HomeMy WebLinkAboutAnchor QEA, LLC - 2015-07-20&-n r
Dept ID PW 15-032 Page 1 of 2
Meeting Date 7/20/2015
CITY OF HUNTINGTON BEACH
REQUEST FOR CITY COUNCIL ACTION
MEETING DATE: 7/20/2015
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Fred A Wilson, City Manager
PREPARED BY: Travis K Hopkins, PE, Director of Public Works
SUBJECT: Approve and authorize execution of three Professional Services Contracts for
On -Call Civil (Ocean) Engineering Services with Anchor QEA, LLC , Moffatt &
Nichol, and Noble Consultants, Inc, each in the amount of $350,000
Statement of Issue
The Public Works Department requires professional civil engineering services on an on -call or as
needed basis to support staff for the design and construction of the capital improvement projects
related to ocean engineering services
Financial Impact
The City's FY 2014/15 Capital Improvement Program (CIP) Budget was adopted on September 2,
2014 and totals $42 8 million (All Funds) for approved projects citywide Each approved CIP
project has a budget containing sufficient funding for design, environmental, engineering,
construction, project management and other required costs The three (3) recommended civil
engineering contracts, totaling $1 05 million, will be funded within each project's individual CIP
budget, as needed As such, no additional funding is required by this action
Recommended Action
A) Approve and authorize the Mayor and City Clerk to execute "Professional Services Contract
Between The City of Huntington Beach and Anchor QEA, LLC for On -Call Civil Engineering
Services" in the amount of $350,000, and,
B) Approve and authorize the Mayor and City Clerk to execute "Professional Services Contract
Between The City of Huntington Beach and Moffatt & Nichol for On -Call Civil Engineering Services"
in the amount of $350,000, and,
S C) Approve and authorize the Mayor and City Clerk to execute "Professional Services Contract
Between The City of Huntington Beach and Noble Consultants, Inc for On -Call Civil Engineering
Services" in the amount of $350,000
Alternative Action(s)
Do not authorize the contracts and direct staff with an alternate action Budgeted Capital Projects
could be delayed until new contracts are approved
Analysis
On January 26, 2015 the City advertised a Request for Qualifications ("RFQ") for On -Call
Engineering & Professional Consulting Services Proposals were requested and submitted in
compliance with Chapter 3 03 of the Huntington Beach Municipal Code Seventy eight (78)
HB -167- Item 11. - 1
Dept ID PW 15-032 Page 2 of 2
Meeting Date 7/20/2015
proposals were received for the following eight categories of Civil Engineering services, Water
Engineering, Development Plan Checking and Entitlement Review Services, Civil/Sewer
Engineering, Geotechnical and Materials Testing, Traffic Engineering, Survey, Ocean Engineering,
and Architectural Services In accordance with qualifications based selected procurement per the
Federal "Brooks Act", State SB 419 and the City of Huntington Beach Municipal Code Section 3 03
"Professional Services" the Public Works Department established a review board Each firm stated
their engineering category of expertise with their proposal, and proposals were then evaluated and
ranked by eight (8) review boards established by the Public Works Department At a minimum the
top three (3) firms were selected for each category to increase opportunity for competitive
proposals for future projects from qualified on -call consultants
The three (3) contracts recommended in this request for council action (RCA) are for support staff
for the design and construction of the capital improvement projects related to coastal features such
as beaches and sea walls These services have historically been utilized to supplement City staff to
meet annual CIP goals, as an extension of staff and/or to provide required expertise for unique
projects It is anticipated that these services will be required based on past years Each project is
evaluated on a case by case basis to determine if these as -needed contract services are
necessary Other categories and groupings of On -Call consulting services will be brought to the
City Council separately for approval
The City's Capital Improvement Program ("CIP") is approximately $42 8 million in Fiscal Year
2014/15, and exceeds $52 million with continuing of funds for projects approved from previous
years Typical design and construction support cost from use of consultants on a CIP project can
vary between ten (10) to twenty (20) percent of total costs for a CIP project Therefore, it is
practical to conservatively assume minimum annual consultant costs would be around $5 million to
the City for total CIP projects, or approximately $15 million over the next three (3) years
Some of the typical projects for ocean on -call design services include,
• Bluff top erosion and stabilization
• City Beach and harbor beaches sand replenishment
• Harbor Dredging analysis and general support
• Coastal Commission expertise
• Pier design and maintenance
With the City bordered by the Pacific Ocean, local residents and tourists are drawn to the beaches
during all seasons The City is responsible for the preservation and enhancement of our existing
beaches to continue beneficial use by the public This preservation work is a joint effort between
the County of Orange and all coastal cities and is a specialty service Therefore, three (3)
consultants were selected to meet projected workload over the next 3 years The anticipated need
for ocean engineering services is $1,050,000 over the term of the contract, or an annual average of
$350,000
Public Works Commission Action: Not required
Environmental Status Not applicable
Strategic Plan Goal Enhance and maintain infrastructure
ment s
rofessiona Services Contract between the City of Huntington Beach and Anchor QEA,
LLC for On -Call Civil Engineering Services
2 Professional Services Contract between the City of Huntington Beach and Moffatt & Nichol
Sao
s e3 Professional Services Contract between the City of Huntington Beach and Noble
0 Consultants, Inc for On -Call Civil Engineering Services
Item 11. - 2 xB -168-
PROFESSIONAL SERVICES CONTRACT BETWEEN
THE CITY OF HUNTINGTON BEACH AND
ANCHOR QEA, LLC
FOR
ON CALL CIVIL ENGINEERING SERVICES
THIS AGREEMENT ("Agreement") is made and entered into by and between the City of
Huntington Beach, a municipal corporation of the State of California, hereinafter referred to as
"CITY," and Anchor QEA, LLC, a California Limited Liability Partnership, hereinafter referred to
as "CONSULTANT "
WHEREAS, CITY desires to engage the services of a consultant to provide on call civil
engineering services, and
Pursuant to documentation on file in the office of the City Clerk, the provisions of the
Huntington Beach Municipal Code, Chapter 3 03, relating to procurement of professional service
contracts have been complied with, and
CONSULTANT has been selected to perform these services,
NOW, THEREFORE, it is agreed by CITY and CONSULTANT as follows
1 SCOPE OF SERVICES
CONSULTANT shall provide all services as described in Exhibit "A," which is
attached hereto and incorporated into this Agreement by this reference These services shall
sometimes hereinafter be referred to as the "PROJECT "
CONSULTANT hereby designates Randy Mason, who shall represent it and be its
sole contact and agent in all consultations with CITY during the performance of this Agreement
2 CITY STAFF ASSISTANCE
CITY shall assign a staff coordinator to work directly with CONSULTANT in the
performance of this Agreement
agree/ surfnet/professional sves mayor I of 11
10/12
3 TERM, TIME OF PERFORMANCE
Time is of the essence of this Agreement The services of CONSULTANT are to
commence on !GLL_,y /� 20 �� (the "Commencement Date") This Agreement
shall automatically terminate three (3) years from the Commencement Date, unless extended or
sooner terminated as provided herein All tasks specified in Exhibit "A" shall be completed no
later than three (3) years from the Commencement Date The time for performance of the tasks
identified in Exhibit "A" are generally to be shown in Exhibit "A." This schedule may be
amended to benefit the PROJECT if mutually agreed to in writing by CITY and CONSULTANT
In the event the Commencement Date precedes the Effective Date, CONSULTANT
shall be bound by all terms and conditions as provided herein.
4. COMPENSATION
In consideration of the performance of the services described herein, CITY agrees to
pay CONSULTANT on a time and materials basis at the rates specified in Exhibit "B," which is
attached hereto and incorporated by reference into this Agreement, a fee, including all costs and
expenses, not to exceed Three Hundred and Fifty Thousand Dollars ($ 350,000 )
5 EXTRA WORK
In the event CITY requires additional services not included in Exhibit "A" or
changes in the scope of services described in Exhibit "A," CONSULTANT will undertake such
work only after receiving written authorization from CITY Additional compensation for such extra
work shall be allowed only if the prior written approval of CITY is obtained
6. METHOD OF PAYMENT
CONSULTANT shall be paid pursuant to the terms of Exhibit "B."
agree/ surfnet/professional svcs mayor 2 of 11
10/12
7 DISPOSITION OF PLANS, ESTIMATES AND OTHER DOCUMENTS
CONSULTANT agrees that title to all materials prepared hereunder, including,
without limitation, all original drawings, designs, reports, both field and office notices, calculations,
computer code, language, data or programs, maps, memoranda, letters and other documents, shall
belong to CITY, and CONSULTANT shall turn these materials over to CITY upon expiration or
termination of this Agreement or upon PROJECT completion, whichever shall occur first These
materials may be used by CITY as it sees fit
8 HOLD HARMLESS
CONSULTANT hereby agrees to protect, defend, indemnify and hold harmless
CITY, its officers, elected or appointed officials, employees, agents and volunteers from and against
any and all claims, damages, losses, expenses, judgments, demands and defense costs (including,
without limitation, costs and fees of litigation of every nature or liability of any kind or nature)
ansmg out of or in connection with CONSULTANT's (or CONSULTANT's subcontractors, if any)
negligent (or alleged negligent) performance of tlus Agreement or its failure to comply with any of
its obligations contained in this Agreement by CONSULTANT, its officers, agents or employees
except such loss or damage which was caused by the sole negligence or willful misconduct of
CITY CONSULTANT will conduct all defense at its sole cost and expense and CITY shall
approve selection of CONSULTANT's counsel This indemnity shall apply to all claims and
liability regardless of whether any insurance policies are applicable The policy limits do not act as
limitation upon the amount of indemnification to be provided by CONSULTANT
9 PROFESSIONAL LIABILITY INSURANCE
CONSULTANT shall obtain and furnish to CITY a professional liability insurance
policy covering the work performed by it hereunder This policy shall provide coverage for
CONSULTANT's professional liability in an amount not less than One Million Dollars
agree/ surfaet/professional secs mayor 3 of 11
10/12
($1,000,000 00) per occurrence and in the aggregate The above -mentioned insurance shall not
contain a self -insured retention without the express written consent of CITY, however an insurance
policy "deductible" of Ten Thousand Dollars ($10,000 00) or less is permitted A claims -made
policy shall be acceptable if the policy further provides that
A The policy retroactive date coincides with or precedes the initiation of the
scope of work (including subsequent policies purchased as renewals or
replacements)
B CONSULTANT shall notify CITY of circumstances or incidents that might
give rise to future claims
CONSULTANT will make every effort to maintain similar insurance during the
required extended period of coverage following PROJECT completion If insurance is terminated
for any reason, CONSULTANT agrees to purchase an extended reporting provision of at least two
(2) years to report claims ansing from work performed in connection with this Agreement
If CONSULTANT fails or refuses to produce or maintain the insurance required by
this section or fails or refuses to furnish the CITY with required proof that insurance has been
procured and is in force and paid for, the CITY shall have the right, at the CITY's election, to
forthwith terminate this Agreement Such termination shall not effect Consultant's right to be paid
for its time and materials expended prior to notification of termination CONSULTANT waives the
right to receive compensation and agrees to indemnify the CITY for any work performed prior to
approval of insurance by the CITY
10 CERTIFICATE OF INSURANCE
Prior to commencing performance of the work hereunder, CONSULTANT shall
furnish to CITY a certificate of insurance subject to approval of the City Attorney evidencing the
foregoing insurance coverage as required by this Agreement, the certificate shall
agree/ sur&iet/professional svcs mayor 4 of 11
10/12
A provide the name and policy number of each carrier and policy,
B state that the policy is currently in force, and
C shall promise that such policy shall not be suspended, voided or canceled by
either party, reduced in coverage or in limits except after thirty (30) days'
prior written notice, however, ten (10) days' prior written notice in the event
of cancellation for nonpayment of premium
CONSULTANT shall maintain the foregoing insurance coverage in force until the
work under this Agreement is fully completed and accepted by CITY
The requirement for carrying the foregoing insurance coverage shall not derogate
from CONSULTANT's defense, hold harmless and mdemmfication obligations as set forth in this
Agreement CITY or its representative shall at all tines have the right to demand the original or a
copy of the policy of insurance CONSULTANT shall pay, in a prompt and timely manner, the
premiums on the insurance hereinabove required
11 INDEPENDENT CONTRACTOR
CONSULTANT is, and shall be, acting at all tunes in the performance of this
Agreement as an independent contractor herein and not as an employee of CITY CONSULTANT
shall secure at its own cost and expense, and be responsible for any and all payment of all taxes,
social security, state disability insurance compensation, unemployment compensation and other
payroll deductions for CONSULTANT and its officers, agents and employees and all business
licenses, if any, in connection with the PROJECT and/or the services to be performed hereunder
12 TERMINATION OF AGREEMENT
All work required hereunder shall be performed in a good and workmanlike manner
CITY may terminate CONSULTANT's services hereunder at any time with or without cause, and
whether or not the PROJECT is fully complete Any termination of this Agreement by CITY shall
agree/ surfnet/professional svcs mayor 5 of 11
10/12
be made in writing, notice of which shall be delivered to CONSULTANT as provided herein In the
event of termination, all finished and unfinished documents, exhibits, report, and evidence shall, at
the option of CITY, become its property and shall be promptly delivered to it by CONSULTANT
13 ASSIGNMENT AND DELEGATION
This Agreement is a personal service contract and the work hereunder shall not be
assigned, delegated or subcontracted by CONSULTANT to any other person or entity without the
prior express written consent of CITY If an assignment, delegation or subcontract is approved, all
approved assignees, delegates and subconsultants must satisfy the insurance requirements as set
forth in Sections 9 and 10 heremabove
14 COPYRIGHTS/PATENTS
CITY shall own all rights to any patent or copyright on any work, item or material
produced as a result of this Agreement
15 CITY EMPLOYEES AND OFFICIALS
CONSULTANT shall employ no CITY official nor any regular CITY employee in
the work performed pursuant to this Agreement No officer or employee of CITY shall have any
financial interest in this Agreement in violation of the applicable provisions of the California
Government Code
16 NOTICES
Any notices, certificates, or other communications hereunder shall be given either by
personal delivery to CONSULTANT's agent (as designated in Section 1 heremabove) or to CITY as
the situation shall warrant, or by enclosing the same in a sealed envelope, postage prepaid, and
depositing the same in the United States Postal Service, to the addresses specified below CITY and
CONSULTANT may designate different addresses to which subsequent notices, certificates or
agree/ surfiiet/professional svcs mayor 6 of 11
10/12
other communications will be sent by notifying the other party via personal delivery, a reputable
overnight carrier or U S certified mail -return receipt requested
TO CITY
City of Huntington Beach
ATTN Tom Herbel
2000 Main Street
Huntington Beach, CA 92648
17 CONSENT
TO CONSULTANT
Anchor QEA, LLC
Attn Randy Mason, P E
7755 Center Avenue, Suite 1060
Huntington Beach, CA 92647
When CITY's consent/approval is required under this Agreement, its
consent/approval for one transaction or event shall not be deemed to be a consent/approval to any
subsequent occurrence of the same or any other transaction or event
18. MODIFICATION
No waiver or modification of any language in this Agreement shall be valid unless in
writing and duly executed by both parties
19 SECTION HEADINGS
The titles, captions, section, paragraph and subject headings, and descriptive phrases
at the beginning of the various sections in this Agreement are merely descriptive and are included
solely for convenience of reference only and are not representative of matters included or excluded
from such provisions, and do not interpret, define, limit or describe, or construe the intent of the
parties or affect the construction or interpretation of any provision of this Agreement
20 INTERPRETATION OF THIS AGREEMENT
The language of all parts of this Agreement shall in all cases be construed as a
whole, according to its fair meaning, and not strictly for or against any of the parties If any
provision of this Agreement is held by an arbitrator or court of competent jurisdiction to be
unenforceable, void, illegal or invalid, such holding shall not invalidate or affect the remaining
agree/ surfnet/professional svcs mayor 7 of 11
10/12
covenants and provisions of this Agreement No covenant or provision shall be deemed dependent
upon any other unless so expressly provided here As used in this Agreement, the masculine or
neuter gender and singular or plural number shall be deemed to include the other whenever the
context so indicates or requires Nothing contained herein shall be construed so as to require the
commission of any act contrary to law, and wherever there is any conflict between any provision
contained herein and any present or future statute, law, ordinance or regulation contrary to which
the parties have no right to contract, then the latter shall prevail, and the provision of this
Agreement which is hereby affected shall be curtailed and limited only to the extent necessary to
bring it within the requirements of the law
21 DUPLICATE ORIGINAL
The original of this Agreement and one or more copies hereto have been prepared
and signed in counterparts as duplicate originals, each of which so executed shall, irrespective of the
date of its execution and delivery, be deemed an original Each duplicate original shall be deemed
an original instrument as against any party who has signed it
22 IMMIGRATION
CONSULTANT shall be responsible for full compliance with the immigration and
naturalization laws of the United States and shall, in particular, comply with the provisions of the
United States Code regarding employment verification
23 LEGAL SERVICES SUBCONTRACTING PROHIBITED
CONSULTANT and CITY agree that CITY is not liable for payment of any
subcontractor work involving legal services, and that such legal services are expressly outside the
scope of services contemplated hereunder CONSULTANT understands that pursuant to
Huntington Beach City Charter Section 309, the City Attorney is the exclusive legal counsel for
agree/ surfneVprofessional svcs mayor 8 of 11
10/12
CITY, and CITY shall not be liable for payment of any legal services expenses incurred by
CONSULTANT
24 ATTORNEY' S FEES
In the event suit is brought by either party to construe, interpret and/or enforce the
terms and/or provisions of this Agreement or to secure the performance hereof, each party shall bear
its own attorney's fees, such that the prevailing party shall not be entitled to recover its attorneys
fees from the nonprevailing parry
25 SURVIVAL
Terms and conditions of this Agreement, which by their sense and context survive
the expiration or termination of this Agreement, shall so survive
26 GOVERNING LAW
This Agreement shall be governed and construed in accordance with the laws of the
State of California
27 SIGNATORIES
Each undersigned represents and warrants that its signature herembelow has the
power, authority and right to bind their respective parties to each of the terms of this Agreement,
and shall indemnify CITY fully for any injuries or damages to CITY in the event that such authority
or power is not, in fact, held by the signatory or is withdrawn
28 ENTIRETY
The parties acknowledge and agree that they are entering into this Agreement freely
and voluntarily following extensive arm's length negotiation, and that each has had the opportunity
to consult with legal counsel prior to executing this Agreement The parties also acknowledge and
agree that no representations, inducements, promises, agreements or warranties, oral or otherwise,
have been made by that party or anyone acting on that party's behalf, which are not embodied in this
agree/ surfnet/professional svcs mayor 9 of 11
10/12
Agreement, and that that party has not executed this Agreement in reliance on any representation,
inducement, promise, agreement, warranty, fact or circumstance not expressly set forth in this
Agreement This Agreement, and the attached exhibits, contain the entire agreement between the
parties respecting the subject matter of this Agreement, and supersede all prior understandings and
agreements whether oral or in writing between the parties respecting the subject matter hereof
29 EFFECTIVE DATE
This Agreement shall be effective on the date of its approval by the City Council
This Agreement shall expire when terminated as provided herein
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed by
and through their authorized officers
agree/ surfiiet/professional svcs mayor 10 of 11
10/12
CONSULTANT,
Anchor QEA, LLC
COMPANY NAME
A California Limited Liability Partnership
By
print name
ITS (circle one) Secre ief Financial Officer/Asst
Secretary - Treasurer ? - , dL
CITY OF HUNTINGTON BEACH, a
municipal corporation of the State of
INITIATED AND APPROVED
,�c- - /� , L�
rector of Public or
APPROVED
Attorney
agree/ surfnet/professional Svcs mayor I I of 11
10/12
EXHIBIT "A"
A STATEMENT OF WORK (Narrative of work to be performed)
CONSULTANT shall provide consulting services on an'as-needed' basis for projects to be
determined during the term of the agreement During the term of the agreement, CITY may elect to
solicit proposals from CONSULTANT CITY shall issue task order for each project based upon the
scope of services, work schedule, and fee proposal submitted to CITY for its review and approval
B CONSULTANT'S DUTIES AND RESPONSIBILITIES
CONSULTANT'S duties and responsibilities shall be per CONSULTANT'S Statement of
Qualification (Exhibit A 1), consistent with the City of Huntington Beach Request for
Qualifications for On -Call Engineering & Professional Consulting Services Upon award, and the
contract period, if CONSULTANT chooses to assign different personnel to the project,
CONSULTANT must submit the names and qualifications of these staff to CITY for approval
before commencing work
C CITY'S DUTIES AND RESPONSIBILITIES
1 Furnish scope of work request for each project
2 Furnish construction plans and specifications to the CONSULTANT.
D WORK PROGRAM/PROJECT SCHEDULE
A project schedule will be developed for each project assigned by CITY
EXHIBIT A
�MI I
ri
7t� �""�! � � a} T,�
., ma's
..-�.
-:.
F";Mx,
-
i
II
I
February 2015 ANCHOR
CITY OF HUNTINGTON BEACH 0 E A
On -call Engineering& Professional
Consulting Services - Category B,
Ocean Engineering
i
Submitted by Anchor QEA
II
1
1
kZANCHOR
QEA
One Pacific Plaza
7755 Center Avenue, Suite 1060
Huntington Beach, California 92647
Phone 657 227 7430
February 18, 2015
1
1
_J
1
J
Attn: Mr. Jim Slobojan, Fiscal Services Division
City of Huntington Beach
2000 Main Street
Huntington Beach, California 92648
Re: On -call Engineering & Professional Consulting Services - Category B, Ocean Engineering
Dear Mr. Slobojan:
On behalf of Anchor QEA, LLC, we are pleased to submit the attached Statement of
Qualifications for on -call engineering and professional services in Category B, Ocean
Engineering. We specialize in waterfront -related projects and currently provide consulting
services to the Cities of Newport Beach and Long Beach. We are excited about this
opportunity to assist the City of Huntington Beach's (City's) Public Works Department with
coastal engineering projects by sharing our wealth of technical expertise, local experience,
and established team of experts.
A New Local Resource for the City of Huntington Beach
Anchor QEA is an internationally recognized
environmental and waterfront engineering
consulting firm that specializes in aquatic, shoreline,
and water resource projects. We have extensive
experience with coastal restoration projects,
Company Ownership
Anchor QEA has been an LLC since 1997;
is headquartered in Seattle, Washington,
is licensed with the City (#A291404); and
is registered with the State of California.
including project planning and permitting, mitigation bank development, engineering
design, surface and ground water quality, habitat restoration, landscape architecture,
contaminated sediment management, and construction management. We have provided a
full range of science and engineering services to the City of Newport Beach for the past 12
years and the City of Long Beach and the Port of Long Beach for the past 14 years.
ANCHOR City of Huntington Beach
' 0EA On -call Engineering & Professional Consulting Services
11
11
Our local staff are waterfront engineering professionals with expertise in marine structure
assessment and engineering design, coastal and geotechnical engineering, and beach
erosion and replenishment processes. Our local engineers are supported by a team of local
dredging, sediment quality, wetlands and habitat restoration, regulatory agency compliance
and permitting, and construction management professionals. Anchor QEA has successfully
developed uniquely tailored project tools to efficiently implement the engineered solution by
using local experts and our vast body of experience in the Southern California region.
Anchor QEA's Huntington Beach office is conveniently located adjacent to Bella Terra Center,
less than 5 miles from City Hall and the Public Work Department's Main Street office, and will
be our lead office for these on -call ocean engineering services.
A Trusted Consultant Team in Southern California
The strength Anchor QEA brings to each and every project reflects our core values of
technological leadership, integrity, superior product quality, and client satisfaction. We are
technical leaders in the region for marine engineering, environmental, permitting, and
construction services and have exceptional relationships with local regulators from the U.S.
Army Corps of Engineers, Regional Water Quality Control Board, California Coastal
Commission, and resource agencies. These relationships have been built on years of trust
earned through our continued pursuit of sound scientific approaches to find novel solutions
that meet everyone's objectives. Because of our trusted relationships, these same regulators
have provided us the unique opportunity to influence future regulatory developments.
Our reputation as the go -to engineering firm for local cities comes from our continued
dedication to the highest quality of project deliverables while successfully meeting client
budget and schedule goals. We approach challenges like no other firm and consistently
develop solutions where all others have failed.
ANCHOR City of Huntington Beach AMk
' QEA `'"" On -call Engineering & Professional Consulting Services
I
Experienced Project Management Team
Randy Mason, a principal engineer in our Huntington Randy Mason I Project Manager
Beach office, will be the project manager and single One Pacific Plaza
point of contact with the City and our team 7555 Center Avenue, Suite1060
Huntington Beach, California 92647
members. Randy will be supported by our Direct. 657.227.7454 ( Cell: 714 702 4208
Huntington Beach and Mission Viejo offices and, if Email. rmason@anchorclea com
needed, can draw the full range of Anchor QEA's
national waterfront expertise and capabilities.
1 Randy is a California registered civil engineer with more than 40 years of professional
experience and 30 years of waterfront project experience within Huntington Harbour, which
includes numerous dock and seawall assessment, repair, and rebuild projects. Prior to joining
Anchor QEA, he also managed the Bolsa Chica Ecological Reserve pedestrian bridge project
for the California Department of Fish and Wildlife, which included working with the Bolsa
Chica Conservancy, and managed several facility design projects for the City's Public Works
Department, working closely with Eric Charlonne.
Steve Cappellino, a principal scientist and member of the corporate management team at
Anchor QEA, will be our team's principal -in -charge. Steve has more than 25 years of
experience managing coastal projects throughout Southern California and across the United
States, and for the past 15 years, he has been working directly for the Cities of Newport Beach
and Long Beach managing marine engineering and coastal studies. His work has won local
(American Society of Civil Engineers Los Angeles and Ventura Chapters), national (U.S. Navy
and American Association of Port Authorities) and international (Western Dredging
Association) awards for innovation, partnering, and cost -savings measures. Steve works from
both our Huntington Beach and Mission Viejo offices and is authorized to assign the
appropriate level of local corporate resources as needed to ensure project success.
In addition to our team leadership, we have committed senior engineers, scientists, and
technical professionals to assume key roles and responsibilities for these ocean engineering
, ANC} 10R City of Huntington Beach
' VQEA Can -call Engineering & Professional Consulting Services 0
L7
I
services. We are prepared to commit all of our team members to the City for the duration of
the contract services.
Relevant Similar Local Experience
Our Statement of Qualifications presents an abbreviated summary of our project experience
in accordance with the page requirements of the City's Statement of Qualifications request.
We have only presented a small portion of our past and ongoing work with the major local
clients (i.e., the Cities of Newport Beach and Long Beach). The selected examples are high -
profile projects that include improving the environment by removing contaminated
sediments, improving and restoring environmentally sensitive habitats, replacing and
repairing critical and public use marine structures, and providing design solutions for
coastline protection to address current flooding, maximum high tides, and predicted future
sea level rise. Our experience includes coastal protection for both short- and long-term
planning and solutions.
As a city, we understand the need to demonstrate responsible project funding and the need
to develop cost-effective solutions as well as solutions that may require phasing to
accomplish long-term goals. We also understand the local interest that these types of
projects generate and the efforts city officials must undertake when working on projects with
coastal issues and concerns. Our local coastal experience includes working closely with city
staff, specially formed citizen's committees, special interest groups, and other stakeholders
through such efforts as community outreach to gather project input and present information.
We have reviewed the general requirements outlined in the City's Statement of Qualifications
request. We can provide the required certificate of insurance and have no exceptions to the
City's Standard Form of Agreement. We have also received and reviewed Addendum No.1,
issued on February 9, 2015 and Addendum No. 2, released on February 10, 2015.
ANC:I-10P City of Huntington Beach
' QEA ` ti On -call Engineering & Professional Consulting Services 0
I
Please contact us by phone at (657) 227-7454 to discuss any aspect of our Statement of
Qualifications. Thank you for the opportunity to submit this qualifications package.
ISincerely,
Steve Cappellino Randy Mason, P.E.
Principal Scientist Principal Engineer
Anchor QEA, LLC Anchor QEA, LLC
I
F
I
r
I
I
I
n
I
I
I
IZANCHOR
OEA
City of Huntington Beach
On call Engineering & Professional Consulting Services
40
REQUEST FOR PROPOSAL
VENDOR APPLICATION FORM
TYPE OF APPLICANT 0 NEW ❑ CURRENT VENDOR
Legal Contractual Name of Corporation Anchor QEA, LLC
Contact Person for Agreement: Randy Mason, P E
Corporate Mailing Address 7755 Center Avenue, Suite 1060
City, State and Zip Code: Huntington Beach, CA 92647
E-Mail Address: rmason@anchorgea corn
Phone 657 227 7430 Fax N/A
Contact Person for Proposals: Randy Mason, P E
Title Project Manager E-Mail Address: rmason@anchorgea corn
Business Telephone 657 227 7430
Is your business. (check one)
❑ NON PROFIT CORPORATION
Is your business (check one)
❑ CORPORATION
❑ INDIVIDUAL
❑ PARTNERSHIP
Business Fax N/A
0 FOR PROFIT CORPORATION
0 LIMITED LIABILITY PARTNERSHIP
❑ SOLE PROPRIETORSHIP
❑ UNINCORPORATED ASSOCIATION
1 of 2
Names & Titles of Corporate Board Members
(Also list Names & Titles of persons with written authorization/resolution to sign contracts)
Names Title Phone
Steve Cappellino
Shelly Anghera
Tom Wang
Federal Tax Identification Number.
Partner 949-347-2780
Partner 949-347-2780
Partner 206-287-9130
91-1851322
City of Huntington Beach Business License Number A291404
(If none, you must obtain a Huntington Beach Business License upon award of contract.)
City of Huntington Beach Business License Expiration Date 1-31-2016
2 of 2
EXHIBIT A: PRE -QUALIFICATION FORM
ON -CALL ENGINEERING & PROFESSIONAL CONSULTING SERVICES
A
Civil Engineering
Yes G
B
Ocean Engineering
Yes / No
C.
Development Plan Checking and Entitlement
Review Services
Yes No
D
Survey
Yes JS
E.
Traffic Engineering
Yes No
F
Water
Yes No
G
Geotechnical Materials Testing and Inspection
Yes No
(Initial) Consultant is willing to execute the Agreement as drafted (See Appendix B)
�C (Initial) Consultant is able to provide the insurance as required (See Appendix C).
Firm Name Anchor QEA, LLC
Firm Address 7755 Center Avenue, Suite 1060, Huntington Beach, CA 92647
-
Signature�,�QDate 2-18 2015
Page 12 of 17
u
C
u
H
u
1
r_
1
Firm Qualifications
A Trusted Ocean Engineering Firm that Acts Locally
Anchor QEA, LLC, is an internationally recognized
environmental and engineering consulting firm that specializes
in aquatic, shoreline, and water resource projects. We have
extensive engineering design and environmental support
experience and have assisted cities, counties, and ports with
harbor maintenance, capital improvement projects, and marine
infrastructure. We understand current coastal and harbor issues
and actively contribute to the industry as leaders by serving on
the board of directors of the Marina Recreation Association,
American Society of Civil Engineers Ports and Harbors Group,
and Western Dredging Association and by actively participating
in the California Marine Affairs and Navigation Conference.
Local Resource for the City of Huntington Beach
Our Huntington Beach office, located less than 5 miles from City
Hall, will lead ocean engineering services for any tasks
requested by the City of Huntington Beach (City). Our Mission
Viejo office will provide support, and Anchor QEA's full range of
company resources will be available to the City if needed.
Local Resource for Current Needs
Seawalls and Sea Level Rise
Dredging
Water Quality
Bluff Stabilization
Wetlands Restoration
Pier and Waterfront Structures
Anchor QEA Relevant Services
Feasibility Studies
Condition Assessments
Marine and Civil Engineering
Coastal Engineering and Modeling
Geotechnical Engineering
Dredging
Sediment Characterization
Environmental Documentation
Permitting
Compliance Monitoring
Construction Management
Anchor QEA, LLC
Anchor QEA has been an LLC since
1997, is headquartered in Seattle,
Washington; is licensed with the City
(#A291404); and is registered with
the State of California
ANCf Ip� City of Huntington Beach
0 L A —_ " On -call Engineering & Professional Consulting Services 0
I
1 Similar Project Experience and Client References
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
* �s
Marina Park Master Plan, Newport Beach
Master planning to develop a public use small craft harbor with a short-term marina, long dock, sailing center docks, and launch
facility. Planning included a feasibility/fatal flaw assessment of harbor geometry, water quality, sedimentation, and soil conditions.
Engineering design included preparing construction documents for waterside improvements and coordinating with concurrent
landside improvements and beach sand and dredged material placement. Ongoing work during construction includes providing
water quality monitoring during dredging, overseeing biological and archeological monitoring during site grading, and
preparing post -dredging reporting submittals. April 2007 to Present 1 $39.5 million
Balboa Island Seawalls Rehabilitation, Newport Beach
Initial study to assess existing seawalls and wave overtopping and flooding impacts from seasonal storms, maximum high tide events,
and future sea level rise on 80-year-old concrete seawalls. Previous work included developing concepts to replace/raise seawalls,
construct a groundwater dewatering system, and adjust building height finished grade (pad) elevation with changes to federal base
flood elevation. Ongoing work involves engineering support to replace/raise seawalls and coordinating City of Newport Beach
outreach. February 2010 to Present 1$34 to $69 million (estimated cost based on selected option)
Rhine Channel, American Legion, and Newport Bay Dredging Design and Construction Management, Newport Beach
Studies, engineering design, dredging design, environmental documentation, public outreach assistance, water quality and sediment
monitoring, subcontractor and construction management, and dredge disposal site identification and disposal assistance. Engineering
design included field investigation to document all waterside, survey seawall, and engineering design to remove and reinstall 120 new
longer guide piles and modify docks. September 2003 to November 2011 1 $6.5 million
Regional General Permit 54 Reauthorization and Eelgrass Management Plan, Newport Beach
Allows individual property owners to conduct maintenance dredging in specified areas. Work included managing and securing
approvals for temporary reauthorization of the City Newport Beach's permit on fast -track basis from the U.S. Army Corps of
Engineers, Regional Water Quality Control Board, and California Coastal Commission. Effort included developing an eelgrass
mitigation plan for Newport Bay. Ongoing work includes securing permit renewals. March 2012 to Present 1 $350,000 (fee)
Randy Mason, Master Planning and Schematic Design (prior to Iris Lee I Senior Civil Engineer I
joining Anchor QEA) I Robert Sherwood, Final Engineering City of Newport Beach I Public
Design and Coordination with Landside Improvements (prior Works Department
tojoining Anchor QEA) I Jack Malone, Environmental ilee@newportbeachca.gov
Compliance during Construction (949) 644-3323
Randy Mason, Project Manager (prior to joining Anchor QEA Robert Stein I Assistant City
and currently) Engineer I City of Newport Beach
Public Works Department
rstein@newportbeachca.gov
(949) 644-3322
Steve Cappellino, Project Manager I Randy Mason, Chris Miller I Harbor Resources
Engineering Design Rhine Channel Waterside Structures (prior Manager I City of Newport Beach
to joining Anchor QEA) I Michael Whelan, Engineering Design I cmiller@newportbeachca.gov 1
Jack Malone, Permitting. (949) 644-3043
Steve Cappellino, Managing Partner I Adam Gale, Project
Manager, Permitting and Compliance
Colorado Lagoon Restoration, Long Beach Steve Cappellino, Project Manager (Phase 2B) I Randy Mason,
Multi -phase project to restore an ecologically significant waterbody in an urban setting. Work includes dredging and filling, Project Manager (Phase 2A) I Kathy Ketteridge, Civil and
sediment characterization, dredged material disposal, wetlands -like habitat restoration/development, permitting, channel creation Hydraulic Engineering I Michael Whelan, Civil Engineering and
to allow entry and exit of ocean -fed water into the lagoon for tidal flushing and improved water quality, two new roadway bridges Dredging I Jack Malone, Permitting.
over channel, civil site work, and environmentally friendly landscaping. September 2011 to Present 1 $5 million (estimated cost)
West Basin (IR Site 7) and Pier G Pill Site, Port of Long Beach
Former Long Beach Naval Station and shipyard sites with contaminated sediments. Remediation required removal of 4 to 6 feet
deep layer of sediment (more than 550,000 cubic yards) in multiple areas and placement for landfills as part of Pier G
expansion/redevelopment. Work included remedial design, sediment characterization, environmental permitting, construction
management, on -site compliance, and closure documents. This project was the Port of Long Beach's first federally mandated
sediment remediation project and recognized as one of the most successful projects ever completed by the Port of Long Beach.
January 2008 to August 2011 1 $7 million (contract value)
Belmont Veterans Memorial Pier Assessment, Long Beach
Underwater, below deck, and topside inspections to assess the current condition of a 1,800-foot-long concrete municipal fishing
pier originally constructed in 1965. Work included identifying unsafe conditions and determining in -place condition and
compliance with current codes. The assessment report presented multiple repair/upgrade options and a full replacement option
with estimated lifespan data, rough order of magnitude costs, and recommendations. Effort included providing follow-on
consulting for potential on -pier restroom building expansion/replacement. May to July 20131 $6.8 to $17.7 million (depending on
selected option)
Glorietta Bay Marina Rebuild, Coronado
Master planning and engineering design to replace a dock system and utilities including new Americans with Disabilities Act
_ gangway, dredging and shoreline re-contouring/re-grading to fully develop water space, new slope protection (1,400-foot long rock
revetment with foundation), and new 17,500-square-foot off -site mudflats eelgrass habitat using salvaged rock and dredged bay
bottom and excavated shoreline material. October 2004 to July 20071$3.7 million and March 2011 to September 2014 1 $4 million
yP ANCHOR
1�OEA�
Steve Cappellino, Project Manager I Michael Whelan, Lead
Engineer I Jack Malone, Permitting
Randy Mason, Project Manager (prior to joining Anchor QEA)
Chris Miller I Harbor Resources
Manager I City of Newport Beach
cmiller@newportbeachca.gov
(949)644-3043
Charlene Angsuco I Tidelands
Capital Projects Manager I City of
Long Beach
charlese.angsuco@longbeach.gov
1(562) 570-6160
Sean Gamette I Program
Delivery Group, Senior
Director/Chief Harbor Engineer 1
Port of Long Beach
sean.gamette@polb.com
(562)283-7363
Eric Lopez I Tidelands Capital
Improvements Program Officer
City of Long Beach I
eric.lopez@longbeach.gov
(562)570-5690
Randy Mason, Project Manager (prior to joining Anchor QEA) Jerome Torres I Senior
Management Analyst I City of
Coronado
jtorres@coronado.ca.us 1
(619)522-7305
City of Huntington Beach
On -call Engineering & Professional Consulting Services
t
I
1
1
1
1
1
t
1
t
1
I
1
STAFFING
Experienced Project Management Team
All ocean engineering tasks awarded to Anchor QEA will be led by Randy Mason, P.E., from our
Huntington Beach office. Randy has more than 40 years of experience, with 30 years of local Orange
and Los Angeles County coastal projects experience that includes numerous condition assessment,
marina repair/replacement, and seawall repair/stabilization projects throughout Huntington
Harbour. Randy will be supported by, Steve Cappellino, a partner with the firm, as the principal -in -
charge. Steve will ensure that the City's objectives are met when each task is assigned, allocate the
appropriate resources, and provide City staff with a local, knowledgeable back-up contact. Steve
works in both our Huntington Beach and Mission Viejo offices and has more than 25 years of
waterfront development experience, 15 of which includes local Orange and Los Angeles County
coastal and harbor experience.
Team Organizational Chart
Tom Wang
Randy Mason, P.E.
Piaject Manage,
Robert Sherwood, P.E.
Deputy Pro'ect Manage,
Steve Cappellino
• •
7
Robert Sherwood, P.E. Kathy lyssaKettCannorldge,n
Ph.D. Jack Malone, Ph.D. 7MIlchael Whelan, P.E.
Alyssa Cannon
We have selected task leaders for our team who are locally and nationally recognized experts in each
discipline and have worked together on coastal and other waterfront projects for more than 10 years.
1
Z�f ANCHOR City of Huntington Beach
OE w On -call Engineering & Professional Consulting Services 40
I
Summary of Key Team Member Qualifications
'Name
I Role
Education
Similar Experience
Steve Cappellino
B.S., Ecotoxicology, 1990,
• West Basin (IR Site 7) Sediment Remediation, Port of
Principal -in -Charge
Western Washington University
Long Beach
'
• Rhine Channel Contaminated Sediment Cleanup,
City of Newport Beach
• Colorado Lagoon Restoration, City of Long Beach
'
Randy Mason, P.E.
B.S., Civil Engineering, 1972,
• Marina Park Master Planning, City of Newport Beach
Project Manager
California State University,
• Balboa Island Seawalls Rehabilitation, City of
Fullerton
Newport Beach
'
• Belmont Veterans Memorial Pier Assessment, City of
Long Beach
Robert Sherwood,
B.S., Civil Engineering, 1999,
. Marina Park Master Planning, City of Newport Beach
'
P.E.
University of California, Irvine
•Port of Hueneme Shore Protection and Waterfront
Deputy Project
Access, Oxnard Harbor District
Manager Marine
• Sunset Aquatic Park, City of Huntington Beach
'
Structures
Michael Whelan, P.E.
M.S., Geotechnical Engineering,
• Rhine Channel Contaminated Sediment Cleanup,
Geotechnical
1995, MIT
City of Newport Beach
M.S., Environmental
. Port of Hueneme Maintenance Dredging and CAD
Engineering, 1992, Georgia
Site Construction, Oxnard Harbor District
Institute of Technology
. Rhine Channel Contaminated Sediment Cleanup,
City of Newport Beach
'
Kathy Ketteridge,
Ph.D., Ocean Engineering, 2001,
• Puget Sound Nearshore Project Strategic
Ph.D.
Stevens Institute of Technology
Restoration Site Conceptual Engineering,
Coastal Engineering
Washington Department of Fish and Wildlife
• Coastal Engineering Evaluation of Existing Seawall,
'
City of Homer
• Colorado Lagoon Habitat Restoration Design and
'
Alyssa Cannon
B.S., Ocean Engineering, 2010,
Modeling
• Colorado Lagoon Restoration, City of Long Beach
Coastal Engineering
Texas A&M University
• Leeway Sailing Center, City of Long Beach
• Clover Island Shoreline Stabilization, Port of
'
Kennewick,
Jack Malone, Ph.D.
Ph.D., Biology, 2001, University
• Rhine Channel Contaminated Sediment Cleanup,
Permit Compliance
of California, Los Angeles
City of Newport Beach
• Port of Hueneme Maintenance Dredging and
t
Confined Aquatic Disposal, Oxnard Harbor District
• Mitigation Bank Development, Port of Los Angeles
Tom Wang
B.S., Civil Engineering, 1990,
• On -call Sediment Management and Coastal
'
Quality Assurance/
University of Washington
Planning, City and County of San Francisco
Quality Control
• Los Angeles County Dredged Material Management
'
Plan Pilot Studies, U.S. Army Corps of Engineers
• On -call Coastal Planning and Dredging Support,
U.S. Army Corps of Engineers
' Resumes for Anchor QEA key team members and additional support staff are provided at the end of
our Statement of Qualifications.
1
ANC[ 101" City of Huntington Beach
' 01 A On -call Engineering & Professional Consulting Services MF
n
I
I
1
t
1
UNDERSTANDING AND METHODOLOGY
Understanding
With the premier Orange County coastline, popular public beaches, a landmark pier, and large areas
of protected coastal wetlands, Anchor QEA understands the importance of protecting the City's high -
profile and valuable coastal resources in both the short and long term.
Our understanding of potential work and critical issues and concerns pertain to the
City's Ocean Engineering category include:
Sediment transfer and beach replenishment
Public use marine structures, such as the
Huntington Beach Pier
Studies and planning to identify and address
long-term preservation of the City's coastline and
its waterfront assets
Methodology
Coastal wetland restoration and protection
Beach and bluff erosion and protection
Near- and long-term impacts from predicted sea
level rise
Existing seawalls and other shoreline protection
Our general methodology for on -call assignments uses a proven sequence of procedures. The
project implementation process begins when our project manager, Randy Mason, receives a specific
task assignment from the City. After review, he will assess the scope of work and develop a cost
estimate and schedule that will be continuously monitored during the course of the work. Task
scope of work, costs, and schedule will be reviewed with the City's representative to ensure mutual
agreement before commencing any work. Randy will select key personnel from our team to
accomplish the task assignment based on the qualifications and experience of the individual relative
to the technical and regulatory requirements of the task.
Randy will be the primary point of contact with the City and our team members. For each task
assignment, an internal kickoff meeting will be held with assigned team members to review the
scope of work, schedule, and the City's goals. Internal team meetings will be held as necessary
during the work to monitor progress against the budget and schedule. Randy and the appropriate
team members will coordinate with City staff during the work as appropriate. To maximize the
effectiveness of these meetings, action item matrices and detailed, timely meeting minutes will be
t ANCHOR City of Huntington Beach
QEA On -call Engineering & Professional Consulting Services 18
I
1
1
1
1
1
t
I
I
created to identify issues, responsible parties, and deadlines. Any challenges that may arise will be
discussed and resolved to ensure steady progress with no surprises later in the project. Our
experience demonstrates that regular meetings encourage dialogue and creativity.
The most effective way to maintain control over cost and schedule is to properly scope the project,
communicate that scope of work, cost, and schedule to the project team and aggressively monitor
progress through continuous communication. To control the budget, Randy will request weekly
budget statements from our project administrator. A detailed schedule, identifying tasks,
milestones, and critical path elements of design and coordination, will be developed and monitored.
Quality Assurance/Quality Control
Anchor QEA has a well -established quality assurance/quality control (QA/QC) program that ensures
quality is maintained in all deliverables throughout project. A QC Plan will be prepared at the outset
of each project and submitted to the City for approval. An independent internal team will be
selected for each project and will include our team technical reviewers and editors. It is our policy to
ensure that all work products are exhaustively checked prior to submittal regardless of content or
complexity of the deliverable. We have committed Tom Wang, an Anchor QEA partner with more
than 24 years of marine project experience to manage our team's QA/QC process. He will direct
additional staff during the review process depending on the nature of the submittal.
' �Q ANCHOR City of Huntington Beach
,Z QEA On -call Engineering & Professional Consulting Services
I
1
1
1
1 Appendix A:
1 Resumes
1
1
1
1
1
1
1
1
1
1
1
1
1
I
1
1
1
1
1
1
1
1
1
[l
1
1
Randy Mason, P.E.
Principal Engineer
Education: B.S., Civil Engineering, California State University, Fullerton, 1972 1 Professional Engineer,
State of California
Randy Mason's 40-year professional career includes more than 30 years focused directly on local
waterfront projects. His experience includes marine structures (piers, wharves, docks, seawalls, and
revetments), coastal bluff protection, and recreational marinas. He has led master planning and
design efforts at various locations along the California and Baja, Mexico coastline; however, the main
focus of his work has been in Orange and Los Angeles counties, including Huntington Harbour,
Newport Beach, Corona del Mar, Dana Point Harbor, and Marina del Rey. His experience also includes
bluff erosion mitigation measures, shoreline and slope protection measures, and waterfront coastal
trails and promenades.
Mr. Mason's Huntington Beach experience includes numerous condition assessments, marina
rebuild/repair, and seawall repair/stabilization projects within Huntington Harbour. With a 20-year
project history in Huntington Harbour, he has become a recognized expert on the area's seawalls
and marinas and is routinely contacted by property owners, homeowners associations, individual
property owners, area realtors, and others to provide consulting expertise. His demonstrated
knowledge of the area led the combined Huntington Harbour Property Owners Association to
request that he author a seawall system technical paper in 2008 that was distributed to all property
owners. In addition, as a principal of his former company, Cash & Associates, Mr. Mason managed
several facility projects for the City's Public Works Department, including pump station and water
well projects and planning and improvements for the Utility Operations Yard.
Mr. Mason has worked with local public agencies including the counties of Orange and Los Angeles;
cities of Huntington Beach, Newport Beach, Long Beach, and Los Angeles; ports of Long Beach and
Los Angeles; and a wide variety of local private sector clients. He has assisted the cities of Newport
Beach and Long Beach with revisions to their waterfront design and construction standards and has
worked closely with the various state and federal agencies having jurisdiction over waterfront
projects. He understands the issues and agency concerns that are specific to coastal and waterfront
projects.
1 Project Experience
Marina Park I City of Newport Beach, California
1 Mr. Mason was the project manager/principal planner for development of waterside components for
a planned 10.5-acre public use waterfront park on Newport Peninsula. Planned waterside
components included a short-term marina and 200-foot-long public dock, Sailing Center and floating
1 docks, an Americans with Disabilities Act (ADA)-compliant ramp with a secure gate and a floating
dock structure for on -water storage of sabots, CFJs, 420s, and other dingy -type craft.
1
LJ
11
I
Randy Mason, P.E.
hIm,11 el Lngu,eer
k
1
11
1
Balboa Island Seawalls Rehabilitation I City of Newport Beach, Public Works Department
Newport Beach, California
Mr. Mason is the project manager for development of concepts and design to replace and raise
existing concrete seawalls around Balboa and Little Balboa Islands. The design is based on
Mr. Mason's involvement in a 2010 seawall integrity/sea level rise study, and the scope has included
assisting with the City's public outreach efforts.
Rhine Channel Dredging I City of Newport Beach, Harbor Resources Division, Public Works Department
Newport Beach, California
Mr. Mason was the project manager of engineering design services for waterside structures impacted
by dredging to remove contaminated sediment. Work involved extensive field investigation, guide
pile analysis to determine new pile lengths, evaluation of seawall stability, development of dredge
limits near seawalls, and plans and specifications to replace affected guide piles and modify docks for
larger piles. An estimated 120 guide piles were replaced.
Bolsa Chica Ecological Reserve Pedestrian Bridge I California Department of Fish and Wildlife
Huntington Beach, California
Mr. Mason was the project manager for the design and installation of a 145-foot-long bridge
composed of mat foundations and a steel truss frame bridge with ADA-compliant approaches. The
design was developed in conjunction with the California Wildlife Foundation and focused on
minimizing negative impacts to the sensitive habitat. Center bridge support was eliminated, so the
structure did not encroach in the waterway, and the bridge was fabricated off site to minimize
on -site construction. Involvement took place over several years while funding was obtained.
Belmont Veterans Memorial Pier Assessment I City of Long Beach I Tidelands Capital Improvement
Division I Long Beach, California
' Mr. Mason was the project director for topside, under -pier, and underwater structural inspections to
assess the condition of a 1,800-foot-long by 24-foot-wide concrete pier supported on concrete
152 piles, originally constructed in 1966. The focus of the inspection was to identify any unsafe
' conditions for public use and determine if the pier was repairable, and if repaired, if it could support
additional loads from new amenities. Evidence of observed deterioration, repair options, costs for
repair versus replacement, and recommendations were incorporated into an assessment report.
1
1
I
Glorietta Bay Marina I City of Coronado, California
Mr. Mason was the project manager/principal engineer for planning and design to replace Docks A
and B and interface with concurrent landside improvements. The project scope included dredging
and slope re -contouring to maximize usable water space and installation of a new rock revetment to
improve water/land interface. Dredged material and rock salvaged from an existing revetment were
used to create a near -site mudflats habitat.
Dana Point Harbor Marina I Orange County I Dana Point, California
Mr. Mason was the project manager for master planning and design to rebuild the 2,400-slip Dana
Point Marina. The project scope included a condition survey and stability analysis of the harbor's
5,100-foot-long seawall to determine its capability to resist anticipated soil pressures from the static
and seismic loads and an evaluation of harbor dredging requirements and nearshore shoaling
quantification.
1
Steve Cappellino
Principal Scientist
' Education: Western Washington University, B.S., Ecotoxicology, 1990
Steve Cappellino is a partner and senior project manager based in Anchor QEA's Mission Viejo office.
Mr. Cappellino has more than 25 years of experience managing waterfront redevelopment,
' dredging, and sediment remediation projects at ports and harbors throughout the United States.
Many of these assignments have included all aspects of the project from initial site characterization
and risk assessment, all the way through alternative development, feasibility evaluation, permitting,
' design, and eventually construction implementation. He actively oversees Anchor QEA's waterfront
work with the cities of Newport Beach and Long Beach and the ports of Long Beach, Los Angeles,
' and Hueneme.
Mr. Cappellino has been an active member of ASTM's sediment subcommittee since 1992 and has
participated in the preparation and review of methods for the collection and testing of sediments for
' use in risk assessments and dredge material evaluations. He has also led the development of several
regional long-term sediment management strategy documents for the U.S. Army Corps of Engineers
(USACE) and the State of California, including the Los Angeles Contaminated Sediments Task Force
Long -Term Management Strategy, the Los Angeles Regional Dredged Material Management Plan,
and the San Francisco Bay Delta Long -Term Management Strategy.
' Project Experience
West Basin (IR Site /) Sediment Rernediation I Port of Long Beach, California
' Mr. Cappellino was retained by the Port of Long Beach to manage a multi -year sediment
remediation/facility redevelopment project at the former Long Beach Naval Shipyard facility. The
area is a former Naval Installation Restoration study site. As such, all work was conducted according
to Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) guidelines
and included full California Environmental Quality Act (CEQA) compliance. Anchor QEA completed
CEQA documents for the project, led the remedial design, and completed field construction
management, where more than 500,000 cubic yards of contaminated sediments were dredged and
placed inside a confined disposal facility. Dredge monitoring included 24-hours, 7-days-a-week
' oversight, as well as hundreds of sediment samples, to verify successful removal. Mr. Cappellino also
led the development of the post -construction compliance reports for submittal to the State of
California, the U.S. Navy, and the U.S. Environmental Protection Agency.
' Rhine Channel Contaminated Sediment Cleanup I City of Newport Beach, California
Mr. Cappellino managed a multi -disciplinary project for the City of Newport Beach to remediate
contaminated sediments from the Rhine Channel in Lower Newport Bay. The Rhine Channel was
contaminated with metals, polychlorinated biphenyls (PCBs), and DDT from past industrial use and
stormwater runoff. Since 2005, Anchor QEA conducted studies that included surface and subsurface
' sediment sampling, bathymetry surveys, debris field mapping, and structural engineering surveys of
the existing shoreline structures, as well as an RI/FS, a CEQA Mitigated Negative Declaration,
engineering design, and permit acquisition. The construction portion of the project was completed
iSteve Cappellino
' in fall 2011, and Anchor QEA managed all construction activities, field (water quality and sediment)
monitoring, and post -construction compliance monitoring.
Colorado Lagoon Restoration I City of I ong Beach, California
Mr. Cappellino is managing the design and permitting of this ecosystem restoration project in the
City of Long Beach that includes dredging and grading the lagoon shoreline to create an eelgrass
and habitat mitigation bank for future development needs. Project elements include coastal
engineering and modeling to simulate future tidal exchange and water quality conditions.
' Middle Harbor Fill Site Third -party Dredge Material Management I Port of Long Beach, California
Mr. Cappellino assisted in the management of all third -party disposal activities within the Middle
Harbor fill site as part of the ongoing construction management effort. In total, almost 1 million
cubic yards of material were transferred to the fill site from various locations around Southern
California and placed in designated areas within the fill site. Anchor QEA's role on the project was to
oversee the disposal activities and coordinate schedules for the construction contractors. This
included ensuring that the proper paperwork was in place and assisting Port staff in selecting the
best location for each disposal event.
' Port of Hueneme Maintenance Dredging and CAD Site Construction I Oxnard Harbor District
Oxnard, California
' Mr. Cappellino led a project to design, permit, and construct a multi-user confined aquatic disposal
(CAD) site for contaminated sediments within Port of Hueneme. The project comprised three distinct
phases: 1) excavating a large pit in the middle of the harbor and placing the clean sand onto an
' adjacent beach; 2) dredging contaminated sediment from the USACE Federal Channel, Oxnard
Harbor District wharves, and U.S. Navy berths and placing the material into the CAD cell; and 3)
constructing a clean cap of sand on top of the contaminated layer to seal the cell and prevent
' chemical migration. Specific elements of this project included CEQA/National Environmental Policy
Act permitting, engineering design, environmental characterization, construction management, field
construction monitoring, and long-term monitoring and maintenance. The total volume of material
managed during this project was approximately 1 million cubic yards.
Cl
t
1l
t
Adam Gale
Managing Environmental Planner
' Education: Certificate Program in Geographic Information Systems, University of Washington, 2007;
B.S., Ecology and Systematic Biology, California Polytechnic State University, Son Luis Obispo, 2004
Certified Erosion & Sediment Control Lead
' Adam Gale is a managing environmental planner with nearly 10 years of environmental planning
and permitting experience, including design and construction work. He has experience on a range
of projects from small-scale private marina developments to large-scale state transportation projects.
' His success is supported by his knowledge in National Environmental Policy Act (NEPA), California
Environmental Quality Act (CEQA), California Coastal Act, Clean Water Act, Rivers and Harbors Act,
' and Essential Fish Habitat and Endangered Species Act regulations. Mr. Gale complements his
regulatory understanding as a natural resource specialist with extensive experience conducting
jurisdictional delineations (wetlands and streams), habitat evaluations, and flora and fauna surveys.
He is a Certified Erosion & Sediment Control Lead (CESCL) and has successfully managed
construction projects, including construction oversight and environmental compliance monitoring.
' Project Experience
Nimitz Marine Facility Research Vessel Berthing Pier Replacement I Ben C. Gerwick, Inc./COWI
' University of California, San Diego I San Diego, California
The Nimitz Marine Facility Research Vessel Berthing Pier Replacement project includes removal and
of the existing pier and wharf and replacement with new structures at the University of California,
' San Diego, Scripps Institution of Oceanography. Mr. Gale is the project manager and has successfully
managed preparation of a combination Initial Study/Environmental Assessment in accordance with
NEPA, CEQA, and other applicable laws. Additionally, he is the environmental permitting lead and
has obtained all project approvals from the U.S. Army Corps of Engineers (USACE), California Coastal
Commission (CCC), California State Lands Commission, and San Diego Regional Water Quality
Control Board (RWQCB). Anchor QEA is currently managing the environmental compliance during
' construction, with a focus on construction noise and vibration monitoring, permit and regulatory
compliance, and biological survey and reporting. The USN is the federal lead agency for this project
and co -applicant on many of the required regulatory approvals.
Marina Park I City of Newport Beach I Newport Beach, California
The Marina Park project is currently under construction with an anticipated completion date of
' December 2015. Once completed, the site will feature a 24,000-square-foot sailing and community
center, a 23-slip marina for visiting boaters, a new Girl Scout House, and revamped tennis and
basketball courts. Mr. Gale is the environmental compliance manager during all phases of
' construction and is responsible for negotiating with state and federal agencies compliance
responsibilities prior to, during, and post -construction. This includes obtaining notice to proceed
and agency pre -construction authorizations, preparing and implementing water quality monitoring
' during dredging operations, overseeing biological and archeological monitoring during site grading
operations, and preparing post -dredging reporting commitments. Mr. Gale will continue to play a
' key role through the remainder of construction.
' Adam Gale
Managing Environmental Planner
' Regional General Permit 54 1 City of Newport Beach, Harbor Resources Department I Newport Beach,
California
' The City of Newport Beach is in the process of obtaining a new Regional General Permit 54 (RGP).
The RGP would allow individual residential and commercial property owners a more streamlined
mechanism to conduct maintenance dredging in specified areas of the harbor that have met state
' and federal sediment quality standards for ocean disposal, beach replenishment, or upland disposal,
as well as minor dock repair or replacement. Mr. Gale is the project manager responsible for
overseeing all aspects of the project, including obtaining approval from USACE, the RWQCB, and the
' CCC. To compliment this effort, Anchor QEA is assisting the City in establishing a city -specific
eelgrass mitigation plan that would allow property owners to mitigate for eelgrass impacts through a
bay -wide approach as opposed to site -specific mitigation requirements. The eelgrass mitigation
plan is an innovative approach that has been developed in close coordination with the USACE, CCC,
RWQCB, and the National Marine Fisheries Service.
' Back Bay Landing Development Plan I Terra Vista Management I Newport Beach, California
Anchor QEA provides comprehensive marina planning services for the Back Bay Landing Marina
development project. The project involves rebuilding a commercial marina in Upper Newport Bay,
' with removal and replacement of existing floats, gangways, and piles; maintenance dredging;
enhancement/mitigation of habitat; upgrade and/or construction of seawalls; construction of a
dry -stack boat storage facility; and construction of visitor and public amenities. Mr. Gale has been
' involved in several aspects of the project; he most recently provided technical review of the draft
Environmental Impact Report (EIR) prepared by the City of Newport Beach. Mr. Gale previously
' conducted a wetland delineation of the project area to facilitate early design considerations for the
proposed project. The delineation focused on the marine component of the project, documenting
the landward extents of waters of the United States subject to the regulatory authority of the USACE
and wetlands as defined by the CCC.
Shellmaker Island Rowing Center Dock Replacement I University of California, Irvine I Newport Beach,
California
' The University of California Irvine (UCI) is currently undertaking a renovation project at its Shellmaker
Island Rowing Center in Newport Beach. Renovations include in -kind replacement of a
' 2,240-square-foot upland concrete deck adjacent to a fixed overwater dock and upland boat house.
The CCC is reviewing UCI's Coastal Development Permit application and has requested that a coastal
hazards analysis be conducted for the proposed deck replacement. Anchor QEA completed the
' analysis that evaluated the current and potential coastal hazards at the site, based on local predicted
sea -level rise estimates, in addition to an evaluation of minimization of impacts from coastal hazards,
both existing and future (potential). Mr. Gale is the project manager overseeing the analysis and will
' continue to support UCI through issuance of the Coastal Development Permit.
1
Alyssa Cannon
Professional Staff
' Education: B.S., Ocean Engineering, Texas A&M University,2010
Alyssa Cannon has more than 3 years of professional experience focused on evaluating nearshore
coastal processes and designing shoreline protection structures and beach nourishment projects. In
' addition to her work at Anchor QEA, she was involved in several research projects during her
undergraduate education, including a feasibility evaluation of proposed large-scale shoreline
protection projects along the Texas coastline and tsunami modeling. Her areas of expertise include
' meta ocean data analysis, wind -wave hindcasting, wave and current modeling, and evaluation and
design of shoreline stabilization solutions.
I
1
1
1
1
t
t
1
1
1
Project Experience
Colorado Lagoon I City of Long Beach I Long Beach, California
As coastal engineer, Ms. Cannon was responsible for completing wind -wave evaluation and project
design tasks. The work included wetland grading, including dredging and upland grading.
Leeway Sailing Center I City of Long Beach I Long Beach, California
As coastal engineer, Ms. Cannon was responsible for completing a coastal hazards analysis. The work
included a wind -wave evaluation, sea level rise estimates, and evaluation of the effects of updated
infrastructure on the local coastal environment.
Clover Island Shoreline Stabilization I Port of Kennewick I Kennewick, Washington
As coastal engineer, Ms. Cannon was responsible for evaluating riverine and coastal processes to
develop design criteria to inform shoreline stabilization design for a redevelopment project at Clover
Island, Washington. The work included development of 60%and 90% design, associated design
drawings, and specifications.
Snohomish County Nearshore Restoration I Snohomish County I Snohomish County, Washington
As coastal engineer, Ms. Cannon was responsible for evaluating coastal processes along 4 miles of
shoreline between Mukilteo and Everett in Puget Sound. The project including evaluating multiple
alternatives and development of a 35%design for two preferred alternatives. Additional work for the
preferred alternatives is currently in progress and involves developing final design drawings and
specifications.
Seahurst Park I City of Burien Parks and Recreation I Burien, Washington
As coastal engineer, Ms. Cannon was responsible for completing wind -wave evaluation and project
design tasks. The work included wind -wave hindcasting and shoreline change modeling using
models developed by the U.S. Army Corps of Engineers (STWAVE and GENESIS). The modeling efforts
were used to evaluate proposed alternatives and inform performance and maintenance costs for the
preferred alternative. The project included significant bulkhead removal and soft shoreline
restoration with public access on Puget Sound. The project received a national 'Best Restored Beach
Award" from the American Shore and Preservation Association in 2010.
I
Erik Pipkin
GIS/CAD Technical Specialist
t Education: B.A., Environmental and Resource Management, Western Washington University, 2006
Erik Pipkin is an expert user of AutoCAD software and has experience in multiple environmental
disciplines, including hydraulic and coastal engineering, habitat restoration, fisheries, and risk
' assessment. He works on all aspects of projects, from concept development to final design, and leads our
drafting/design team in producing deliverables such as permit drawings, conceptual and alternative
drawings, construction drawings, and volumetric analysis. As an experienced user of ArcGIS, he finds that
' being able to use both CAD and GIS software in the development of designs adds to project efficiency.
Project Experience
tDeer Lagoon Restoration Project I Wild Fish Conservancy I Whidbey Island, Washington
As lead GIS Analyst, Mr. Pipkin acquired, synchronized, and analyzed topographic and bathymetric
' data. He pre- and post -processed GIS data for incorporation into hydraulic models and assessment of
alternatives for improving tidal transfer and fish habitat within a man-made lagoon. Analyses were
conducted to evaluate the impacts to adjacent uplands and habitat improvements.
tRiparian Inventory and Function Assessment I Whatcom County I Bellingham, Washington
Mr. Pipkin used GIS to complete an inventory and functional assessment of riparian conditions in
' eight creek systems and more than 100 miles of associated marine shoreline. Riparian vegetation
conditions were inventoried using a variety of aerial imagery sources, LiDAR, and available GIS. The
inventory collected conditions for large woody debris potential, wildlife corridors, and water quality.
' GIS was used to store and analyze the data to determine the current conditions and restoration need.
A project geodatabase and metadata were created and transferred to the client.
' Colorado Lagoon Phase 2B Design Project I City of Long Beach I Long Beach, California
Mr. Pipkin is the lead CAD designer for this restoration and park design project that involves
substantial upland regrading, dredging and filling of a tidal lagoon, storm drainage, and public
' access. Mr. Pipkin has used both GIS and CAD to develop products to assist the design and convey
restoration and engineering concepts.
' Development Support (Restoration) at Whiteman Cove I South Puget Sound Salmon Enhancement
Group I Key Peninsula, Washington
Mr. Pipkin was the lead GIS/CAD Analyst on this project. He developed multiple topographic and
bathymetric surface models for use in hydraulic models to assess restoration alternatives. Analyses
were conducted to assess the proposed restoration design and identify potential flooding impacts
within the cove. He produced CAD maps and GIS figures in support of the project.
t East Waterway Supplemental Remedial Investigation/ Feasibility Study I Port of Seattle, Washington
Mr. Pipkin was the lead GIS Analyst responsible for developing GIS tools to assist in the evaluation of
' sediment transport and contamination. The project involved assessing and modeling
hydrodynamics and sediment transport processes within the East Waterway, including contributions
from stormwater and combined sewer outfalls that discharge into the Waterway. Mr. Pipkin created
' GIS tools to post -process and present model output for evaluation.
1
I
Jack Malone, Ph.D.
Managing Scientist
' Education: Ph.D., Biology, University of California, Los Angeles, 2002; B.S., Biology/Marine Sciences,
University of North Carolina, Chapel Hill, 1995
Dr. Jack Malone is a managing scientist with more than 12 years of experience in all aspects of
' permitting and regulation, including preparation of state and federal environmental documentation
relating to complex marine and waterfront projects such as sediment management and remediation,
port and harbor development, dredging and infrastructure development, habitat restoration, essential
fish habitat and endangered species issues, and sediment and water quality. Prior to joining Anchor
QEA, Dr. Malone was a regulatory project manager in the Los Angeles District of the U.S. Army Corps of
' Engineers (USACE). He was in charge of the USACE's role as lead federal agency for various complex
marine and aquatic projects in Southern California.
' Project Experience
Colorado Lagoon Restoration Phase 2B I City of Long Beach I Long Beach, California
Dr. Malone is supporting the City of Long Beach in the restoration of Colorado Lagoon to establish a
' mitigation bank by leading the permitting process and supporting the City in regulatory and
resource agency negotiations. The project entails creation of intertidal and subtidal habitat, planting
' of eelgrass, establishment of native upland vegetation, creation of a bioswale, and conversion of an
asphalt road to a walking trail.
Rhine Channel Contaminated Sediment Cleanup I City of Newport Beach I Newport Beach, California
t Dr. Malone led the preparation of the City of Newport Beach's Initial Study/Mitigated Negative
Declaration and all required permit applications and supporting information for the City's project to
remove contaminated sediments from the Rhine Channel. The Rhine Channel is contaminated as a
result of past industrial use and stormwater runoff. Anchor QEA also assisted with extensive
stakeholder outreach efforts and pre -application meetings with the regulatory agencies.
t Construction was completed in December 2011 with beneficial reuse of the dredged material at the
Port of Long Beach's Middle Harbor fill site.
Permitting and Environmental Compliance I City of Newport Beach I Newport Beach, California
' Dr. Malone has supported the City of Newport Beach with a variety of permitting and environmental
compliance efforts. He has supported the City in renewing Regional General Permit 54 for
maintenance dredging, developing a harbor -wide eelgrass management plan, and compliance with
' permits and approvals for the Marina Park development project.
On -call Environmental Support i City of Long Beach I Long Beach, California
' Dr. Malone is supporting the City of Long Beach in multiple permitting and regulatory compliance
efforts. These include renewal of Regional General Permit 30 for maintenance dredging,
development of a Habitat Mitigation and Monitoring Plan for the Naples Seawall Rehabilitation
' project, permitting support for the Alamitos Bay Marina Rehabilitation project, development of a
coastal hazards analysis to satisfy California Coastal Commission requirements for the Leeway Sailing
Center renovations project, and investigations of water quality at Rainbow Lagoon.
1
I
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Kathy Ketteridge, Ph.D.
Senior Professional
Education: Ph.D., Ocean Engineering, Stevens Institute of Technology, 2001; M.S., Ocean Engineering, Stevens
Institute of Technology, 1997;B.S., Civil Engineering, University ofMaryland, 1993
Dr. Ketteridge has more than 18 years of experience in analysis and design of a wide variety of
coastal engineering, restoration, and enhancement projects on the East, West, and Gulf coasts. She
has managed numerous coastal assessment/restoration projects from stakeholder and public
visioning and conceptual design through construction. She brings focused and proven technical
proficiency to the team in the areas of processes -based restoration, numerical modeling of tidal
hydrodynamics, wave transformation and sediment transport, interaction and integration of
shoreline armoring with natural shorelines, and impacts of sea level rise on project implementation
and sustainability.
Project Experience
Keyport Lagoon Restoration I U.S. Navy I USNB Kitsap Keyport, Washington
As project manager and senior coastal engineer, Dr. Ketteridge was responsible for developing 2-D
tidal circulation and wave models to evaluate the performance of proposed restoration alternatives
(new tidal inlet) and provide design criteria for a proposed new bridge to be built across the new
inlet. Work included wind -wave hindcasting, an evaluation of design storm parameters and
associated wave loads, and shoreline protection requirements for the various project elements.
Scour analysis in the nearshore area and in the Lagoon post project were also evaluated.
Cabo Riviera Wave and Tidal Hydrodynamic Modeling I La Riviera, Mexico
As senior coastal engineer, Dr. Ketteridge was responsible for development and implementation of a
coupled 2-D tidal circulation and nearshore wave model (DELFT3D and SWAN) to evaluate the
performance of the entrance channel to the Cabo Riviera marina, currently under construction.
Project work included model development and validation, development of the offshore wave
climate used to drive the nearshore wave model, and implementation of the model to evaluate wave
heights within the entrance channel for a variety of wave directions. Results of the modeling were
used to inform an evaluation of sedimentation in the navigation channel as well as impacts to
nearshore coastal processes.
Leeway Sailing Center Coastal Hazards Analysis I City of Long Beach I Long Beach, California
Dr. Ketteridge was the senior coastal engineer responsible for conducting an existing and future
coastal hazards analysis for the Leeway Sailing Center in Long Beach, California, in support of
proposed renovations to the buildings and fixed pier at that project site. The work included
developing estimates of winds, waves, and water levels at the site to evaluate present day and future
coastal hazards that could impact the facility. Impacts due to sea level rise estimates for the years
2050 and 2064 (the end of the design life for the structures) were evaluated following guidance
developed by the California Coastal Commission.
1
Matthew R. Henderson, P.E.
Senior Managing Engineer
' Education: M.S., Coastal and Oceanographic Engineering, University of Florida, 1999; B.S., Civil Engineering,
Worcester Polytechnic Institute, 19911 Professional Engineer, State of New York; Loss Prevention System
Training Certification
' Mr. Henderson is an experienced coastal and environmental engineer. He has acquired more than 20
years of combined experience serving private and government clients throughout the United States
' in the areas of coastal engineering, hurricane surge modeling, wave modeling, hydraulics and
hydrodynamics, riverine flood modeling, and sediment erodability and stability assessments. Mr.
Henderson has specialized expertise in modeling hurricane storm surges for bays and estuaries on
t the Gulf of Mexico (including Louisiana, Mississippi, and Florida) and Atlantic Coast, including
Chesapeake Bay for the Maryland Port Administration and Maryland Environmental Service. He has
extensive experience developing two-dimensional (2-D) hydrodynamic and wave models, including
the Advanced Circulation (ADCIRC), M2D, DELFT3D-FLOW, and Steady State Spectral WAVE (STWAVE)
and SWAN. Mr. Henderson has developed models of large bays and estuary systems and evaluated
temporal and spatial distributions of tides and currents, tidal flows, rare hurricane events, waves, and
' freshwater flows. Mr. Henderson has performed shoreline erosion and protection designs for
waterfront and restoration projects.
' Project Experience
Dredged Material Disposal Modeling I US Army Corps of Engineers I Monterey Bay, California
' While at another firm, Mr. Henderson served as a Senior Engineer involved with dredged material
disposal modeling supporting a risk -based evaluation of dredged material placement from Moss
Landing Harbor. Fate and transport of DDT -containing dredged material from a submerged
1 nearshore disposal pipeline was evaluated to predict impacts on exposure levels in Monterey
Canyon. The BANG1 D turbidity current model was used to determine the distance down -canyon
that a turbidity current could transport DDT -containing dredged material. Water column suspended
sediment concentrations during dredged material placement were estimated using the Suspended
Sediment Fate (SSFATE) model. Ambient and time -series water column and sediment
' concentrations were computed for each exposure area. Model results were used to establish
exposure areas for receptors within canyon and on canyon shelf.
Port of Gulfport Storm Surge Analysis and Shoreline Protection Design I Mississippi State Port
' Authority I Gulfport, Mississippi
Mr. Henderson was the senior coastal engineer responsible for hydrodynamic and wave modeling to
' develop coastal engineering design parameters for the site. Hurricane simulations were performed
using the U.S. Army Corps of Engineers ADCIRC model and the STWAVE model. Mr. Henderson used
model predictions to design the coastal shoreline protection.
1
11
I
Michael Whelan, P.E.
Senior Managing Engineer
' Education: M.S., Geotechnical Engineering, Massachusetts Institute of Technology, 1995;
M.S., Environmental Engineering, Georgia Institute of Technology, 1992; B.S., Geological Engineering,
Colorado School of Mines, 19901 Professional Engineer, State of California 1 40-hour HAZWOPER Trained
' Michael Whelan's 17 years of experience as a civil, environmental, and geotechnical engineer includes
management, design, and oversight of sediment remediation, restoration, monitoring, and
development projects for offshore and upland sites. His extensive civil and sediment design
' experience allows him to develop cost-effective and readily implemented design and construction
approaches for remediation and restoration projects involving waterfront cleanup and construction,
' river and shoreline improvements, stabilization of landslide areas and offshore slopes, comparative
evaluations of design alternatives, creation of plans, specifications, and cost estimates, bidding and
contractor selection, and construction management.
' Project Experience
Rhine Channel Contaminated Sediment Cleanup I City of Newport Beach, California
Mr. Whelan is Anchor QEA's lead engineer for the engineering evaluation and development of
conceptual cost estimates for various remedial alternatives of contaminated sediment in Newport Harbor
t and the Rhine Channel, a waterway area heavily used by public, business, and industrial interests. His
responsibilities include determining overall volume of impacted sediments, developing cost-effective
and technically feasible methods for removing or managing sediments, and reviewing structural
' conditions of existing seawalls and facilities in the channel. Mr. Whelan's engineering findings and
conclusions have been documented in a Draft Feasibility Study and Alternatives Evaluation.
Port of Hueneme Maintenance Dredging and CAD Site Construction I Oxnard Harbor District
' Oxnard, California
Mr. Whelan was the lead civil and environmental engineer and project manager for this project involving
development of a multi-user confined aquatic disposal (CAD) site for contaminated sediments within
Port Hueneme. The project comprised three phases: excavating a large pit in the middle of the harbor
and placing clean sand onto an adjacent beach; dredging contaminated sediment from the Federal
' Channel, Oxnard Harbor District docks, and Navy docks and placing the material into the CAD cell; and
constructing a clean cap of sand on top of the contaminated layer to seal the cell and prevent chemical
migration. Design elements included dredging design, resistance to erosion, modeling of chemical
' breakthrough and water quality impacts, and consolidation of materials placed in the CAD. Mr. Whelan
continues to act as the lead engineer for post -construction monitoring surveys.
' Holly Street Landfill Cleanup/Whatcom Creek Estuary Restoration I City of Bellingham Parks
Department I Bellingham, Washington
Mr. Whelan was the lead design engineer for this project that included excavating and capping both
' sides of the creek shoreline with materials configured to stabilize the banks, isolate chemical
contaminants in the underlying refuse and soil, and withstand a 100-year flow event. Mr. Whelan
incorporated habitat restoration elements into the design, including anchored and unanchored large
' woody debris and a rock berm to create an intertidal side channel.
Robert Sherwood, P.E.
Waterfront Engineer
Education: B.S., Civil Engineering, University of California, Irvine,1999; Coastal Engineering
Certificate, Old Dominion University, 20111 Professional Engineer, State of California
Robert Sherwood has worked as a project engineer on a wide range of projects, including the design of
' boat docks and marinas, boat launch ramp facilities, plazas and promenades, bulkheads and shore
protection, utilities and landside improvements, and dredging and lake restoration projects. Mr.
Sherwood has also been involved with the inspections of bridges, docks, wharves, and bulkheads both
above and below water. He has assisted clients with initial feasibility studies, as well as obtaining
grants for waterfront facilities, and is typically involved with a project from the planning stages through
t the end of construction. His ocean engineering experience includes public agency projects and several
projects in Orange County.
' Project Experience
Marina Park I City of Newport Beach I Newport Beach, California
Mr. Sherwood was responsible for the waterfront aspects of the Marina Park Project, which
' encompassed a 10.5-acre site and involved the construction of a public park and a
24,000-square-foot Community and Sailing Center building, as well as a 23-slip marina which
required new bulkheads and dredging of the basin. Coordination with concurrent project landside
improvements and placement of beach quality sand and dredge material were critical to the success
of this project.
' Sunset Aquatic Marina I Goldrich & Kest Industries, LLC I Huntington Beach, California
Mr. Sherwood was the project engineer in charge of new dock layout, construction documents,
permitting, and construction support services for a 240-slip marina in Huntington Harbour.
' Reconfiguration of the marina reflected the current trends in boating toward wider and larger boats,
incorporating an Americans -with -Disabilities -Act -accessible gangway and a vessel pump -out station.
Port of Hueneme Shore Protection and Waterfront Access I Oxnard Harbor District I Port Hueneme,
California
Mr. Sherwood was the project engineer overseeing the drawings and cost estimate for the
' reconstruction of more than 3,000 feet of shore protection, as well as development of the adjacent
land behind the slope for public access. Landside improvements included a 24-foot-wide
maintenance/pedestrian/bicyclist access roadway/promenade, plaza areas, and parking areas.
' Alamitos Bay Marina I City of Long Beach, Marine Bureau I Long Beach, California
Mr. Sherwood was the lead engineer on the design -build team responsible for coordinating the
' drawings for all disciplines on the project to replace docks for 1,625 boat slips and landside
improvements in Basins 1 to 7 for the Alamitos Bay Marina.
I
1
1
1
1
1
1
Tom Wang
Principal Engineer/Senior Partner
Education: B.S., Civil Engineering, University of Washington, 1990 1 Professional Engineer, State of
Washington; Hazardous Waste Operations and Emergency Response Certified
Thomas Wang has more than 25 years of experience managing and designing a diverse range of
marine projects, both in the United States and internationally, from the initial planning and
permitting stages through design and construction. Unlike traditional coastal engineers, Mr. Wang
has extensive experience developing innovative solutions that balance the engineering challenges
(e.g., safety and stability) when working in the nearshore environment against resource agency
objectives to provide greater environmental benefit and sustainable development or restoration.
Mr. Wang has led the coastal engineering design on several nationally award winning beach
restoration projects.
Mr. Wang has successfully integrated coastal engineering, dredging, dredged material beneficial
1 reuse, marine geotechnical engineering, and constructability issues on many complex marine
development and maintenance projects. He is an internationally recognized dredging expert and
was selected as the Western Dredging Association's 2004 "Dredger of the Year." The U.S. Army Corps
1 of Engineers (USACE) selected Mr. Wang to be the U.S. representative to PIANC for developing
dredging best management practices guidance.
1 Project Experience
1
1
1
1
1
11
1
1
On -call Coastal Planning Indefinite Delivery, Indefinite Quantity (IDIQ) I U.S. Army Corps of Engineers,
Los Angeles District I Los Angeles, California
Mr. Wang was the program manager for this multi -year contract that included maintenance
dredging design, sediment remediation design, sediment characterization, programmatic sediment
management, marine geotechnical investigations, coastal engineering analyses, water quality
monitoring, National Environmental Policy Act review, and construction management and
environmental compliance support on multiple projects in Southern California. One project, a joint
effort by USACE, US Navy, and Port Hueneme, won multiple awards, including the 2009 Secretary of
Defense Environmental Restoration Team Award.
Port of Long Beach On -call Construction Management I Port of Long Beach, California
Mr. Wang has provided technical services for dredging, numerical modeling of sediment transport,
water quality evaluation, and oceanographic physical processes evaluation. These efforts were
conducted in support of ongoing dredging and confined disposal facility construction projects.
Campbell Shipyard Remediation, Habitat Restoration, and Site Redevelopment I Port of San Diego,
California
Mr. Wang was the project manager for this complex cleanup project conducted under a Cleanup and
Abatement Order. The site was redeveloped for Hilton Hotel use. The project included seawall repair
and replacement, soil cleanup, remedial dredging, habitat restoration, sheetpile wall breakwater,
engineered cap, mole pier retrofit, propwash and wave erosion protection, shipway demolition, and
utility relocation.
1
EXHIBIT "B"
Payment Schedule (Hourly Payment)
A Hourly Rate
CONSULTANT'S fees for such services shall be based upon the following hourly rate and cost
schedule
B Travel Charges for time during travel are not reimbursable
C Billing
All billing shall be done monthly in fifteen (15) minute increments and matched to an
appropriate breakdown of the time that was taken to perform that work and who
performed it
2 Each month's bill should include a total to date That total should provide, at a glance,
the total fees and costs incurred to date for the project
3 A copy of memoranda, letters, reports, calculations and other documentation prepared
by CONSULTANT may be required to be submitted to CITY to demonstrate progress
toward completion of tasks In the event CITY rejects or has comments on any such
product, CITY shall identify specific requirements for satisfactory completion
4 CONSULTANT shall submit to CITY an invoice for each monthly payment due
Such invoice shall
A) Reference this Agreement,
B) Describe the services performed,
C) Show the total amount of the payment due,
D) Include a certification by a principal member of CONSULTANT's firm that
the work has been performed in accordance with the provisions of this
Agreement, and
E) For all payments include an estimate of the percentage of work completed
Upon submission of any such invoice, if CITY is satisfied that CONSULTANT is
making satisfactory progress toward completion of tasks in accordance with this
Agreement, CITY shall approve the invoice, in which event payment shall be made
within thirty (30) days of receipt of the invoice by CITY Such approval shall not be
unreasonably withheld If CITY does not approve an invoice, CITY shall notify
CONSULTANT in writing of the reasons for non -approval and the schedule of
performance set forth in Exhibit "A" may at the option of CITY be suspended until
the parties agree that past performance by CONSULTANT is in, or has been brought
into compliance, or until this Agreement has expired or is terminated as provided
herein
Exhibit B
Any billings for extra work or additional services authorized in advance and in writing
by CITY shall be invoiced separately to CITY Such invoice shall contain all of the
information required above, and in addition shall list the hours expended and hourly
rate charged for such time Such invoices shall be approved by CITY if the work
performed is in accordance with the extra work or additional services requested, and if
CITY is satisfied that the statement of hours worked and costs incurred is accurate
Such approval shall not be unreasonably withheld Any dispute between the parties
concerning payment of such an invoice shall be treated as separate and apart from the
ongoing performance of the remainder of this Agreement
Exhibit B
Anchor QEA, L.L.C.
2015 BILLING RATES*
Professional Level Hourlv Rates
Principal CM'/Engmeer/LA2/Planner/Scientist
Senior Managing Analyst/CMIEngmeer/LA/Planner/Scientist .
Managing Analyst/CM/Engineer/LA/Planner/Scientist
Senior Analyst/CM/Engineer/LA/Planner/Scientist
Staff 3 Analyst/CM/Engineer/LA/Planner/Scientist ...
Staff 2 Analyst/CM/Engineer/LA/Planner/Scientist
Staff 1 Analyst/CM/Engineer/LA/Planner/Scientist
Senior CAD Designer .....
CAD Designer
Technician . . . ... .. ....
Technical Editor
Project Coordinator
Special Hourly Rates
$230
... $203
$189
$168
.. ... $148
$133
... $112
$117
$98
....... $95
... $98
$94
National expert consultant $377
All work by a testifying expert 1 5 times professional level rate
EXPENSE BILLING RATES
Expense Rates
Computer Modeling (per hour) .... $10 00
Graphic Plots (varies with plot size) $3-6/sf
Mileage (per mile) Current Federal Standard
FEE ON LABOR AND EXPENSE CHARGES
Subcontracts/subconsultants 10%
Travel and other direct costs . ..... .... ... .. . 10%
Field equipment & supplies .. ........ ... .... 10%
1 CM = Construction Manager
2 LA = Landscape Architect
3 CAD = Computer Aided Design
*A 4% annual escalation will be applied on January 1 of each following year
2015 List of Consultants Submitted RFQ
Vendor Name
Vendor Name
Advantec Consulting Engineers, Inc
KCG Consulting Group
AECOM Technical Services, Inc
Kleinfelder
AESCO, Inc
KOA Corporation
AKM Consulting Engineers
Koury Engineering & Testing, Inc
Albert Grover & Associates
OFF Consulting Engineers
Alta Planning + Design
Langan Engineering and Environmental Inc
American Geotechnical, Inc
LEE & RO, Inc
Anchor QEA
Leighton Consulting, Inc
AndersonPenna Partners, Inc
MARRS Services, Inc
APA Engineering, Inc
McLean & Schultz
Axiom Corporation
Mirjahangir Engineering/Amiran Construction Co
BKF Engineers
Moffatt & Nichol
Case Land Surveying, Inc
MTGL, Inc
CivilSource, Inc
Myers Houghton & Partners, Inc
Civil Works Engineering
Ninyo & Moore
Converse Consultants
Noble Consultants, Inc
COWI Marine North America
Onward Engineering
CWE
Pacific Advanced Civil Engineering, Inc
D Woolley & Associates
PENCO Engineering, Inc
DKS Associates
Professional Service Industries
DMc Engineering
Psomas
ERSC Inc
Quantum Quality Consulting, Inc
FPL & Associates, Inc
RBF Consulting
Fugro Consultants, Inc
Richard Brady & Associates
Geocon West, Inc
SA Associates
Geo-Environmental, Inc
Sequoia Consultants
Geologic Associates, Inc
Stetson Engineers Inc
GEOSCIENCE Support Services, Inc
Tait & Associations, Inc
Geosyntec Consultants
Terracon Consultants, Inc
GHD
Tetra Tech
GMU Geotechnical, Inc
Towill, Inc
Group Delta Consultants, Inc
Transpo Group
Guida Surveying Inc
TTG Engineers
Gwynne Pugh Urban Studio
Twining, Inc
Harris & Associates, Inc
VA Consulting, Inc
IDS Group, Inc
W G Zimmerman Engineering, Inc
Interwest Consulting Group
West Yost Associates
Iteris
Westberg + White
Joseph C Truxaw and Associates, Inc
Willdan Engineering
PROFESSIONAL SERVICES CONTRACT BETWEEN
THE CITY OF HUNTINGTON BEACH AND
ANCHOR QEA, LLC
FOR
ON CALL CIVIL ENGINEERING SERVICES
Table of Contents
1
Scope of Services
1
2
City Staff Assistance
2
3
Term, Time of Performance
2
4
Compensation
... 2
5
Extra Work
.2
6
Method of Payment
3
7
Disposition of Plans, Estimates and Other Documents
3
8
Hold Harmless
3
9
Professional Liability Insurance
4
10
Certificate of Insurance
5
11
Independent Contractor
6
12
Termination of Agreement
6
13
Assignment and Delegation
6
14
Copynghts/Patents
7
15
City Employees and Officials
..7
16
Notices
7
17
Consent
8
18
Modification
8
19
Section Headings
8
20
Interpretation of this Agreement
8
21
Duplicate Original
9
22
Immigration
.9
23
Legal Services Subcontracting Prohibited
9
24
Attorneys Fees
10
25
Survival
10
26
Governing Law
10
27
Signatories
10
28
Entirety
10
29
Effective Date
11
ANCHOR
OEA "
27201 Puerta Real, Suite 350
Mission Viejo, California 92691
Phone 949 347 2780
May 19, 2015
Duncan Lee, P.E
City of Huntington Beach, Public Works Department
2000 Main Street
Huntington Beach, California 92648
Re- Anchor QEA Contract for On -call Ocean Engineering Services
Dear Mr Lee
The purpose of this letter is to describe the governance of Anchor QEA as it relates to our
contract signing authority. Anchor QEA is a limited liability corporation (LLC, i e.,
partnership) founded in Seattle, Washington, in 1997. We currently have 37 general
partners who are also shareholders in the firm. All 37 partners have the legal authority to
execute a contract on behalf of the LLC per the terms of our internal operating agreement.
Company management occurs via an Executive Committee comprised of seven general
partners. I am currently one of the seven members of the Executive Committee.
Within California, we have three general partners who manage our local operations. One
partner is located in Northern California and two in Southern California. The attached
contract was executed by me and Dr Shelly Anghera, the other local partner We do have a
chief financial officer, Jon Rodriguez, but he is not currently a partner and thus does not
possess the legal authority to execute a contract on behalf of the LLC
Attached to this letter are two copies of the signed contract along with a copy of our standard
rate sheet for 2015. Randy Mason, our principal engineer and client lead for this work,
would be billed at the principal category according to the rate sheet Specific technical staff
would be assigned to the project based on the nature of the task assignment.
www anchorgea corn
Mr Duncan Lee, P E , City of Huntington Beach
May 19, 2015
Page 2
Please let me know if the City of Huntington Beach requires any further clarifications or
documentation to support our contract approval
Sincer y,
Steve Cappellino
Partner
Anchor QEA, LLC
2015 List of Consultants Submitted RFQ
Vendor Name
Vendor Name
Advantec Consulting Engineers, Inc
KCG Consulting Group
AECOM Technical Services, Inc
Kleinfelder
AESCO, Inc
KOA Corporation
AKM Consulting Engineers
Koury Engineering & Testing, Inc
Albert Grover & Associates
KPFF Consulting Engineers
Alta Planning+ Design
Langan Engineering and Environmental Inc
American Geotechnical, Inc
LEE & RO, Inc
Anchor QEA
Leighton Consulting, Inc
AndersonPenna Partners, Inc
MARRS Services, Inc
APA Engineering, Inc
McLean & Schultz
Axiom Corporation
Mirjahangir Engineering/Amiran Construction Co
BKF Engineers
Moffatt & Nichol
Case Land Surveying, Inc
MTGL, Inc
CivilSource, Inc
Myers Houghton & Partners, Inc
Civil Works Engineering
Ninyo & Moore
Converse Consultants
Noble Consultants, Inc
COWI Marine North America
Onward Engineering
CWE
Pacific Advanced Civil Engineering, Inc
D Woolley & Associates
PENCO Engineering, Inc
DKS Associates
Professional Service Industries
DMc Engineering
Psomas
ERSC Inc
Quantum Quality Consulting, Inc
FPL & Associates, Inc
RBF Consulting
Fugro Consultants, Inc
Richard Brady & Associates
Geocon West, Inc
SA Associates
Geo-Environmental, Inc
Sequoia Consultants
GeoLogic Associates, Inc
Stetson Engineers Inc
GEOSCIENCE Support Services, Inc
Tait & Associations, Inc
Geosyntec Consultants
Terracon Consultants, Inc
GHD
Tetra Tech
GMU Geotechnical, Inc
Towill, Inc
Group Delta Consultants, Inc ITranspo
Group
Guida Surveying Inc
TTG Engineers
Gwynne Pugh Urban Studio
Twining, Inc
Harris & Associates, Inc
VA Consulting, Inc
IDS Group, Inc
W G Zimmerman Engineering, Inc
Interwest Consulting Group
West Yost Associates
Iteris
Westberg + White
Joseph C Truxaw and Associates, Inc
Wilidan Engineering
AC RE]i CERTIFICATE F LIABILITY INSURANCE
DATE(MMtDD1YYYY)
5/28/2015
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER.
IMPORTANT If the certificate holder is an ADDITIONAL INSURED, the pollcy(ies) must be endorsed If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement s
PRODUCER
Servco Pacific Insurance
1100 Dexter Ave N
Ste 220
CONTACT
Kpllv
-NAME
PHONE FA/C No ) 2Q6-260-2903
E-MAIL
INSURERS AFFORDING COVERAGE
NAIC #
Seattle WA 98109
INSURER A Travelers Indemnity Company of Amer .25666
INSURED 645
INSURER B Lloyds. of London`
INSURER C
Anchor QEA, LLC
INSURER D
720 Olive Way
Suite 1900
Seattle WA 98101
INSURER E
INSURER F
�Ka]7t3:i_FCI li :iityw�'Illl:2.11li?il:id: a _ :a1Ttk�[rlE��lgl'1:1�:
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS
INSR TYPE OF INSURANCE
LTR
ADDLISUOR
INSR
WVD
POLICY NUMBER
POLICY EFF i POUCY EXP
MMtDD/YYYY MM@DrYYYY
LIMITS
A GENERAL LIABILITY I
Y
6805251 LO34
10/10/2014
i O/10/2015
EACH OCCURRENCE
$1,000 000
X C_OMMERCIAL GENERAL LIABILITY
AMA T ENiED
PREMISES Ea occurrence
$1,000,000
MED EXP (Any aria person)
$10,000
_
1 'I CLAIMS MADE JA I OCCUR
PERSONAL &ADV INJURY
51 000 000
�X Employers Llab
GENERAL AGGREGATE
$2,000,000
I� v
r
GEN'L AGGREGATE LIMIT APPLIES PER
PRODUCTS - COMPIOP AGG
$2 000,000
$
l POLICY X , PRO- LOC
AUTOMOBILE LIABILITY
Ea accident;_
BODILY INJURY (Per person)
$
ANY AUTO
AL_ OWNED SCHEDULED
AUTOS AUTOS
NON -OWNED
_j HIREDAUTOS AUTOS
i
BODILY INJURY (Per accident)
$
PROPERTY DAMAGE
fPeraccrdenf
$
$
UMBRELLA LIAB
OCCUR
EACH OCCURRENCE
I $
AGGREGATE
is
EXCESS UABH
CLAIMS-MADE
DED RETENTIONS
is
WORKERS COMPENSATION
WC STATU• OTH-
AND EMPLOYERS' LIABILITY IN
ANY-ROPRIETORIPAR-NERIEXECUTIVE Y�
EEL EACH ACCIDENT
—'-- —
s
EL DISEASE - EA EMPLOYEE
$
{ OFFiCERtMEMBER EXCLUDED?
(Mandatory in NH)
NIA
EL DISEASE POLICY LIMIT
$
If yes describe under
DESCRIPTION OF OPERATIONS below
B
Professional Liability &
Pollution Liability
WW11053140501
0/10/2014
0/10/2016
Each Claim $1 000 000
Aggregate $1,000 000
Deductible $10 000
DESCRIPTION OF OPERATIONS J LOCATIONS I VEHICLES (Attach ACORD 101, Additional Remarks Schedula, 9 more apace is required)
City of Huntington Beach is included as Additional Insured on General Liability policy 30 days notice of cancellation applies
APPROVED AS TO FL-0 M
�w�:iiiaL■s��r3t.�■Ina� •r-••�'.,��-•■t 1•��rllr:utra.rraccs:��:�xw►•Jraa+r�I�t�luaz�
City of Huntington Beach
2000 Main Street
Huntington Beach, CA 92648
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
ACCORDANCE WITH THE POLICY PROVISIONS
AUTHORIZED REPRESENTATIVE
✓r
U IUBU-2010 AC;VKU C;UK1'VKA i iVN An rtgnis reserves
ACORD 26 (2010/06) The ACORD name and logo are registered marks of ACORD
Uity of Huntington
2000 Main Street ® Huntington Beach, CA 92648
(714) 536-5227 ® www.huntingtonbeachca.gov
Office of the City Clerk
Joan L. Flynn, City Clerk
July 23, 2015
Anchor QEA, LLC
Attn Randy Mason, P E
7755 Center Avenue, Suite 1060
Huntington Beach, CA 92647
Dear Mr Mason
Enclosed for your records is a copy of the fully executed "Professional Services Contract
Between The City of Huntington Beach and Anchor QEA, LLC for On Call Civil Engineering
Services "
Sincerely,
Joan L Flynn, CIVIC
City Clerk
J F pe
Enclosure
Sister Cities Anjo, Japan ® Wartakere, New Zealand