HomeMy WebLinkAboutCity Council - 2007-76 RESOLUTION NO. 2007-76
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF HUNTINGTON BEACH
AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE PROGRAM
SUPPLEMENT NO. N036 TO MASTER AGREEMENT NO. 12-5181R FOR
BROOKHURST STREET MEDIAN LANDSCAPE ENHANCEMENT
WHEREAS, on November 20, 2006, the City entered into an agreement with the State of
California for the Federal Aid Program, identified as Agreement No. 12-5181 R; and
Program Supplement No. N036 to the above mentioned Master Agreement requires
median landscape improvements; and
The estimated project cost for this agreement is as follows: N036 (Brookhurst Street
Median Landscape Enhancement) $1,141,230; and
From the estimated project cost,the following dollar amount will be appropriated from
Federal and State funds to the project as shown on Attachment A hereto: N036 (Brookhurst
Street Median Landscape Enhancement) $370,000; and
NOW, THEREFORE,the City Council of the City of Huntington Beach does hereby
resolve as follows:
1. That the Mayor and City Clerk are authorized and directed to execute the
necessary documents to implement Program Supplement No.N036 to Master Agreement No. 12-
5181R for the Brookhurst Street Median Landscape Enhancement.
PASSED AND ADOPTED by the City Council of the City of Huntington Beach at a
regular meeting thereof held on November 19 , 2007.
AZAB
Ma or
APPROVED AS TO FORM:
Attorney If
�v�3v ��- 1a �30/0�
REVIEWED AND APPROVED. INITIATED AND APPROVED:
-
C ky Admi istrator Acting Director of Public Works
15319
(PROGRAM SUPPLEMENT NO. N036 Date:September 24,2007
to Location:12-ORA-0-HNTB
ADMINISTERING AGENCY-STATE AGREEMENT Project Number:RPSTPLE-5181(160)
FOR FEDERAL-AID PROJECTS NO. 12-5181R E.A. Number:12-402564
This Program Supplement hereby incorporates the Administering Agency-State Agreement for Federal Aid which was entered into
between the Administering Agency and the State on 12/06/06 and is subject to all the terms and conditions thereof.This Program
Supplement is executed in accordance with Article I of the aforementioned Master Agreement under authority of Resolution No.
2007-76 ,approved by the Administering Agency on 11/19/2007 (See copy attached).
The Administering Agency further stipulates that as a condition to the payment by State of any funds derived from sources noted
below obligated to this project,the Administering Agency accepts and will comply with the Special covenants or Remarks setforth
on the following pages.
PROJECT LOCATION:
Brookhurst Street from Kamuela Drive to Cutty Sark Drive and Yorktown Avenue from Brookhurst Street to 600 feet east
TYPE OF WORK: Median landscaping and concrete block walls LENGTH: 0.5(MILES)
Estimated Cost Federal Funds Matching Funds
H220 $370,000.00 LOCAL OTHER
$1,141,230.00 $771,230.00 $0.00 $0.00
CITY OF HUNTINGTON BEACH STATE OF CALIFORNIA
Department f Transportaftion
o
By By
Gil Coerper, MaAy4L,
5 Chief, office of Project Implementation
Date November 26 2007 Division of Local Assistance
Attest pp^^ II
o i n ugar ' Date f Liz �, �
Title Acci�ttapt Oi y�l�L
I hereby certify upon m4perso al knowledge that budgeted funds are available for this encumbrance:
Accounting Officer Date $370,000.00
Chapter Statutes Item Year BC Category Fund Source AMOUNT
171 2007 2660-101-890 2007-2008 20.30.600.731 S 228010 892-F 370,000.00
Program Supplement 12-5181R-N036- ISTEA Page 1 of 4
.12-ORA-0-HNTB 09/24/2007
kPSTPLE-5181(160)
SPECIAL COVENANTS OR REMARKS
1. Award information shall be submitted by the ADMINISTERING AGENCY
to the District Local Assistance Engineer within 60 days after
the project contract award. A copy of the award package shall
also be included with the submittal of the ADMINISTERING AGENCY's
first invoice for the construction contract to:
Department of Transportation
Division of Accounting
Local Programs Accounting Branch, MS #33
P. O. Box 942874
Sacramento, CA 94274-000.1.
Failure to do so will cause a delay in the State processing
invoices for the construction phase. Please refer to Section
.15.7 "Award Package" of the Local Assistance Procedures Manual.
2. ADMINISTERING AGENCY agrees that it will only proceed with work
authorized for specific phase(s) with an "Authorization to
Proceed" and will not proceed with future phase(s) of this
project prior to receiving an "Authorization to Proceed" from the
STATE for that phase(s) unless no further State or Federal funds
are needed for those future phase(s) .
3. Any State and Federal funds that may have been encumbered for
this project are only available for disbursement for a period of
five (5) years and seven' (7) years, respectively, from the start
of the fiscal year(s) that those funds were appropriated within
the State Budget Act. All project funds not liquidated within
these periods will revert unless an executed Cooperative Work
Agreement extending these dates is requested and is approved by
the -California Department of Finance per Government Code Section
16304. The exact date of each fund reversion will be reflected
in the approved finance letter(s) issued for this project.
Notwithstanding the unliquidated sums of project specific State
and Federal funding remaining and available to fund project work,
any invoice for reimbursement that is not submitted to the
Department on or before 60 days after that applicable fixed fund
reversion date will not be paid from that fiscal year' s
encumbered funds because all of these unexpended funds will be
irrevocably reverted by the Department ' s Division of Accounting
on that date.
Program Supplement 12-5181R-N036- ISTEA Page 2 of 4
,72=ORA-0-HNTB 09/24/2007
RPSTPLE-5181(160)
SPECIAL COVENANTS OR REMARKS
Pursuant to a directive from the State Controller' s Office and
the Department of Finance, the last date to submit invoices for
reimbursed work in each fiscal year is May 15th in order for
payment to be made out of those then current appropriations.
Project work performed and invoiced after May 15th will be
reimbursed only out of available funding that might be encumbered
in the subsequent fiscal year, and then only when those funds are
actually allocated and encumbered as authorized by the California
Transportation Commission and the Department 's Accounting Office.
4. ADMINISTERING AGENCY agrees, as a minimum, to submit .invoices at
least once every six months commencing after the funds are
encumbered for each phase by the execution of this Project
Program Supplement Agreement, or by STATE' s approval of an
applicable Finance Letter. STATE reserves the right to suspend
future authorizations/obligations, and invoice payments for any
on-going or future federal-aid project by. ADMINISTERING AGENCY if
PROJECT costs have not been invoiced by ADMINISTERING AGENCY for
a six-month period.
If no costs have been invoiced for a six-month period,
ADMINISTERING AGENCY agrees to submit for each phase a written
explanation of the absence of PROJECT activity along with target
billing date and target billing amount.
ADMINISTERING AGENCY agrees to submit the final. report documents
that collectively constitute a "Report of Expenditures" within
one hundred eighty (180) days of PROJECT completion. Failure of
ADMINISTERING AGENCY to submit a "Final Report of Expenditures"
within 180 days of PROJECT completion will result in STATE
imposing sanctions upon ADMINISTERING AGENCY in accordance with
the current Local Assistance Procedures Manual.
5. This PROJECT is subject to the timely use of funds provisions
enacted by Senate Bill 45 (SB 45) , approved in 1997, and
subsequent CTC guidelines and State procedures approved by the
CTC and STATE, as outlined below:
Funds allocated for the environmental & permits, plan
specifications & estimate, and right-of-way components are
available for expenditure until the end of :the second fiscal year
Program Supplement 12-5181R-N036- ISTEA Page 3 of 4
'12-0RA-O-HNTB 09/24/2007
19PSTPLE-5181(160)
SPECIAL COVENANTS OR REMARKS
following the year in which the funds were allocated.
Funds allocated for the construction component are subject to an
award deadline and contract completion deadline. ADMINISTERING
AGENCY agrees to award the contract within 6 months of the
construction fund allocation and complete the construction or
vehicle purchase contract within 36 .months of award.
6. This PROJECT is programmed to receive Federal Transportation
Enhancement Activities (TEA) fund. The ADMINISTERING AGENCY
agrees that any functional or operational change to a TEA
PROJECT, before, during or after PROJECT acquisition and/or
construction, that does not comply with, or is in conflict with,
the TEA program requirements and the original purpose of the
Project at .the time it was programmed may render the PROJECT
ineligible for Federal reimbursement and ADMINISTERING AGENCY may
be required to reimburse STATE the entire amount of TEA funds
contributed to the project or the value of the TEA fund
contribution, based upon the fair market value of the acquisition
and/or construction, at the time the conflict and/or
non-compliance is determined, whichever is greater.
7. The ADMINISTERING AGENCY will advertise, award and administer
this project in accordance with the current published Local
Assistance Procedures Manual.
Program Supplement 12-5181R-N036- ISTEA Page 4 of 4
Res.. No. 2007-76
STATE OF CALIFORNIA
COUNTY OF ORANGE ) ss:
CITY OF HUNTINGTON BEACH )
I, JOAN L. FLYNN the duly elected, qualified City Clerk of the City of
Huntington Beach, and ex-officio Clerk of the City Council of said City, do hereby
certify that the whole number of members of the City Council of the City of
Huntington Beach is seven; that the foregoing resolution was passed and adopted
by the affirmative vote of at least a majority of all the members of said City Council
at a regular meeting thereof held on November 19, 2007 by the following vote:
AYES: Bohr, Carchio, Coerper, Green, Hansen, Hardy
NOES: None
ABSENT: Cook
ABSTAIN: None
Jilt
Clerk and ex-offici Clerk of the
City Council of the City of
Huntington Beach, California