9/91 -2- (1118d)
1
C.
1
5. All building spoils, such as unusable lumber, wire, pipe, and
other surplus or unusable material, shall be disposed of at an
off -site facility equipped to handle them.
6. Proposed structures shall be architecturally compatible with
existing structures.
7. Low -volume heads shall be used on all spigots and water faucets.
INFORMATION ON SPECIFIC CODE REQUIREMENTS:
1. The development shall comply with all applicable provisions of
the Ordinance Code, Building Division, and Fire Department.
2. The applicant shall meet all applicable local, State, and
Federal Fire Codes, Ordinances, and standards.
3. The Zoning Administrator reserves the right to revoke Coastal
Development Permit No. 91-32 if any violation of these
conditions or the Huntington Beach Ordinance Code occurs.
ITEM 2: CONDITIONAL EXCEPTION NO, 91-43
Applicant: Gary M. Peters
3421 Quickstep Circle
Huntington Beach, CA 92649
Request: To permit a remodel and room addition over an
existing garage to an existing two (2) story
residence with an eleven (11) foot front setback
in lieu of fifteen (15) feet as required by
Section 9110.6 of the Huntington Beach Ordinance
Code.
Location:
3421 Quickstep Circle
Mike Connor, Staff Planner, reported that the residence is located in
Huntington Harbor within the coastal zone. The project is
categorically excluded pursuant to Coastal requirements. The
property is located at the end of a cul-de-sac. Staff said only 22
square feet of the addition encroaches into the front setback. In
addition, the building has an average front setback of sixteen (16)
feet. Staff concluded by recommending approval with findings and
suggested conditions of approval due to the minor encroachment and
the location of the property.
THE PUBLIC HEARING WAS OPENED.
Gary Peters, the applicant, was present and concured with staff's
report.
ZA Minutes - 10/9/91
-3-
(1118d)
There were no other persons present and the public hearing was closed.
CONDITIONAL EXCEPTION NO. 91-43 WAS APPROVED BY THE ZONING
ADMINISTRATOR WITH THE FOLLOWING FINDINGS AND CONDITIONS OF
APPROVAL. THE ZONING ADMINISTRATOR STATED THAT ALL ACTIONS TAKEN BY
THE ZONING ADMINISTRATOR CAN BE APPEALED TO THE PLANNING COMMISSION
WITHIN TEN CALENDAR (10) DAYS.
FINDINGS FOR APPROVAL:
1. The establishment, maintenance and operation of the proposed
remodel and addition to an existing Single Family Residence
will not be detrimental to:
a. The general welfare of persons residing or working in the
vicinity; The average front setback is sixteen (16) feet
which exceeds the fifteen (15) foot minimum required by
code.
b. Property and improvements in the vicinity of such use or
building. The average front setback is sixteen (16) feet
which exceeds the fifteen (15) foot minimum required by
code.
2. Because of special circumstances applicable to the subject
property, including size and shape, the strict application of
the Zoning Ordinance is found to deprive the subject property
of privileges enjoyed by other properties in the vicinity and
under identical zone classifications. The parcel is on a
curved cul-de-sac street which causes a curvature of the front
property line. This makes the parcel unique and unlike other
parcels in the vicinity.
3. The granting of Conditional Exception No. 91-43 to permit a
minimum eleven (11) foot front yard setback in lieu of fifteen
(15) feet is necessary in order to preserve the enjoyment of
one or more substantial property rights. The approval of an
eleven (11) foot front setback will provide a sixteen (16)
foot average setback.
4. The granting of Conditional Exception No. 91-43 to permit an
eleven (11) foot front setback in lieu of fifteen (15) feet
will not be materially detrimental to the public welfare, or
injurious to property in the same zone classifications. The
portion of the 2nd story addition which encroaches into the
front setback area is triangular in shape (4' X 111) and is
approximately 22 square feet in size.
5. The granting of Conditional Exception No. 91-43 to
eleven (11) foot front setback in lieu of fifteen
will not adversely affect the General Plan of the
Huntington Beach. The addition to a single family
conforms with the low density residential land use
in the General Plan.
permit an
(15) feet
City of
residence
designation
1
11
ZA Minutes - 10/9/91 -4- (1118d)
6. The applicant is willing and able to carry out the purposes for
which Conditional Exception No. 91-43 is sought and he will
proceed to do so without unnecessary delay.
SPECIAL CONDITIONS OF APPROVAL:
1. The site plan, floor plans, and elevations received and dated
September 9, 1991 shall be the conceptually approved layout.
2 The Zoning Administrator shall be notified in writing if any
changes in building height, floor area, setbacks, building
elevations or open space are proposed as a result of the plan
check process. Building permits shall not be issued until the
Zoning Administrator has reviewed and approved the proposed
changes. The Zoning Administrator reserves the right to
require that an amendment to the original entitlement be
processed if the proposed changes are of a substantial nature.
3. All building spoils, such as unusable lumber, wire, pipe, and
other surplus or unusable material, shall be disposed of at an
off -site facility equipped to handle them.
4. Low -volume heads shall be used on all spigots and water faucets.
5. The proposed addition shall be architecturally compatible with
existing structures.
6. Conditions of approval shall be printed verbatim on all working
drawings submitted for plan check.
INFORMATION ON SPECIFIC CODE REQUIREMENTS:
1. The development shall comply with all applicable provisions of
the Ordinance Code, Building Division, and Fire Department.
2. The applicant shall meet all applicable local, State, and
Federal Fire Codes, Ordinances, and standards.
3. The Zoning Administrator reserves the right to revoke this
Conditional Exception No. 91-43 if any violation of these
conditions of the Huntington Beach Ordinance Code occurs.
ITEM 3: USE PERMIT NO, 91-46
Applicant: Access Controls, Inc.
6312 Santa Ana Canyon Rd., #316
Anaheim, CA 92807
Request: To permit security access gates at an existing
apartment complex.
Location: 16761 Viewpoint Lane (Banbury Cross Apartments)
ZA Minutes - 10/9/91 -5- (1118d)
Tiffany Allevato, Staff Planner, repo
rtehat the request is to
permit security gate access on the non south portions of the
Banbury Cross Apartments. Staff reco that all parking spaces
lost as a result of the gates be repin a one for one basis,
all inoperable vehicles be removates be constructed in
compliance with Fire Department standards and a pedestrian egress
gate be provided on -site. Staff concluded by recommending approval
with findings and suggested conditions of approval.
THE PUBLIC HEARING WAS OPENED.
Geoff Szabo, representing the applicant, advised that there is
adequate parking spaces for all residents and visitors.
Harland Brown, 16761 Viewpoint, said the reason for the gates is for
security and would prefer that visitors park outside to prevent
automobile thefts.
The Zoning Administrator said he would require a call box system to
enable guests to park inside.
There were no other persons present to speak for or against the
request and the public hearing was closed.
CONDITIONAL EXCEPTION NO. 91-46 WAS APPROVED BY THE ZONING
ADMINISTRATOR WITH THE FOLLOWING FINDINGS AND CONDITIONS OF
APPROVAL. THE ZONING ADMINISTRATOR STATED THAT ALL ACTIONS TAKEN BY
THE ZONING ADMINISTRATOR CAN BE APPEALED TO THE PLANNING COMMISSION
WITHIN TEN CALENDAR (10) DAYS.
FINDINGS FOR APPROVAL:
1. The establishment, maintenance and operation of the vehicular
access gates will not be detrimental to:
a. The general welfare of persons residing or working in the
vicinity; the gates will not have an effect on other
residents in the area since parking to be enclosed is
designed and reserved for tenants and guests of Banbury
Cross Apartments.
b. Property and improvements in the vicinity; the gates are
to be located approximately 70 feet from the front
property line and will have no impact upon adjacent
properties.
2. The proposal is consistent with the goals and objectives of
the City's General Plan and Land Use Map. The apartment
complex is consistent with the high density residential land
use designation in the General Plan. The gates will provide
added security for property of residents of Banbury Cross
Apartments.
ZA Minutes - 10/9/91 -6- (1118d)
3. The access to and parking for the proposed vehicular access
gates does not create an undue traffic problem. The gates
will not have an effect on traffic or parking.in the area
since parking to be enclosed is designed and reserved for
tenants and guests of Banbury Cross Apartments.
CONDITIONS OF APPROVAL:
1. The site plan, floor plans, and elevations received and dated
August 28, 1991 shall be the conceptually approved layout.
2. The Zoning Administrator shall be notified in writing if any
changes in height, setbacks, or elevations proposed as a
result of the plan check process. Building permits shall not
be issued until the Zoning Administrator has reviewed and
approved the proposed changes. The Zonifig Administrator
reserves the right to require that an amendment to the
original entitlement be processed if the proposed changes are
of a substantial nature.
3. Prior to issuance of building permits:
A. Any parking spaces lost where gates will be installed
shall be replaced on a one for one basis on site.
B. All abandoned and/or
inoperable
vehicles, as previously
reported by the Code
Enforcement
Staff must be abated
prior to issuance of
permits.
C. Guest spaces shall be
designated
for all parking spaces
outside of the access
gates and
included in submittal of
revised plans.
D. Plans shall be revised to show a call box at the north
gate for guests to contact the residents they are
visiting in order to enter the premises.
4. FIRE DEPARTMENT REQUIREMENTS
A. Installation of the gates shall comply with Fire
Department Standard #403 for Security Gates.
B. Gates shall open to a clear unobstructed width of 26 feet.
5. BUILDING DEPARTMENT REOUIREMENTS:
A. Pedestrian egress gate shall be provided at a location to
be approved by the Building Division.
6. Service roads and fire lanes, as determined by the Fire
Department, shall be posted and marked.
7. Fire access lanes shall be maintained. If fire lane
violations occur and the services of the Fire Department are
required, the applicant will be liable for expenses incurred.
ZA Minutes - 10/9/91 -7- (1118d)
8. There shall be no outside storage of inoperable vehicles,
vehicle parts, equipment or trailers.
9. All building spoils, such as unusable lumber, wire, pipe, and
other surplus or unusable material,- shall be disposed of at
an off -site facility equipped,to handle them.
10. Proper signage shall be implemented at north access gate
designating the parking spaces outside of the access gate as
short term - one hour parking. The limited term parking
shall be enforced by the Banbury Cross Management.
11. The call boa shall have a tenant listing provided with phone
numbers for each unit. Signage shall be provided to assist
visitors in locating the call boa.
12. Conditions of approval shall be printed verbatim on all
working drawings submitted for plan check.
INFORMATION ON SPECIFIC CODE REQUIREMENTS:
1. The development shall comply with all applicable provisions
of the Ordinance Code, Building Division, and Fire Department.
2. The applicant shall meet all applicable local, State, and
Federal Fire Codes, Ordinances, and standards.
3. The applicant shall obtain the necessary permits from the
South Coast Air Quality Management District.
4. Prior to issuance of building permits the applicant shall
re -stripe the parking lot so that it conforms to provisions
of Article 960 of the Huntington Beach Ordinance Code.
ITEM 4• ADMINISTRATIVE REVIEW NO 91-6/USE PERMIT NO, 91-49
NEGATIVE DECLARATION NO, 91-16
Applicant: City of Huntington Beach
2000 Main Street
Huntington Beach, CA 92648
Request: Administrative Review: to review in concept, for
recommendation to the Coastal Commission, a two phased
development proposal:
Phase I - to fill the site with approximately 23,500
cubic yards of dirt for future development of a Beach
Maintenance Facility.
Phase II - to construct a 15,000 square foot Beach
Maintenance Facility which includes regarding the site
to meet National Flood Insurance Program requirements
of elevating new structures above the base flood
elevation.
ZA Minutes - 10/9/91 -8- (1118d)
Use Permit: This request includes an eight (8) foot,
six (6) inch high retaining wall to be constructed
along the west and south property lines and a vehicle
access ramp from Edison Avenue to the facility.
Location: 8660 Edison Avenue
Mike Connor, Staff Planner, reported that the plans conform to Code
requirements. Staff concluded by recommending that the project be
approved in concept and forwarded to the Coastal Commission.
THE PUBLIC HEARING WAS OPENED.
No one was present to speak for or against the request and the
public hearing was closed.
ADMINISTRATIVE REVIEW NO. 91-16/USE PERMIT NO. 91-49/NEGATIVE
DECLARATION NO. 91-16 WAS "APPROVED IN CONCEPT" BY THE ZONING
ADMINISTRATOR WITH THE FOLLOWING FINDINGS AND CONDITIONS OF
APPROVAL. THE ZONING ADMINISTRATOR STATED THAT ALL ACTIONS TAKEN BY
THE ZONING ADMINISTRATOR CAN BE APPEALED TO THE PLANNING COMMISSION
WITHIN TEN CALENDAR (10) DAYS.
FINDINGS FOR "APPROVAL IN CONCEPT"/ADMINISTRATIVE REVIEW NO, 91-6:
1. The establishment, maintenance and operation of the Beach
Maintenance Facility (Phase I & II) will not be detrimental to:
a. The general welfare of persons residing or working in the
vicinity; The Beach Maintenance Facility will be located
adjacent to a tank storage yard , a flood control channel,
and a wholesale nursery. No detrimental impacts are
anticipated.
b. Property and improvements in the vicinity of such use or
building. The Beach Maintenance Facility will be located
adjacent to a tank storage yard, a flood control channel,
and a wholesale nursery. No detrimental impacts are
anticipated.
2. The proposal is consistent with the goals and objectives of the
City's General Plan and Land Use Map. The Beach Maintenance
Facility is a permitted use within the General Industrial Land
Use Designation in the General Plan.
FINDINGS FOR "APPROVAL IN CONCEPT"/USE PERMIT NO, 91-49:
1. The establishment, and maintenance of the eight (8) foot, six
(6) inch high retaining wall will not be detrimental to:
a. The general welfare of persons residing or working in the
vicinity; The retaining wall will be located adjacent to a
tank storage yard and a wholesale nursery. No detrimental
impacts are anticipated.
ZA Minutes - 10/9/91 -9- (1118d)
b. Property and improvements in the vicinity of such use or
building. The retaining wall will be located adjacent to a
tank storage yard and a wholesale nursery. No detrimental
impacts are anticipated._
2. The proposal is consistent with the goals and objectives of the
City's General Plan and Land Use Map. The retaining wall is an
accessory structure to the Beach Maintenance Facility which is
a permitted use within the General Industrial Land Use
Designation in the General Plan.
CONDITIONS OF APPROVAL/ADMINISTRATIVE REVIEW NO 91-6 & USE PERMIT
N0, 91-49:
1. The site plan, floor plans, and elevations received and dated
October 1, 1991 shall be the conceptually approved layout.
2 The Zoning Administrator shall be notified in writing if any
changes in building height, floor area, setbacks, building
elevations or open space are proposed as a result of the plan
check process. Building permits shall not be issued until the
Zoning Administrator has reviewed and approved the proposed
changes. The Zoning Administrator reserves the right to
require that an amendment to the original entitlement be
processed if the proposed changes are of a substantial nature.
3. Prior to issuance of building permits, the following plans and
items shall be submitted and/or completed by the applicant:
a. Rooftop Mechanical Equipment Plan. Said plan shall
indicate screening of all rooftop mechanical equipment and
shall delineate the type of material proposed to screen
said equipment.
b. A Landscape Construction Set submitted to the Departments
of Community Development and Public Works. The landscape
construction set shall include a landscape plan prepared
and signed by a State Licensed Landscape Architect which
includes all proposed/existing plant materials (location,
type, size, quantity), irrigation plan, grading plan and
approved site plan, and copy of conditions of approval.
The landscape plan shall be in conformance with Section
9608 and 9550.13 of the Huntington Beach Ordinance Code .
The set must be complete and approved by both departments
prior to issuance of building permits. A minimum of eight
(8) percent of the site shall be landscaped.
c. The retaining wall and perimeter fencing shall be reviewed
by the Planning Division for materials, colors and
elevations.
4. Fire Department requirements shall be as follows:
1
:l
ZA Minutes - 10/9/91 -10- (1118d)
a. Automatic sprinkler systems will be installed throughout to
comply with Huntington Beach Fire Department and Uniform
Building Code Standards. Shop drawings will be submitted
to and approved by the Fire Department prior to
installation.
b. A fire alarm system will be installed to comply with
Huntington Beach Fire Department and Uniform Fire Code
Standards. Shop drawings will be submitted to and approved
by the Fire Department prior to installation. The system
will provide the following:
1. Water flow, valve tamper and trouble detection
2. 24 hour supervision
d. Fire extinguishers will be installed and located in areas
to comply with Huntington Beach Fire Code Standards.
e. Three fire hydrants will be installed prior to combustible
construction. Shop drawings will be submitted to the
Public Works Department an approved by the Fire Department
prior to installation.
f. Fire lanes will be designated and posted to comply with
City Specification #415.
g. Security gates will be designed to comply with City
Specification #403.
h. Address numbers will be installed to comply with City
Specification #428. The size of the numbers will be the
following:
1. The number for the building will be sized a minimum of
ten (10) inches with a brush stroke of one and one-half
(1 1/2) inches.
i. Installation or removal of underground flammable or
combustible liquid storage tanks will comply with Orange
County Environmental Health and Huntington Beach Fire
Department requirements.
j. Fire access roads will be provided in compliance with the
Huntington Beach Fire Code and City Specification #401.
Include the circulation plan and dimensions of all access
roads (24' or 27' fire lanes, turnarounds and 17' by 45'
radius turns.) Attached is City Specification #401.
k. The project will comply with all provisions of Huntington
Beach Municipal Code Title 17.04.085 and City Specification
#429 for new construction within the methane gas overlay
districts.
ZA Minutes - 10/9/91
-11-
(1118d)
1. Fire Department access around complete building shall be
provided by gate(s) at fences separating the main building
and the portion to be leased.
5. All building spoils, such as unusable lumber, wire, pipe, and
other surplus or unusable material, shall be disposed of at an
off -site facility equipped to handle them.
6. Low -volume heads shall be used on all spigots and water faucets.
7. If lighting is included in the parking lot, high-pressure
sodium vapor lamps shall be used for energy savings. All
outside lighting shall be directed to prevent "spillage" onto
adjacent properties.
8. Conditions of approval shall be printed verbatim on all working
drawings submitted for plan check.
9. This Administrative Review No. 91-6 and Use Permit No. 91-49
shall not become effective until and unless this project is
approved by the California Coastal Commission.
INFORMATION ON SPECIFIC CODE REQUIREMENTS:
1. The development shall comply with all applicable provisions of
the Ordinance Code, Building Division, and Fire Department.
2. The applicant shall meet all applicable local, State, and
Federal Fire Codes, Ordinances, and standards.
3. The applicant shall obtain the necessary permits from the South
Coast Air Quality Management District.
4. Development shall meet all local and State regulations
regarding installation and operation of all underground storage
tanks.
5. A detailed soils analysis shall be prepared by a registered
Soils Engineer. This analysis shall include on -site soil
sampling and laboratory testing of materials to provide
detailed recommendations regarding grading, chemical and fill
properties, foundations, retaining walls, streets, and
utilities.
THE MEETING WAS ADJOURNED AT 2:00 PM BY THE ZONING ADMINISTRATOR TO
A STUDY SESSION ON MONDAY, OCTOBER 14, 1991 AT 4:00 PM AND THEN TO
THE NEXT REGULARLY SCHEDULED MEETING OF THE ZONING ADMINISTRATOR ON
WEDNESDAY, OCTOBER 16, 1991, AT 1:30 PM.
Scott Hess
Zoning Administrator
:jr
ZA Minutes - 10/9/91 -12- (1118d)