HomeMy WebLinkAboutNoble Consultants - 2015-07-207
}
Dept ID PW 15-032 Page 1 of 2
Meeting Date 7/20/2015
CITY OF HUNTINGTON BEACH
REQUEST FOR CITY COUNCIL ACTION
MEETING DATE: 7/20/2015
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Fred A Wilson, City Manager
PREPARED BY: Travis K Hopkins, PE, Director of Public Works
SUBJECT: Approve and authorize execution of three Professional Services Contracts for
On -Call Civil (Ocean) Engineering Services with Anchor QEA, LLC , Moffatt &
Nichol, and Noble Consultants, Inc, each in the amount of $350,000
Statement of Issue
The Public Works Department requires professional civil engineering services on an on -call or as
needed basis to support staff for the design and construction of the capital improvement projects
related to ocean engineering services
Financial Impact
The City's FY 2014/15 Capital Improvement Program (CIP) Budget was adopted on September 2,
2014 and totals $42 8 million (All Funds) for approved projects citywide Each approved CIP
project has a budget containing sufficient funding for design, environmental, engineering,
construction, project management and other required costs The three (3) recommended civil
engineering contracts, totaling $1 05 million, will be funded within each project's individual CIP
budget, as needed As such, no additional funding is required by this action
Recommended Action
A) Approve and authorize the Mayor and City Clerk to execute "Professional Services Contract
Between The City of Huntington Beach and Anchor QEA, LLC for On -Call Civil Engineering
Services" in the amount of $350,000, and,
cS
B) Approve and authorize the Mayor and City Clerk to execute "Professional Services Contract
Between The City of Huntington Beach and Moffatt & Nichol for On -Call Civil Engineering Services"
in the amount of $350,000, and,
C) Approve and authorize the Mayor and City Clerk to execute 'Professional Services Contract
Between The City of Huntington Beach and Noble Consultants, Inc for On -Call Civil Engineering
Services" in the amount of $350,000
Alternative Action(s)
Do not authorize the contracts and direct staff with an alternate action Budgeted Capital Projects
could be delayed until new contracts are approved
Analysis
On January 26, 2015 the City advertised a Request for Qualifications ("RFQ") for On -Call
Engineering & Professional Consulting Services Proposals were requested and submitted in
compliance with Chapter 3 03 of the Huntington Beach Municipal Code Seventy eight (78)
HB -167- Item 11. - 1
Dept ID PW 15-032 Page 2 of 2
Meeting Date 7/20/2015
proposals were received for the following eight categories of Civil Engineering services, Water
Engineering, Development Plan Checking and Entitlement Review Services, Civil/Sewer
Engineering, Geotechnical and Materials Testing, Traffic Engineering, Survey, Ocean Engineering,
and Architectural Services In accordance with qualifications based selected procurement per the
Federal "Brooks Act", State SB 419 and the City of Huntington Beach Municipal Code Section 3 03
"Professional Services" the Public Works Department established a review board Each firm stated
their engineering category of expertise with their proposal, and proposals were then evaluated and
ranked by eight (8) review boards established by the Public Works Department At a minimum the
top three (3) firms were selected for each category to increase opportunity for competitive
proposals for future projects from qualified on -call consultants
The three (3) contracts recommended in this request for council action (RCA) are for support staff
for the design and construction of the capital improvement projects related to coastal features such
as beaches and sea walls These services have historically been utilized to supplement City staff to
meet annual CIP goals, as an extension of staff and/or to provide required expertise for unique
projects It is anticipated that these services will be required based on past years Each project is
evaluated on a case by case basis to determine if these as -needed contract services are
necessary Other categories and groupings of On -Call consulting services will be brought to the
City Council separately for approval
The City's Capital Improvement Program ("CIP") is approximately $42 8 million in Fiscal Year
2014/15, and exceeds $52 million with continuing of funds for projects approved from previous
years Typical design and construction support cost from use of consultants on a CIP project can
vary between ten (10) to twenty (20) percent of total costs for a CIP project Therefore, it is
practical to conservatively assume minimum annual consultant costs would be around $5 million to
the City for total CIP projects, or approximately $15 million over the next three (3) years
Some of the typical projects for ocean on -call design services include,
• Bluff top erosion and stabilization
• City Beach and harbor beaches sand replenishment
• Harbor Dredging analysis and general support
• Coastal Commission expertise
• Pier design and maintenance
With the City bordered by the Pacific Ocean, local residents and tourists are drawn to the beaches
during all seasons The City is responsible for the preservation and enhancement of our existing
beaches to continue beneficial use by the public This preservation work is a joint effort between
the County of Orange and all coastal cities and is a specialty service Therefore, three (3)
consultants were selected to meet projected workload over the next 3 years The anticipated need
for ocean engineering services is $1,050,000 over the term of the contract, or an annual average of
$350,000
Public Works Commission Action: Not required
Environmental Status Not applicable
Strategic Plan Goal Enhance and maintain infrastructure
Attachment(s)
1 Professional Services Contract between the City of Huntington Beach and Anchor QEA,
,� LLC for On -Call Civil Engineering Services
&Nichol
'r2 Professional Services Contract between the City of Huntington Beach and Moffatt
�r
Professional Services Contract between the City of Huntington Beach and Nob
Consultants, Inc for On -Call Civil Engineering Services
Item 11. - 2 HB -168-
PROFESSIONAL SERVICES CONTRACT BETWEEN
THE CITY OF HUNTINGTON BEACH AND
NOBLE CONSULTANTS, INC
FOR i
ON CALL CIVIL ENGINEERING SERVICES
THIS AGREEMENT ("Agreement") is made and entered into by and between the City of
Huntington Beach, a municipal corporation of the State of California, hereinafter referred to as
"CITY," and Noble Consultants, Inc, a California corporation, hereinafter referred to as
"CONSULTANT."
WHEREAS, CITY desires to engage the services of a consultant to provide on call civil
engineering services; and
Pursuant to documentation on file in the office of the City Clerk, the provisions of the
Huntington Beach Municipal Code, Chapter 3.03, relating to procurement of professional service
contracts have been complied with; and
CONSULTANT has been selected to perform these services,
NOW, THEREFORE, it is agreed by CITY and CONSULTANT as follows:
1. SCOPE OF SERVICES
CONSULTANT shall provide all services as described in Exhibit "A," which is
attached hereto and incorporated into this Agreement by this reference. These services shall
sometimes hereinafter be referred to as the "PROJECT."
CONSULTANT hereby designates Ronald M. Noble, who shall represent it and be
its sole contact and agent in all consultations with CITY during the performance of this Agreement.'
2. CITY STAFF ASSISTANCE
CITY shall assign a staff coordinator to work directly with CONSULTANT in the
performance of this Agreement.
agree/ surfnet/professional svcs mayor 1 of 11
10/12
3. TERM, TIME OF PERFORMANCE
Time is of the essence of this Agreement. The services of CONSULTANT are to
commence on �(,iL,�% /XD , 20,4:-?� (the "Commencement Date") This Agreement
shall automatically terminate three (3) years from the Commencement Date, unless extended or
sooner terminated as provided herein. All tasks specified in Exhibit "A" shall be completed no
later than three (3) years from the Commencement Date The time for performance of the tasks
identified in Exhibit "A" are generally to be shown in Exhibit "A." This schedule may be
amended to benefit the PROJECT if mutually agreed to in writing by CITY and CONSULTANT
In the event the Commencement Date precedes the Effective Date, CONSULTANT
shall be bound by all terms and conditions as provided herein
4. COMPENSATION
In consideration of the performance of the services described herein, CITY agrees to
pay CONSULTANT on a time and materials basis at the rates specified in Exhibit "B," which is
attached hereto and incorporated by reference into this Agreement, a fee, including all costs and
expenses, not to exceed Three Hundred and Fifty Thousand Dollars ($ 350,000 )
� �:r1.7e\1.I MW
In the event CITY requires additional services not included in Exhibit "A" or
changes in the scope of services described in Exhibit "A," CONSULTANT will undertake such
work only after receiving written authorization from CITY Additional compensation for such extra
work shall be allowed only if the prior written approval of CITY is obtained.
6 METHOD OF PAYMENT
CONSULTANT shall be paid pursuant to the terms of Exhibit "B."
agree/ surfnet/professional Svcs mayor 2 of 11
10/12
7. DISPOSITION OF PLANS, ESTIMATES AND OTHER DOCUMENTS
CONSULTANT agrees that title to all materials prepared hereunder, including,
without limitation, all original drawings, designs, reports, both field and office notices, calculations,
computer code, language, data or programs, maps, memoranda, letters and other documents, shall
belong to CITY, and CONSULTANT shall turn these materials over to CITY upon expiration or
termination of this Agreement or upon PROJECT completion, whichever shall occur first. These
materials may be used by CITY as it sees fit.
8. HOLD HARMLESS
CONSULTANT hereby agrees to protect, defend, indemnify and hold harmless
CITY, its officers, elected or appointed officials, employees, agents and volunteers from and against
any and all claims, damages, losses, expenses, judgments, demands and defense costs (including,
without limitation, costs and fees of litigation of every nature or liability of any kind or nature)
arising out of or in connection with CONSULTANT's (or CONSULTANT's subcontractors, if any)
negligent (or alleged negligent) performance of this Agreement or its failure to comply with any of
its obligations contained in this Agreement by CONSULTANT, its officers, agents or employees
except such loss or damage which was caused by the sole negligence or willful misconduct of
CITY. CONSULTANT will conduct all defense at its sole cost and expense and CITY shall
approve selection of CONSULTANT's counsel This indemnity shall apply to all claims and
liability regardless of whether any insurance policies are applicable. The policy limits do not act as
limitation upon the amount of indemnification to be provided by CONSULTANT.
9. PROFESSIONAL LIABILITY INSURANCE
CONSULTANT shall obtain and furnish to CITY a professional liability insurance
policy covering the work performed by it hereunder. This policy shall provide coverage for
CONSULTANT's professional liability in an amount not less than One Million Dollars
agree/ sur&iet/professional svcs mayor 3 of 11
10/12
($1,000,000.00) per occurrence and in the aggregate. The above -mentioned insurance shall not
contain a self -insured retention without the express written consent of CITY; however an insurance
policy "deductible" of Ten Thousand Dollars ($10,000.00) or less is permitted. A claims -made
policy shall be acceptable if the policy further provides that•
A The policy retroactive date coincides with or precedes the initiation of the
scope of work (including subsequent policies purchased as renewals or
replacements).
B. CONSULTANT shall notify CITY of circumstances or incidents that might
give rise to future claims.
CONSULTANT will make every effort to maintain similar insurance during the
i
required extended period of coverage following PROJECT completion. If insurance is terminated
for any reason, CONSULTANT agrees to purchase an extended reporting provision of at least two
(2) years to report claims arising from work performed in connection with this Agreement
If CONSULTANT fails or refuses to produce or maintain the insurance required by
this section or fails or refuses to furnish the CITY with required proof that insurance has been
procured and is in force and paid for, the CITY shall have the right, at the CITY's election, to
forthwith terminate this Agreement. Such termination shall not effect Consultant's right to be paid
for its time and materials expended prior to notification of termination. CONSULTANT waives the
right to receive compensation and agrees to indemnify the CITY for any work performed prior to
approval of insurance by the CITY
10. CERTIFICATE OF INSURANCE
Prior to commencing performance of the work hereunder, CONSULTANT shall
furnish to CITY a certificate of insurance subject to approval of the City Attorney evidencing the
foregoing insurance coverage as required by this Agreement, the certificate shall:
agree/ surfnet/professional svcs mayor 4 of 11
10/12
A. provide the name and policy number of each carrier and policy;
B. state that the policy is currently in force; and
C. shall promise that such policy shall not be suspended, voided or canceled by
either party, reduced 1n coverage or in limits except after thirty (30) days'
prior written notice; however, ten (10) days' prior written notice in the event
of cancellation for nonpayment of premium
CONSULTANT shall maintain the foregoing insurance coverage in force until the
work under this Agreement is fully completed and accepted by CITY.
The requirement for carrying the foregoing insurance coverage shall not derogate
from CONSULTANT's defense, hold harmless and indemnification obligations as set forth in this
Agreement. CITY or its representative shall at all times have the right to demand the original or a
copy of the policy of insurance. CONSULTANT shall pay, in a prompt and timely manner, the
premiums on the insurance hereinabove required.
11. INDEPENDENT CONTRACTOR
CONSULTANT is, and shall be, acting at all times in the performance of this
Agreement as an independent contractor herein and not as an employee of CITY. CONSULTANT
shall secure at its own cost and expense, and be responsible for any and all payment of all taxes,
social security, state disability insurance compensation, unemployment compensation and other
payroll deductions for CONSULTANT and its officers, agents and employees and all business
licenses, if any, in connection with the PROJECT and/or the services to be performed hereunder.
12. TERMINATION OF AGREEMENT
All work required hereunder shall be performed in a good and workmanlike manner.
CITY may terminate CONSULTANT's services hereunder at any time with or without cause, and
whether or not the PROJECT is fully complete. Any termination of this Agreement by CITY shall
agree/ surfiiet/professional svcs mayor 5 of 11
10/12
be made in writing, notice of which shall be delivered to CONSULTANT as provided herein. In the
event of termination, all finished and unfinished documents, exhibits, report, and evidence shall, at
the option of CITY, become its property and shall be promptly delivered to it by CONSULTANT.
13 ASSIGNMENT AND DELEGATION
This Agreement is a personal service contract and the work hereunder shall not be
assigned, delegated or subcontracted by CONSULTANT to any other person or entity without the
prior express written consent of CITY. If an assignment, delegation or subcontract is approved, all
approved assignees, delegates and subconsultants must satisfy the insurance requirements as set
forth in Sections 9 and 10 hereinabove.
14. COPYRIGHTS/PATENTS
i
CITY shall own all rights to any patent or copyright on any work, item or material
produced as a result of this Agreement it
15. CITY EMPLOYEES AND OFFICIALS
CONSULTANT shall employ no CITY official nor any regular CITY employee in
the work performed pursuant to this Agreement No officer or employee of CITY shall have any
financial interest in this Agreement in violation of the applicable provisions of the California
Government Code
16. NOTICES
Any notices, certificates, or other communications hereunder shall be given either by
personal delivery to CONSULTANT's agent (as designated in Section 1 hereinabove) or to CITY as
the situation shall warrant, or by enclosing the same in a sealed envelope, postage prepaid, and
depositing the same in the United States Postal Service, to the addresses specified below. CITY and
CONSULTANT may designate different addresses to which subsequent notices, certificates or
agree/ surfliet/professional svcs mayor 6 of 11
10/12
other communications will be sent by notifying the other party via personal delivery, a reputable
overnight carrier or U S. certified mall -return receipt requested:
TO CITY:
City of Huntington Beach
ATTN Tom Herbel
2000 Main Street
Huntington Beach, CA 92648
17. CONSENT
TO CONSULTANT:
Noble Consultants, Inc
Attn: Ronald M. Noble
359 Bel Marin Keys Boulevard, #9
Novato, CA 94949
When CITY's consent/approval is required under this Agreement, its
consent/approval for one transaction or event shall not be deemed to be a consent/approval to any
i
subsequent occurrence of the same or any other transaction or event.
a
18. MODIFICATION
No waiver or modification of any language in this Agreement shall be valid unless in
wasting and duly executed by both parties.
19. SECTION HEADINGS
The titles, captions, section, paragraph and subject headings, and descriptive phrase's
at the beginning of the various sections in this Agreement are merely descriptive and are included
solely for convenience of reference only and are not representative of matters included or excluded
from such provisions, and do not interpret, define, limit or describe, or construe the intent of the
parties or affect the construction or interpretation of any provision of this Agreement.
20. INTERPRETATION OF THIS AGREEMENT
The language of all parts of this Agreement shall in all cases be construed as a
whole, according to its fair meaning, and not strictly for or against any of the parties. If any
provision of this Agreement is held by an arbitrator or court of competent jurisdiction to be
unenforceable, void, illegal or invalid, such holding shall not invalidate or affect the remaining
agree/ surfnet/professional Svcs mayor 7 of 11
10/12
covenants and provisions of this Agreement. No covenant or provision shall be deemed dependent
upon any other unless so expressly provided here. As used in this Agreement, the masculine or
neuter gender and singular or plural number shall be deemed to include the other whenever the
context so indicates or requires. Nothing contained herein shall be construed so as to require the
commission of any act contrary to law, and wherever there is any conflict between any provision
contained herein and any present or future statute, law, ordinance or regulation contrary to which
the parties have no right to contract, then the latter shall prevail, and the provision of this
Agreement which is hereby affected shall be curtailed and limited only to the extent necessary to
bring it within the requirements of the law
21. DUPLICATE ORIGINAL
The original of this Agreement and one or more copies hereto have been prepared
and signed in counterparts as duplicate originals, each of which so executed shall, irrespective of the
date of its execution and delivery, be deemed an original. Each duplicate original shall be deemed
an original instrument as against any party who has signed it
22. IMMIGRATION
CONSULTANT shall be responsible for full compliance with the immigration and
naturalization laws of the United States and shall, in particular, comply with the provisions of the
United States Code regarding employment verification.
23. LEGAL SERVICES SUBCONTRACTING PROHIBITED
CONSULTANT and CITY agree that CITY is not liable for payment of any
subcontractor work involving legal services, and that such legal services are expressly outside the
scope of services contemplated hereunder. CONSULTANT understands that pursuant to
Huntington Beach City Charter Section 309, the City Attorney is the exclusive legal counsel for
agree/ surfner/professional svcs mayor 8 of 11
10/12
CITY; and CITY shall not be liable for payment of any legal services expenses incurred by
CONSULTANT.
24. ATTORNEY' S FEES
In the event suit is brought by either party to construe, interpret and/or enforce the
terms and/or provisions of this Agreement or to secure the performance hereof, each party shall bear
its own attorney's fees, such that the prevailing party shall not be entitled to recover its attorney's
fees from the nonprevailing party.
25. SURVIVAL
Terms and conditions of this Agreement, which by their sense and context survive
the expiration or termination of this Agreement, shall so survive.
26. GOVERNING LAW
This Agreement shall be governed and construed in accordance with the laws of the
State of California.
27. SIGNATORIES
Each undersigned represents and warrants that its signature herembelow has the
power, authority and right to bind their respective parties to each of the terms of this Agreement,
and shall indemnify CITY fully for any injuries or damages to CITY in the event that such authority
or power is not, in fact, held by the signatory or is withdrawn.
28. ENTIRETY
The parties acknowledge and agree that they are entering into this Agreement freely
and voluntarily following extensive arm's length negotiation, and that each has had the opportunity
to consult with legal counsel prior to executing this Agreement The parties also acknowledge and
agree that no representations, inducements, promises, agreements or warranties, oral or otherwise,
have been made by that party or anyone acting on that party's behalf, which are not embodied in this
agree/ surf ier/professional svcs mayor 9 of 11
10/12
Agreement, and that that party has not executed this Agreement in reliance on any representation,
inducement, promise, agreement, warranty, fact or circumstance not expressly set forth in this
Agreement. This Agreement, and the attached exhibits, contain the entire agreement between the
parties respecting the subject matter of this Agreement, and supersede all prior understandings and
agreements whether oral or in writing between the parties respecting the subject matter hereof.
29. EFFECTIVE DATE
This Agreement shall be effective on the date of its approval by the City Council.
This Agreement shall expire when terminated as provided herein.
IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed by
and through their authorized officers.
agree/ surfnet/professional svcs mayor 10 of 11
10/12
CONSULTANT,
Noble Consultants, Inc
COMPANY NAME
A California Corporation
print name
ITS: (circle one) Chairm residen ice President
I,
By: <
I/Print
ITS- a Secretary/Chief Financial Officer/Asst
Secretary - Treasurer
CITY OF HUNTINGTON BEACH, a
municipal corporation of the State of
INITIATED AND APPROVED:
irector of Pu 11c orks
agree/ surfnet/professional svcs mayor 11 of 11
10/12
EXHIBIT "A"
A. STATEMENT OF WORK: (Narrative of work to be performed)
CONSULTANT shall provide consulting services on an'as-needed' basis for projects to be
determined during the term of the agreement. During the term of the agreement, CITY may elect to
solicit proposals from CONSULTANT. CITY shall issue task order for each project based upon the
scope of services, work schedule, and fee proposal submitted to CITY for its review and approval.
B. CONSULTANT'S DUTIES AND RESPONSIBILITIES:
CONSULTANT'S duties and responsibilities shall be per CONSULTANT'S Statement of
Qualification (Exhibit A.1), consistent with the City of Huntington Beach Request for
Qualifications for On -Call Engineering & Professional Consulting Services. Upon award, and the
contract period, if CONSULTANT chooses to assign different personnel to the project,
CONSULTANT must submit the names and qualifications of these staff to CITY for approval
before commencing work.
C. CITY'S DUTIES AND RESPONSIBILITIES:
1. Furnish scope of work request for each project.
2. Furnish construction plans and specifications to the CONSULTANT.
D. WORK PROGRAM/PROJECT SCHEDULE:
A project schedule will be developed for each project assigned by CITY.
EXHIBIT A
-A
if QUALIFICATIONS
'essional Consulting Services
Bering Service Category
ity of Huntington Beach
iblic Works Department
February 18, 2015
NOBLE
CONSULTANTS, INC
February 18, 2015
City of Huntington Beach, Fiscal Services Division
2000 Main Street
Huntington Beach, CA 92648
ATTN Mr Jim Slobotan
Cl/CD
RE Proposal for On -Call Engineering & Professional Consulting Services
Ocean Engineering
For the City of Huntington Beach
Dear Mr SloboJ an
In response to your January 26 2015 Request for Qualification, Noble Consultants, Inc (NCI) is
pleased to present our Statement of Qualifications to provide Ocean Engineering on -call
engineering and professional consulting services for the City Included herein are copies of the
completed vendor application forms, a summary of our relevant coastal and ocean engineering
background and experience, and how we propose to staff the anticipated range of services that
may arise over the course of the on -call services agreement
The City's 10-mile long coastal zone includes a string of important public beaches, a significant
small craft harbor complex, a signature ocean pier, and unique estuarine environments As such,
t areas of study that may arise will likely involve shoreline preservation and regional sediment
management issues, coastal flood protection, sea -level rise vulnerability assessment, pier
maintenance, water circulation, coastal and harbor structures, and small craft harbor navigation
and berthing Individual task orders may require close collaboration with protect partners and
U
1
❑ NOVATO 359 BEL MARIN KEYS BLVD , SUITE 9, NOVATO, CA 94949-5637 (415) 884-0727 FAX (415) 884-0735
❑ IRVINE 2201 DUPONT DR, SUITE 830, IRVINE, CA 92612-7509 (949) 752-1530 FAX (949) 752-8381
http //Wvvw nobleconsultants com
Li
F
u
NOBLE CONSULTANTS, INC
Mr Jim Slobojan
Proposal for Professional Engineering Services
On -Call Engineering & Professional Consulting Services
For the City of Huntington Beach
February 18, 2015
Page 2 of 2
stakeholders including the U S Army Corps of Engineers, U S Navy, County of Orange, other
federal, state, and local agencies, and/or City residents
To be able to respond to this diverse study scope, we have compiled a Project Team that consists
of senior level professionals who have intimate knowledge of and experience with the Orange
County coastline and the City's shoreline environment, harbor area, and surrounding wetlands
Our coastal and marine services history includes federal, state, county, and city clients
throughout Orange and Los Angeles Counties and California Most relevant to this solicitation is
our involvement with the Orange County Coast of California Storm and Tidal Waves Study,
Orange and Los Angeles County's Coastal Regional Sediment Management Plans, and our on -
call marine services contracts with the County of Orange and the Los Angeles County
Department of Beaches and Harbors
We appreciate the opportunity to present this Statement of Qualifications for your consideration,
and we look forward to your review of our credentials We welcome the opportunity to visit with
you in person to elaborate further on the merits of our capabilities and why we believe that we
are the most qualified firm to be the City's on -call Ocean Engineer
Sincerely,
NOBLE CONSULTANTS, INC
0
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
REQUEST FOR PROPOSAL
VENDOR APPLICATION FORM
TYPE OF APPLICANT 0 NEW ❑ CURRENT VENDOR
Legal Contractual Name of Corporation Noble Consultants, Inc
Contact Person for Agreement Ronald M Noble
Corporate Mailing Address 359 Bel Marm Keys Blvd , #9
City, State and Zip Code Novato, CA 94949
E-Mail Address rnoble@nobleconsultants com
Phone 415-884-0727 Fax 415-884-0735
Contact Person for Proposals Jon T. Moore
Title Vice President Engineering
Business Telephone 949-752-1530
Is your business (check one)
❑ NON PROFIT CORPORATION
Is your business (check one)
0 CORPORATION
❑ INDIVIDUAL
❑ PARTNERSHIP
E-Mail Address Imoore@nobleconsultants com
Business Fax 949-752-8381
0 FOR PROFIT CORPORATION
❑ LIMITED LIABILITY PARTNERSHIP
❑ SOLE PROPRIETORSHIP
❑ UNINCORPORATED ASSOCIATION
I of 2
1
1
1
1
1
1
1
1
Names & Titles of Corporate Board Members
(Also list Names & Titles of persons with written authorization/resolution to sign contracts)
Names Title Phone
Ronald M. Noble CEO/CFO
Sally Saucer Secretary
George Fischer Director
Verdi Adams Director
949-752-1530
225-612-4104
225-612-3000
225-612-3000
Federal Tax Identification Number 94-2875153
City of Huntington Beach Business License Number
(If none, you must obtain a Huntington Beach Business License upon award of contract)
City of Huntington Beach Business License Expiration Date
2 of 2
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
EXHIBIT A: PRE -QUALIFICATION FORM
ON -CALL ENGINEERING & PROFESSIONAL CONSULTING SERVICES
SERVICE (CATEGORIES
" PROP,O SING? °Y%N
circle :orie,
A.
Civil Engineering
Yes
B
Ocean Engineering
Yes No
C.
Development Plan Checking and Entitlement
REVIEW Services
YES
D.
Survey
Yes "EJ
E.
Traffic Engineering
Yes "D
F.
Water
Yes / ED
G.
Geotechnical Materials Testing and Inspection
Yes No
* (Initial) Consultant is willing to execute the Agreement as drafted (See Appendix B).
,& (Initial) Consultant is able to provide the insurance as required (See Appendix C)
Firm Name: Noble Consultants Inc
Firm Address: 2201 Duaont Dnve. Suite 830 Irvine CA 92612
Signature:
Page 12 of 17
Firm Qualifications
NCI is a civil, coastal, and structural professional engineering firm that is dedicated exclusively
to the study, planning, permitting, design, and construction of marine, shoreline, small craft
harbor, and waterfront facilities for public agencies, industry, and private clients The company
has been in existence for over 35 years, and it has recently been acquired by Gulf Engineers and
Consultants as a wholly owned subsidiary to provide coastal and ocean engineering capabilities
for the parent company
The firm's breadth of scope of services and technical abilities include siting, surve ing
p gY
and permitting, numerical modeling, engineering analysis and design, regulatory entitlements
and permit processing, preparation of contract documents, and construction management This
capability allows NCI to assist clients on all phases of project development assess project
feasibility, optimize site plans, prepare detailed construction plans and specifications, obtain
permits from regulatory agencies, and oversee construction
1 The company's extensive project portfolio includes task work that has involved initial site
investigations and consultation, field monitoring and data collection, hydrographic surveying,
hydrologic and coastal analyses (flood levels, flood routing, wave dynamics, beach processes,
tides, currents, sedimentation, water quality, etc ), development of hydrologic, hydraulic and
coastal design criteria, planning, permitting and design of hydrologic and coastal structures
(flood barriers, dikes, shore protection, beach replenishment, breakwaters, groins, navigation
improvements, marina layouts and berthing, piers, docks, waterfront bulkheads, etc), preparation
of construction drawings, specifications and bid documents, planning reports, cost -benefit
analysis, project cost estimates, environmental impact assessments, construction inspection and
monitoring, and post -construction monitoring Projects have been performed for government
agencies, corporate industry and private individuals along coastal shorelines, estuaries, bays,
lagoons, reservoirs, lakes, rivers and inland waterways throughout Orange County, the state of
California, the United States, and the world
NCI has routinely assisted coastal agencies with all of the necessary planning, design, and
1 construction expertise to address analysis of existing conditions, retrofit existing facilities, or
0
11
design new improvements The company's technical capabilities and expertise include the
following categories bathymetric and beach surveys, oceanographic instrumentation and
measurement, estuarine and coastal analyses, flood and !hydrology studies, hydraulic and
sedimentation analyses, physical and numerical modeling,' storm damage assessments, water
quality and circulation analyses, GIS Integration, beach nourishment, breakwaters, jetties and
groins, channel stabilization, drainage facilities /culverts /eni rgy dissipaters, dredging, marinas,
harbors and beach facilities, navigational improvements, piers, wharves, bulkheads and docks,
residential /commercial waterfront development, seawalls, revetments and dikes, shore and river
bank protection, inspection of existing coastal structures, monitoring and maintenance programs,
'
and project construction management
i
Key Personnel
I
The Key Personnel who will be assigned to the Ocean Engineering On -Call Services Contract
are shown in the Project Management Chart in Figure 1 The team is comprised of professionals
with expertise in coastal processes, wave and current hydrodynamics, coastal and harbor
structures design, numerical modeling, and dredging Our Principal In -Charge and our Project
Manager for all work performed under this contract will be Ronald M Noble and Jon T Moore,
respectively The lead principal investigator for each technical area anticipated for this contract is
identified in the chart The Team has been designed to provide redundancy for QA/QC function
®
■
and responsiveness to City task order and assignment schedules
i
Summaries of the credentials and qualifications of each member of our Project Team are
provided below Complete resumes of all members of the Project Team are included at the end of
this statement of qualifications
Ronald Noble, P.E. — Quality Assurance/ Quality Control
Mr Noble has over 45 years of experience I in
coastal -ocean engineering,
navigational/dredging projects, waterfront structures, hydrologic analysis and computer
modeling His project experience includes beach nourishment and shoreline stabilization,
dredging, navigational improvements, marinas, wetlands restoration, piers, floating berths,
breakwaters, bulkheads, seawalls, groins, and channel stabilization structures
n
Jon Moore, P.E — Project Manager
Mr Moore is a civil/coastal engineer with over 40 years of specialized experience in coastal
and offshore projects His project history includes site planning, design, permitting, problem
solving, environmental assessment, preparation of plans and specifications, and construction
oversight for all types of coastal structures, harbor and marina development, and civil works
construction
Chia -Chi Lu, P.E., Ph.D. — Principal Investigator Coastal Engineering
Dr Lu specializes in coastal and hydraulic engineering with over 28 years of experience He
has extensive experience in the development of numerical models to simulate coastal,
hydrodynamic, and hydraulic processes and analyze engineering problems
Wenkai Qin, P.E., Ph. D. — Principal Investigator Numerical Modeling, Estuarine and Coastal
Hydrodynamics
Dr Qm specializes in coastal processes and riverme engineering He has extensive
experience in the numerical simulation of water circulation and sediment transport
phenomena and physical model investigations to characterize wave transformation, nearshore
hydrodynamics, coastal processes, riverme sedimentation, and hydraulics
Eric Polson, P.E. — Dredging
Mr Polson has over 30 years of experience in maintenance dredging and dredging equipment
operations Specific areas of application include reuse of material for wetland and habitat
restoration, restoration of navigation waterways, and channel design
Thomas Fischetti, P.E. — Coastal Structures Design
Mr Fischetti has over 30 years of experience in civil and structural engineering His design
experience encompasses numerical structural analysis of load paths and stresses,
specification of construction materials, and preparation of construction documents for
residential, industrial and public works projects Specific project experience includes repair
of deteriorated structures and design of new floating docks, seawalls bulkheads, and piers
0
n
IL
11
References
The following references may be contacted to verify NCI's capabilities and performance history
1 On -Call Coastal Engineering Services for the County of Orange OC Parks
Susan Brodeur, Senior Coastal Engineer, Susan biodeur(abocparks com, (949) 585-644
NCI has been coastal engineering consultant to the County of Orange since 1987 Services
have included Sunset Harbor maintenance dredging, development of Sunset Beach dock
standards, and various other coastal engineering, bulkhead design, maintenance dredging,
and marina projects
2 Harbor Engineer for the Los Angeles County Department of Beaches and Harbors
John Kelly, Deputy Director of Capital Projects, JKellygbh lacounty gov, (310) 305-9532
NCI has been Harbor Engineer for the Department since 2005 Services have included
Redondo and Venice Beach nourishment projects, design of the 250 slip Anchorage 47
marina, public accessway design, storm damage assessment of public beach facilities and
infrastructure, and shoreline preservation planning for the County's public beach facilities
3 Semeniuk Slough Maintenance Dredging, Balboa and Newport Piers Rehabilitation, City of
Newport Beach, Department of Public Works
Robert Stein, Assistant City Engineer, RSteingnewportbeachca gov, (949) 644-3322
Services are ongoing for planning, design, and construction for maintenance dredging of a
1,500 —ft long waterway, NCI completed structural renovation of the City's two municipal
ocean piers
4 Los Angeles County Coastal Regional Sediment Management Plan, Los Angeles County
Coastal Storm Waves and Tidal Study, Orange County Coastal Storm Waves and Tidal Study
U S Army Corps of Engineers, Los Angeles District
Susie Ming, Chief Coastal Section, susan in mmgna,usace armymil, (213) 452-3789
NCI prepared the regional sediment management plan for the entire Los Angeles County
shoreline in conformance with the joint federal and state Coastal Sediment Management
Workgroup's program, the comprehensive technical study on shoreline coastal processes
and sediment transport dynamics for the Los Angeles and Orange Counties coastlines The
Los Angeles County studies are ongoing
��I
City of HuntingtaN
Beach
NUL� Ocean Engineering Consultation
Project Manager QA/QC Review
Jon Moore, P.E. Ronald Noble, P.E.
NCI Principal Investigators
Coastal Engineering
Chia -Chi Lu, Ph. D., P.E.
Hydrodynamics/Numerical Modeling
Wenkai Qin, Ph. D., P.E.
Pier/ Bulkhead/ Coastal Structures
Thomas Fischetti, P.E.
Dredging
Eric Polson, P.E.
I, Figure 1. Project Management Chart
11
11
';a
NOBLE
ro
EDUCATION
• University of California Berkeley,
1969, M S , Civil & Coastal
Engineering
• San Jose State University,1968,
B S , Civil Engineering
REGISTRATION/CERTIFICATION
• California, Civil Engineer, 1973,
RCE 23436
• Diplomate, Coastal Engineering
(ACOPNE Certification 45)
• Diplomate, Port Engineering
(ACOPNE Certification 41)
• Diplomate, Water Resources
Engineering (AAWRE
Certification #631)
• NAUI Scuba Diver,1971
PROFESSIONAL AFFILIATIONS
• American Society of Civil
Engineers
• Association of Coastal
Engineers
• American Council of Engineering
Companies of California
• American Shore and Beach
Preservation Association
• California Shore and Beach
Preservation Association
• California Marine Parks and
Harbor Association
• Permanent International
Association of Navigation
Congresses
• American Nuclear Society
PROFESSIONAL RECOGNITION
• Recipient of the 2008 ASCE
International Coastal
Engineering Award
• Recipient of the 2009 ASCE
John G Moffatt -Frank E Nichol
Harbor and Coastal Engineering
Award
• Recipient of the 2012 ASBPA
Morrough P O'Brien Award
• Past President of Coasts,
Oceans, Ports, and Rivers
Institute (COPRI) of ASCE
• Past Governor of Technical
Region Board of Governors
(TRBG) of ASCE
• Vice -Chair, Coastal Engineering
Research Council Member
since appointed in July 1980
10/7/2014
Ronald M. Noble, P.E., D.CE, DYE, D.WRE
EXPERTISE
Senior Principal Engineer
Mr Noble has 45 years of experience in coastal -ocean engineering,
navigational/dredging projects, waterfront structures, hydrologic
analysis and hydrodynamic modeling He has worked on a broad cross
section of coastal/oceanographic and hydrologic engineering projects
involved with riverine, estuarine, and coastal processes, dredging
operations, navigational surveys, flood studies and the design of port
facilities, small craft harbors, recreational marinas, and waterfront
structures Projects have Included beach nourishment & stabilization,
navigational Improvements, wetlands restoration, piers, floating berths,
breakwaters, bulkheads, seawalls, groins, levees, and channel
stabilization structures He has been equally Involved in overseeing
analyses, permit processing, engineering design, construction contract
documents & bidding, and construction management for these projects
EXPERIENCE
U S Army Corps of Engineers, San Francisco District —
Civil/Waterfront Engineer on VE Team for the Pier 36 Removal and
Environmental Compliance project for the Port of San Francisco This VE
Study consisted of demolition of Pier 36, demolition of the marginal wharf
between Piers 30/32 and 38, and repairs to the concrete seawall The VE
study identified 14 alternatives that could potentially add value to the
project
San Diego Association of Governments - Principal-In-Charge/Project
Manager for the (SANDAG) Regional Beach Sand Project
Responsibilities included preparation of design, plans, specifications, and
contract documents, and overseeing construction management/resident
inspection to re -nourish twelve San Diego County beaches with over 2
million cubic yards of sandy material dredged from six offshore borrow
sites Dredging was performed with a trailing suction hopper dredge that
then attached to inshore mono -buoys for pumping sand materials to shore
County of Orange — Principal -In -Charge and Project Manager for the
Upper Newport Bay Sediment Control & Enhancement Project Provided
construction management oversight support to County of Orange for
dredging one million cubic yards in Upper Newport Bay with offshore
barge disposal during 1 % year period Services included contractor
dispute resolution, interpretation of contract documents, review of change
orders, and providing/managing three to five construction inspectors for 24
hours per day operation
BEACON — Coastal Regional Sediment Management Plan - Directed a
comprehensive coastal study for BEACON along the Santa
Barbara/Ventura Counties coastline which included the inventory of
offshore, harbor entrance and fluvial sand sources, estimating erosion
rates and sediment budgets, preparing a comprehensive sand
management program to control beach erosion and recommending and
Ronald M Noble
Page 1 of 3
11
• Past President Board of
Trustees of the Academy of
Coastal, Ocean, Port &
Navigation Engineers
(ACOPNE) of CEC
• Member Board of Directors of
Civil Engineering Certification,
Inc (CEC)
• Member of 2011 ASCE Task
Committee on Institute
Operating Procedures (TCIOP)
• Past Director & Charter Member,
Association of Coastal
Engineers
• Past Director, American Shore
and Beach Preservation
Association
• Past President, Marin Chapter -
Consulting Engineers and Land
Surveyors of California
• Chairman, ICCE 2006 (30th
International Conference on
Coastal Engineering), San
Diego, California, September
2006
• Co -Chair, 2011 Conference on
Coastal Engineering Practice,
San Diego, California, August
2011
• Director, World Marina
Conference, Inc that sponsored
World Marina Conference, Long
Beach, California, April 29 -
May 2, 1991
• Chairman, American Nuclear
Society Committee that
developed an American National
Standard on Design Basis
Flooding at Power Reactor Sites
• U S Expert Representative on
the International Atomic Energy
Agency Committee for
Development of an International
Standard on Design Basis
Floods for Nuclear Power Plants
on Coastal Sites
• General Chairman, National
Shoreline symposium,
"Shoreline Forum'79", held in
Los Angeles, California
• Member, ANS Committee on
Site Evaluation of Power
Reactor Sites
1 10/7/2014
Ronald M. Noble, P.E., ®.CE, ®.PE, ®.WRE
Senior Principal Engineer
Implementing an effective monitoring plan to observe indicators of beach
health
• U S Navy Southwest Division - Principal -In -Charge for U S Navy
Special Project M10-90 to perform hydrographic and underwater diving
surveys, perform topographic mapping, and prepare plans, specifications,
bid documents and construction cost estimates for maintenance dredging
of six miles of channel, Piers 1,2,7,8 and 13, and Chollas and Paleta
Creeks at Naval Station, San Diego
• US Navy Southwest Division - Principal -In -Charge for US Navy
Special Project M1-90 to perform hydrographic and underwater diving
surveys, perform topographic mapping, perform geotechnical vibracore
sampling, and prepare plans, specifications, bid documents and
construction cost estimates for maintenance dredging of ammunition Pier
Bravo and the turning basin for the Quaywall on North Island, San Diego
• City of Oceanside - Project manager for overseeing rehabilitation of City
of Oceanside Municipal Pier that included feasibility studies, development
of design criteria, demolition of storm damaged pier, design of new pier
including buildings and shoreline protection, and construction
management and inspection of pier, buildings and shoreline protection
during construction
• City of San Leandro - Directed design for replacement of the San
Leandro Marina including reconfiguration of berthing layout and
preparation of plans, specifications, cost estimates, construction schedule,
and bid documents for new floating dock and piling system, approach
piers, dredging, and utilities and landscape improvements Directed
construction management and resident inspection during construction
Sunroad Enterprises - Performed engineering design, and prepared
plans and specifications for new 550 boat Sunroad Marina in San Diego
Bay, which included concrete floating dock system, all appurtenances and
a prestressed concrete sheet pile breakwater Also, provided construction
inspection
• U S Navy Southwest Division - Prepared conceptual design and
directed final design, plans, specifications and cost estimates for the
Navy's NTC marina expansion project in San Diego Bay, which included
floating timber dock system, two concrete piers, shoreline protection,
support building and site improvements
• City of San Leandro - Principal -In -Charge for preparing engineering
design, plans and specifications for the reconfiguration of the City of San
Leandro's 112-acre upland confined dredge disposal site to handle
maintenance dredging This project included engineering design,
environmental permitting, development of long range operational plan,
removal of deposited dredge sediments, water quality testing and
reconfiguration improvements
Ronald M Noble
Page 2 of 3
L
NOBLE
CONSULIANIS, INC
:' utmpaity ;
Ronald M. Noble, P.E., MICE, ®.PE, ®.WRE
Senior Principal Engineer
• County of Orange - Principal -In -Charge for the Sunset Harbor Maintenance Dredging Project for the
County's 120,000 cubic yards of maintenance dredging within a two-mile channel at Huntington
Harbor/Sunset Harbor Services Included hydrographic surveying and mapping, preparation of plans,
specifications, bid documents and cost estimates, geotechnical and environmental Investigations,
mitigation of eelgrass, and construction monitoring
• Coronado Cay Company - Design engineer for Coronado Cays Company's, Coronado Cays waterfront
development in San Diego, which included engineering design, plans, specifications and cost estimates
for one million cubic yards of dredging for a one mile long navigation channel, bulkheads, and rock slope
protection
• U S Army Corps of Engineers, Alaska District - Principal responsible for review of NCI dredging
evaluation analysis for Wrangell Narrows Navigation Improvement Project consisting of up to 15 million
cubic yards of dredging for 24 miles of channel widening and deepening within the narrow passage
between Mitkof and Kupreanof Islands, Alaska
' • City of Huntington Beach & City of Redondo Beach - Directed the engineering studies to develop
oceanographic design criteria and recommend alternative plans for repair or replacement of the
Huntington Beach and Redondo Beach Municipal Piers, and performed engineering design and
preparation of plans and specifications for reconstruction of the damaged Redondo Beach pier
• U S Navy Southwest Division - Principal -In -Charge for U S Navy harbor expansion project at Naval
Weapons Station, Seal Beach, which included conceptual design and cost evaluation for expansion of
existing harbor facilities including new channel dredging, breakwater, trestle and pier/wharf structures,
and offshore terminal to handle AOE-6 class ships
• Several Clients - Directed and/or performed the engineering analysis and design, including plans,
specifications and cost estimates, and performed construction management and inspection, for shoreline
protection consisting of revetments, seawalls, bulkheads, groins, breakwaters and beach nourishment
These improvements have been designed using stone, concrete, steel, and sand for locations throughout
California, the United States, and overseas
• U S Army Corps of Engineers, Los Angeles District - Directed preparation of reconnaissance reports,
final feasibility reports and conditional surveys for southern California harbors for the U S Army Corps of
Engineers These studies included engineering analyses and cost -benefit evaluations for harbor
improvements such as dredging, breakwater/jetty modifications, spur groins and sediment traps
• U S Army Corps of Engineers, Honolulu District - Performed siting and design investigation for dock
structures at 15 atolls within the Marshall Islands Group This investigation included site selection,
development of design criteria, and the design, configuration, and alignment schemes for dock structures
Ronald M Noble
10/7/2014 Page 3 of 3
NOBLE
,
f_0NbUL1AN1�,, IN( —
,kid t��"2s�'`�`° *��aGECcompaiy
EDUCATION
• University of California Berkeley,
1972, M S , Civil Engineering
• University of California Berkeley,
1971, B S , Civil Engineering
REGISTRATION/CERTIFICATION
• California, Civil Engineer,1975,
RCE 25673
• Diplomate, Coastal Engineering
(ACOPNE Certification #36)
PROFESSIONAL AFFILIATIONS
• American Society of Civil
Engineers
• American Shore and Beach
Preservation Association
• Tau Beta Pi
• ChiEpson
PROFESSIONAL RECOGNITION
• Chairman, Waterway, Port,
Coastal and Ocean Division,
ASCE, 1978 - 1985
• Chairman, San Francisco
Section, Waterway, Port,
Coastal, and Ocean Division
Technical Group, 1977 —1980
• Treasurer, San Francisco
Section ASCE, 1979 —1980
• Director, American Shore and
Beach Preservation Association
• Co -Chairman, Coastal Zone `78,
First Symposium on Coastal
Zone Management,1978
EXPERTISE
Jon T. Moore, P.E., ®.CE
Principal Engineer
Mr Moore is a civil/coastal engineer with over 42 years of specializing
in coastal and offshore projects His breadth of experience includes
design criteria recommendation, site planning, problem mitigation
studies to rectify existing adverse conditions, environmental
assessment of proposed improvements and the preparation of plans
and specifications for various types of coastal structures development
and civil works construction
EXPERIENCE
City of Avalon - Project engineer for the Casino Fuel Pier replacement
project in Avalon, CA in 2010, completed in 2011 Responsibilities
included geotechnical, geophysical, and survey field studies to map
features and investigate an unusual sub -surface deep rubble foundation
Performed structural design of reinforced concrete pier with innovative
steel pipe pile/rock anchor foundation, special steel frame fender system
fabrications, and electrical and mechanical design of utilities and fuel
dispensing system concealed within integrated utility trench
County of Orange — USCG Bulkhead Replacement, Newport Harbor,
CA - Principal in Charge for design of steel sheet pile bulkhead
replacement In Lower Newport Harbor Design services and construction
consultation services completed in 2010 Duties included structural design
of seismically resistant steel pipe pile lateral anchor and tieback system,
heavy duty coated steel sheet pile bulkhead driven in hard formational
material, reinforced concrete cap, replacement of floating docks, and
maintenance dredging
• County of Orange — Principal in Charge for Salt Creek Beach Revetment in Dana Point, CA for the
County of Orange The project entails inspection, evaluation, design, permitting, construction of a 1,500-
foot long ocean front revetment and public accessway exposed to severe storm wave attack Services
included topographic surveying, development of oceanographical design criteria including potential sea
level rise impacts, coordination with regulatory agencies, and preparation of construction plans and
specifications Work began in 2007 and is progressing to detailed design and construction The estimated
construction costs will approximately $2,000,000
• County of Los Angeles - Principal in Charge for various on call services as Harbor Engineer for the Los
Angeles County Department of Beaches and Harbors Between 2005 and 2011 have completed over 50
task orders covering harbor and coastal engineering planning studies, dock replacement, design of beach
accessways, beach nourishment projects, storm drainage improvements, and tsunami and storm damage
response and repair investigations Prepared construction plans and specifications and coordinated with
Department of Public Works to complete capital improvement projects utilizing the expedited Los Angeles
County Job Order Contract system
t
Jon T Moore
10/7/2013 Page 1 of 2
L�
I
NOBLE
Al
(,ONSULI
14
Jon T. Moore, P.E., ®.CE
Principal Engineer
City of Oxnard - Mandalay Bay Seawall Repair, Mandalay Bay, Ca - Principal in Charge for a 14
year on call contract with the City of Oxnard to provide services for Mandalay Bay's 6 5 mile long
seawall and watering system These services have included seawall repair and maintenance, plans,
specifications and oversight of maintenance dredging, plan checks, emergency responses to
homeowners and storm damage, and underwater survey oversight This project began in 1993 and is
an ongoing project Over $4,000,000 has been spent to date for various seawall repairs and
maintenance dredging work
Port of San Diego - National City Marina Preliminary Engineering Design - Project engineer for the
250-slip National City Marina basin in San Diego Harbor Responsible to the Unified Port District of
San Diego for preparation of conceptual design plans, assistance with lessee solicitation, preparation
of final plans and specifications, and consultation during construction The work included excavation
and removal of 400,000 cubic yards of sand and bay deposits, optimization of the small craft slip
layout to fit available space, perimeter slope protection, upland access, parking and infrastructure,
three public buildings and landscaping Special project design conditions included seismic risk, poor
foundation conditions and a significant federal flood control channel adjacent to the entrance
Conceptual design studies began in 1992, and construction was completed in 2005 The project cost
was $7,200,000
• County of Ventura - Principle in Charge for the Channel Islands Harbor Revetment Shoreline
Stabilization Project This project consisted of replacement of approximately 4,000 feet of faded slope
stabilization Services included forensic analysis to determine slope stability and soil piping issues
Design consisted of a sheet pile toe wall to stabilize the over steepened slope and new quarry stone
armor over geotextile foundation Design work began in 2004 Construction was completed in 2007
for a cost of $5,300,000, and the design saved the client over $1 million dollars
• B E A C O N - Goleta Beach Demonstration Beach Nourishment Project, Goleta, CA As Project
Manager, responsibilities included detailed geophysical and geotechnical field investigation to locate
and characterize the engineering and environmental properties offshore and deposits for use in
beach nourishment Negotiated contract documents with dredging contract to perform the work
Obtained all regulatory entitlements from local, state, and federal agencies Prepared engineering
documents to specify borrow and nourishment limits Provide construction supervision
City of Ventura — Surfer's Point Park Plan and Managed Retreat Project Manager for the Surfer's
Point Plan for Managed Retreat Supervised civil, geotechnical, coastal and landscape design
elements to prepare innovative, erosion protection solution for a threatened urbanized shoreline that
mimics naturally occurring processes Project involved extensive interaction with Coastal
Conservancy, regulatory agencies to address competing use issues, stakeholder concerns, and user
requirements Alternative plans were formulated and evaluated to select a preferred plan for
shoreline re -development
• City of Ventura — Ventura Pier Storm Damage Consultation - Project engineer for the 1995 storm
damage assessment of the San Buenaventura Pier The study included a structural engineering
review of timber pile capacity, storm wave conditions, and formulation of alternative
repair/reconstruction methods Assisted the City to implement a modified repair program and
provided consultation during construction Project engineer for design of steel pile/framed and timber
stringer/deck system of reconstructed outer pier end including providing construction management
during 1999-2000
1 10/7/2013
Jon T Moore
Page 2 of 2
1
r
OBLE
(-ONSULIANIS, IN(.
c;
• University of Miami/RSMAS,
1984, Ph D , Applied Marine
Physics
• University of Miami/RSMAS,
1981, M S , Ocean Engineering
• Cheng Kung University, Taiwan,
1975, M S , Hydraulic
Engineering
• Cheng Kung University, Taiwan,
1971, B S , Hydraulic
Engineering
REGISTRATION/CERTIFICATION
• California, Civil Engineer,1994,
RCE 52521
• Diplomate, Coastal Engineering
(ALCOPNE Certification #31)
PROFESSIONAL AFFILIATIONS
• American Society of Civil
Engineers
EXPERTISE
Chia -Chi Lu, Ph.D., P.E., D.CE
Associate Coastal Engineer II
Dr Lu specializes in the fields of coastal and hydraulic engineering and
has extensive experience in the development of numerical simulation
on related engineering problems by using various numerical techniques
such as finite difference method, finite element method and boundary
element method He has extensive experience in the development of
numerical models to simulate coastal and hydraulic processes and
analyze engineering problems He has conducted numerous coastal
investigations and planning studies along the San Diego, Orange, Los
Angeles, and Santa Barbara and Ventura counties shorelines
EXPERIENCE
BEACON - Involved in preparing a comprehensive erosion management
plan for 60-miles of urbanized shoreline in Santa Barbara and Ventura
County The multi -disciplinary study prepared for the BEACON joint
powers authority entailed definition of past, present and future coastal
processes, delineation of problems and opportunities for improvement,
identification of suitable offshore borrow sources for sand replenishment
and formulation of technically, environmentally and economically feasible
shoreline preservation and enhancement strategies
• BEACON — Prepared an oceanographic assessment of a Draft EIR/ES for the BEACON beach
nourishment demonstration project The fate of the disposed dredged material as well as its potential
impacts to the coastal processes was characterized via a series of comprehensive computer simulation
programs developed by Water Resource Support Center, Waterways Experiment Station, Corps of
Engineers
• USACE, Los Angeles District — Performed a reconnaissance study to assess storm damage potential
associated with shoreline erosion, seacliff retreat and wave related flooding within the Encinitas shoreline
reach A coastal engineering analysis to document relevant oceanographic and sediment transport
conditions, and prediction of future damages to property and infrastructure was prepared Various
alternative measures consisting of engineering and environmental evaluations were proposed to mitigate
the storm damage scenarios
• USACE, Los Angeles District - Performed a comprehensive analysis of nearshore wave transformation,
potential shoreline erosion, littoral transport and sediment budget for the entire Santa Barbara/Ventura
County coastline on the BEACON coastal sand management project Extensive numerical modeling of
long- and short-term beach accretion and erosion was conducted
• SANDAG - Performed the engineering design required and preparation of final construction plans and
specifications for the San Diego Regional Beach Sand Project The beach nourishment project consists
of the replenishment of two million cubic yards of beach sand dredged from six offshore areas along 12
designated sites Beach characteristics of each receiver site were assessed to determine the appropriate
placement footprint including length and cross-section
• USACE, Los Angeles District - Performed a numerical simulation of transformed wave patterns to
characterize the nearshore wave climate within the Orange County coastal area as part of the Coast of
California Storm and Tidal Waves Study Wave Characteristics in deep water, corresponding to the
Chia -Chi Lu
10/7/2013 Page 1 of 2
I
1
NOBLE Chian -Chi Lu, Ph.D., P.E., D.CE
CON SULIANiS, 1NC
Associate Coastal Engineer II
categorized weather patterns, were computed and then transferred to the nearshore water areas via a
spectral back -refraction transformation model A Monte Carlo simulation technique was applied to
' generate a synoptic atlas of the nearshore wave climate in this region
• U S Fish and Wildlife Service - Prepared a coastal process assessment for the EIR/EIS of the
proposed Bolsa Chica Wetlands Restoration Project A tidal inlet to improve the fresh and salt water
' exchange between the ocean and wetlands was proposed by the protect design team The potential
impacts on adjacent beaches were evaluated including beach loss, alteration of nearshore wave
characteristics, inlet interruption to the alongshore littoral transport, and potential sediment deposit within
' the wetland basins Detailed review comment and constructive suggestions were made to the protect
design team for the re -analysis of the design features Potential mitigation measures to minimize the
adverse impacts were addressed
• USACE, San Francisco District - Protect Manager for the Bel Mann Keys Unit V Expansion of the
Hamilton Wetland Restoration protect to perform numerical simulations of hydraulic, hydrodynamics, and
sedimentation in Novato Creek and the proposed Unit V northern wetland basin The numerical models
of HEC-RAS, RMA2, and SED2D were respectively applied to predict flood stages in the creek and
' adjoining basins under various flood events, to characterize the tidally induced creek hydrodynamics and
to estimate the long-term sedimentation in the creek and tidal wetland basin A bathymetric survey in
Novato Creek, and deployment and retrieval of tide gages and current meters were conducted to collect
the baseline information that is necessary for the execution of the numerical simulations The model
results were used to assess the potential impacts to the navigability in Novato Creek under the typical
tidal conditions as well as the flood stages during severe flood events
USACE, Los Angeles District - Project Manager and Lead Engineer for a numerical model to statistically
'•
predict bluff failure scenarios for the Cities of Encinitas and Solana Beach The Monte Carlo techniques
combined with an empirical short-term toe erosion model were applied to characterize the randomness of
bluff face exposed to wave attack and upper bluff failure The statistic representation for the bluff -top
retreat was derived from the field data observed in the past, and random wave heights were generated
from the hindcasted deepwater waves that propagated to the bluff base between 1979 and 2001 The
model results were used in the economic evaluation for the without -project conditions as well as any
'
proposed engineering measures
• U S. Marine Corps - Project Manager for a hydrodynamic simulation of the Santa Margarita River
Estuary using the RMA2 module of the SMS The tidal -induced estuarine hydrodynamics, including water
level and currents, were modeled with the consideration of the wetting and drying process within the
estuary boundary The model calibration was performed using the water level data at the USGS gage
located in the estuary This simulation was conducted in support of a feasibility study for a constructed
wastewater treatment wetland to assess the potential impacts of any discharge of treated water on the
estuarine water quality
• USACE, Los Angeles District - Lead Engineer for a modeling study of the fates of disposed material at
a permanent (LA-2) and a to -be -designated (LA-3) ocean disposal site, respectively The modeled
1
results were used for the preparation of the Environmental Impact Assessment (EIS) to evaluate any
potential impacts to the to -be -designated LA-3 site as well as the existing LA-2 site The computer models
of STFATE and LSFATE developed by the Corps of Engineers were applied to numerically estimate the
fate of disposed material including the phases of convective decent, dynamic collapse and passive
dispersion
I
' 10/7/2013
Chia -Chi Lu
Page 2 of 2
I
1
I
CON!SULI
NOBLE ANI$, INC
University of Delaware, 2003,
Ph D , Civil / Coastal
Engineering
Tsinghua University, China,
1997, Ph D , M E , Hydraulic &
River Engineering
Wuhan University, China,1991,
B S , River Engineering
REGISTRATIONXERTIF (CATION
• California, Civil Engineer, 2005,
RCE 68730
• Diplomate, Coastal Engineering
(ACOPNE Certification #73)
PROFESSIONAL AFFILIATIONS
• American Society of Civil
Engineers
EXPERIENCE
Wenkai Qin, Ph.D., P.E., D.CE
Senior Coastal/Hydraulic Engineer III
EXPERTISE
Dr Qin is a registered civil engineer with 18 years of experience
specializing in coastal engineering and water resources This work has
included modeling of coastal processes (tides, waves, currents,
sediment transport, and coastal morphology), development of
oceanographic design criteria, design of marina facilities, shoreline
protection, coastal and waterfront structures, and wetland restoration
projects, shoreline feasibility and storm damage reduction studies,
hydrodynamics, sediment transport and water quality studies for
coastal zones, estuaries, rivers, wetlands, lagoons, bays, and coastal
developments, coastal and rivenne flood hazard analysis and
mapping, hydrologic and hydraulic (H&H) studies, and risk and
uncertainty analysis
Dr Qin has extensive experience with coastal and surface water
models and software such as STWAVE, REFDIF, CMS -Wave, SWAN,
Boussinesq wave models, ADCIRC, SHORECIRC, GENESIS,
SBEACH, CEDAS, CMS -Flow, RMA2, RMA4, SED2D, HEC-HMS,
HEC-GeoRAS, HEC-RAS, HEC-FDA, and SAM He also has
extensive experience in developing numerical models for coastal and
water resources applications using FORTRAN, Matlab and C++
• USACE, ERDC - Developed nonlinear wave models for regular and irregular waves Developed a
sediment transport model for alongshore and cross -shore sediment transport and beach morphology
Incorporated the wave models, nearshore circulation model SHORECIRC and the sediment transport
model into a coupled nearshore wave -current -sediment transport model system for comprehensive
coastal processes Verified the model system with the physical model investigations conducted at the US
Army Engineer Research and Development Center (ERDC)
• Watt, Tieder, Hoffar & Fitzgerald, LLP — Conducted technical review for the forensic studies of New
Orleans Hurricane Protection in Hurricane Katrina that were conducted by IPET, ILIT and Team
Louisiana The review focused on storm surge and wave studies, levee and floodwall performance
evaluation, and interior drainage and pumping analyses
• FERC — Technical Review for Coastal Engineering Studies and Designs Selected review work included
(1) Gulf LNG Project Seawall and Storm Surge Protection Wall Design, Jackson County, Mississippi, (2)
Design Studies for Aguirre Offshore GasPort LNG Project, Bahia De Jobos, Puerto Rico, and (3) Design
Studies for Lavaca Bay LNG Terminal Project, Lavaca Bay, Texas
• Northwest Hydraulics Consultants - Conducted FEMA coastal flood hazard analysis and mapping
study for the Pacific Coast Reviewed methodologies, models and field data for storm wave
characteristics, wave runup, setup and overtopping Reviewed and developed geometric models and
process -based models for event based erosion (EBE), and prepared the draft of the focused study on
EBE Developed and tested geometric models for storm -induced beach and dune erosion in Southern
California and Oregon Coast Prepared guidelines for FEMA EBE assessment Reviewed DHI's Pilot
Wenkai Qin
11 /17/2013 Page 1 of 2
NOBLE Wenkai Qin, Ph.D., P.E., D.CE
(.ONSULIANIN, INC
Senior Coastal/Hydraulic Engineer III
Study for Del Norte County Coastal FIS Update, Application of West Coast Guidelines & Specifications
(FEMA Region IX)
• USACE, Los Angeles District - Lead engineer of the Encinitas and Solana Beach Shoreline Feasibility
Study Developed a USACE-certified Monte Carlo model to statistically simulate the shoreline/bluff-top
retreat over a 50-year design life cycle, considering the random characteristics of wave climates and bluff
collapses triggered by wave -induced bluff -toe erosion Developed and evaluated shoreline protection
alternatives including beach nourishments, notch fills, seawalls and revetments Predicted beach
nourishment performance for various beach fill design options using GENESIS with STWAVE and
RCPWAVE models Conducted cost and benefit analysis, and optimized beach nourishment design
parameters such as beach fill locations and lengths, initial berm widths and elevations, replenishment
cycles, and placement of sand retention structures Developed conceptual design of beach
nounshments, revetments and seawalls Provided cost estimates and construction methods
• Various Clients - Protect manager and/or lead engineer for coastal engineering analysis to develop
oceanographic design criteria for shore protection projects and coastal structures Scope of services
typically included wind -wave hindcasting, analysis of NDBC or CDIP buoy wave data or the WIS
hindcasted wave data, wave propagation and transformation modeling, tidal frequency analysis, return
frequency analyses for storm wave events, estimating future sea level rise, computing wave runup using
SPM/CEM methods, CEDAS and/or FEMA models, determining coastal flood elevations considering still
water levels, sea level rise and wave runup, computing wave overtopping rate, calculating wave loading
on structures, developing oceanographic design criteria, providing conceptual design, analyzing the long-
term shoreline evolution and storm -induced beach erosion, and/or assessing project impacts to costal
processes Selected projects included (1) San Rafael Avenue Seawall (Revetment) Study for the City of
Belvedere, CA, (2) PG&E Portrero Shoreline Revetment Improvement, San Francisco, CA, (3) Wave
Study and Wave Runup Analysis for the Levee Plan at Foster City, CA, (4) Storm Erosion, Wave Runup
Analyses, and Beach Impact Assessment for the Aquatic Youth Center at Dockweiller Beach, Los
Angeles County, CA, (5) Coastal Hydraulic Analysis for Draper's Boat House Repairs and Floating Dock,
Inverness, CA, and (6) Coastal Hydraulic Analysis for Carlson Residence Improvement, Marshall, CA
• Padre Associates, Inc - Performed oceanographic impact assessment associated with a proposed
PRC-421 submerged hard -bottom substrate feature within the Santa Barbara Channel Applied a
coupled nearshore wave -current -sediment transport model system to assess the potential project impacts
to the nearshore wave climate, currents and sediment transport
• WRA - Protect leader and principle modeler of the hydrodynamic, wave, and sedimentation modeling
study for the Yosemite Canal Wetlands Restoration Project, San Francisco The Corps 2-D models
RMA2 and SED2D were used to model the tidal currents and tide -induced sedimentation in Yosemite
Canal and South Basin for the existing condition and proposed restoration plan The ACES and
STWAVE were used to model wave conditions during extreme storm events, and a model was developed
to estimate the wave -induced erosion potential during the storm events
11
1 11/17/2013
Wenkai Qin
Page 2 of 2
C
IIIII
AN IS INC
aGEC company
NOm,
• Humboldt State University,1984,
B S , Environmental Resources
Engineering, Water Resources,
Sediment Transport &
Geotechnical Engineering
REGISTRATION/CERTIFICATION
• California, Civil Engineer, 1991
RCE 47731
PROFESSIONAL AFFILIATIONS
• American Society of Civil
Engineers
• National Society of Professional
Engineers
PROFESSIONAL RECOGNITION
• Past President, American
Society of Civil Engineers —
Sacramento Section
• Past Vice President, California
Legislative Council for
Professional Engineers
EXPERIENCE
Eric Polson, P.E.
Senior Associate Engineer
EXPERTISE
Mr Polson is a registered civil engineer who has worked primarily
in the areas of dredging equipment and operations, beneficial reuse
of dredged material for intertidal, wetland and upland habitat
restoration, marine construction and demolition and navigation
channel design for twenty eight years as a professional engineer
and project manager Mr Polson has broad and specialized
experience in the engineering, design, regulatory, environmental,
economic, construction, operations and political issues relative to
dredging, marine construction and demolition, dredged material
reuse and management and habitat restoration projects in marine,
intertidal and freshwater environments Mr Polson's projects
include technically, environmentally and politically complex projects
that require advanced engineering skills, integration and
coordination with a wide range of scientists and environmental
professionals and coordination with the public and special interest
groups Mr Polson's primary focus is on the development of cost
effective and environmentally superior designs, incorporation of
innovative, low impact and low cost construction techniques and
rapid response to construction and emergency situations
Hamilton Wetlands Restoration Project - Final Design, Construction and Operations Plans
Since 1996 1 have been working with the California State Coastal Conservancy, US Army Corps of
Engineers, San Francisco Bay Conservation and Development Commission and other agencies for
the final design, construction sequencing, operations plans, dredged material supplies and
sequencing, utilities relocation and protection, property transfer issues, cost estimating,
environmental permitting and compliance and general technical advice and oversight This effort
includes incorporating the adjacent 1,600 acre Bel Marin Keys Unit V parcel into the Project design
and construction plan and assisting with the development of the Supplemental EIR/S for adding BMK-
V I have also coordinated recent and past emergency levee repair work on the Bel Mann Keys Unit
V parcel
• Hamilton Wetlands Restoration Project - Feasibility Study, EIR/EIS & Cost Estimate Worked
with staff from the US Army Corps of Engineers, San Francisco Bay Conservation and Development
Commission and the California State Coastal Conservancy to provide input and advice for the
Feasibility Study, respond to comments on the EIR/EIS and develop and review detailed cost
estimates Also coordinated with the Port of Oakland -50 foot Deepening Project on detailed cost
estimates for dredging and dredged material transport and off-loading
• Hamilton Wetlands Restoration Project - Conceptual Plan Worked with a multi -disciplined team of
engineers, ecologists, biologists and scientists to develop the conceptual plan for tidal and seasonal
wetlands restoration on a 1000 acre site adjacent to San Pablo Bay This work included developing
site plans for wetland restoration using dredged material, determining dredged material placement
techniques, laying out the dredged material off -loader area and pipeline route, developing dredged
material chemical and physical suitability criteria, developing dredged material quantity and type
Eric Poison
5/8/2014 Page 1 of 3
a GEC companI -_ 7,Nq t' �
NOBLE
Eric Poison, P.E.
Senior Associate Engineer
requirements for various project alternatives, investigating potential dredged material sources for the
project and developing cost estimates
Montezuma Wetlands Project Recent efforts include reviewing operations, reports and future plans
for this project as a member of the Technical Advisory Committee During project design I provided
specific final design details for process water facilities, pipelines, design plans and grades, off -loader
facilities and operations and power supplies Also provide general peer review and advice
Previously developed a detailed report required for responding to comments on the Projects EIR/EIS
including the accuracy of dredged material placement techniques, control of final dredged material
elevations, dredged material off -loader operations and the economic and liability considerations
relative to off-loading equipment ownership and operation
• Sonoma Baylands Wetlands Restoration Project Provided daily on -site inspection of the hydraulic
placement of dredged materials, water quality monitoring, tidally limited water discharge operations,
hydraulic off -loader operation and maintenance, tug boat and barge operations, dredged material
discharge pipeline installation, movement and removal and other site construction and operation
activities Operated in -situ dredged material density monitoring equipment and developed daily
reports of water levels, dredged material levels and dredged material densities
• Sears Point Wetlands Project Worked with a team of engineers and scientist to develop the initial
t design for this large wetland and upland habitat restoration protect Also provided construction
estimates for dredging and land based construction features of the project during environmental
documentation
• Bel Marin Keys Unit V Restoration Project Worked with a team of consultants to develop an
interim management plan for the 1,600 acre BMK-V site and complete final design details and
coordination for this project which is a federally approved addition to the Hamilton Wetlands
'
Restoration Project
• Removal of Creosote Treated Pilings and Structures from San Francisco Bay Worked with the
San Francisco Estuary Institute, California State Coastal Conservancy and a large number of Bay
area regulatory and resource agencies on a broad based study effort for removal of creosote treated
material from San Francisco Bay The specific focus was developing an action plan that covered
removal techniques and costs, seasonal timing considerations, best management practices, disposal
and reuse options for creosote treated materials, creosote pile encapsulation techniques, permitting
and ownership issues, potential enforcement of historic permit conditions and removal of creosote
treated debris from intertidal areas
• Vallejo Ferry Maintenance Dredging Project Worked within a team of consultants to plan, design,
permit and oversee a maintenance dredging of the Vallejo Ferry Terminal in 2008 Provided
oversight on all permitting actions
• Long Term Management Strategy (LTMS) - The LTMS was a large multi -agency Project to develop
and implement a strategic 50 year plan for all dredging and all dredged material management in the
entire San Francisco Bay Region This management strategy includes all federal and state regulatory
and resource agencies and many local, environmental and special interest groups Following are
selected LTMS reports which I wrote entirely or provided a significant contribution
• LTMS - Tidal Wetlands Restoration Potential Using Dredged Sediments Worked with a team of
wetland scientists and engineers to develop a ranking system to evaluate the wetland restoration
potential for diked historic baylands throughout the San Francisco Bay Region Developed ranking
Eric Poison
5/8/2014 Page 2 of 3
NOBLE Eric Poison, P.E.
GOr,bUl.IANI$, INC
Senior Associate Engineer
logic for elevation and grade, off-loading distance, site capacity, utility and infrastructure and other
engineering constraints Evaluated the engineering constraints for hundreds of potential restoration
sites within San Francisco Bay Region with this ranking system
• LTMS - Reuse/Upland Site Analysis and Documentation Developed conceptual plans and
descriptions of dredged material reuse options including wetland restorations, levee construction and
upland construction Investigated the potential of thirty dredged material reuse sites throughout the
Region and all transportation factors for those sites
LTMS - Analysis of Remediation Technologies for Contaminated Dredged Material Developed
chemical and physical criteria for dredged material disposal and beneficial reuse in cooperation with
regulatory agency staff Investigated dredging equipment and techniques applicable to environmental
protection during contaminated sediment removal Evaluated the effectiveness and cost of a wide
r range of remediation technologies for applicability to contaminated dredged material and
transportation options to move materials to secure locations
LTMS - Engineering Elements of Dredged Material Rehandling Facilities Developed site specific
conceptual level plans for dredged material rehandling facilities including cell layout, off-loading
location and pipeline alignment, discharge water facilities requirements and operational and
management considerations This work included evaluation of the relative costs of water, rail and
road based transportation of dredged materials
• Feasibility Analysis for Rehandling Dredged Material at the Leonard Ranch Site Developed
specific portions of this rehandling facility feasibility analysis and design including placement cell
layout, off -loader location and pipeline alignment, process water facilities, operation and management
considerations, operated and evaluated computer programs to predict dredged material de -watering
and desiccation rates based on material type and local weather conditions, and evaluated the impacts
■ and costs of existing infrastructure constraints
• Dredged Material Disposal and Reuse on the Upper Sacramento Deep Water Ship Channel
Developed future maintenance and new work dredging volume predictions and evaluated the related
■ disposal area requirements Evaluated the existing and potential dredged material disposal and
reuse sites owned by or potentially available to the Port of Sacramento Developed
recommendations to assist the Port of Sacramento with near term and long term land purchase, sale
and use decisions
r
• Bel Marin Keys Community Service District - Lagoon and Creek Dredging and Operation
Developed preliminary maintenance dredging plans for the North Lagoon and Novato Creek This
r work included coordination of aerial photography, hydrographic surveys, tidal sedimentation studies,
navigation lock operational requirements, tidal navigation constraints and Lagoon flushing operations
Related work included developing permit application packages and coordination with regulatory and
resource agencies Also worked with the District staff to develop a lagoon flushing program to
improved water lagoon quality and reduced sedimentation
• City of Redwood City - Flood Control Operations Consultation Conducted a document and field
review of flood control problems on local watershed areas Worked on -site with the City's planning,
engineering and operations staff to develop operational techniques to reduce flooding without
requiring any significant structural modifications or operational cost increases
■
■
r
5/8/2014
Eric Poison
Page 3 of 3
beacn raciiity i ne tirst was the structural repair of an existing 50-year old concrete wharf that, due to
' 10/7/2013
Thomas J Fischetti
Page 1 of 3
1
11
C
EDUCATION
• California Polytechnic State
University,1981, B S ,
Architectural Engineering
• California Polytechnic State
University,1981, Applied
Mathematics (Independent
Studies)
REGISTRATIONICERTIFICATION
• California, Civil Engineer,1984,
RCE 39539
• Alaska, Civil Engineer,1984, CE
7052
• Washington, Professional
Engineer,1986, 0027570
PROFESSIONAL AFFILIATIONS
• American Society of Civil
Engineers
• American Shore and Beach
Preservation Association
• Tau Beta Pi
• Chi Epson
PROFESSIONAL RECOGNITION
• American Institute of Steel
Construction
• Tau Beta Pi Engineering Honors
Fraternity
• Beta Kappa Phi Honors
Fraternity
Thomas J. Fischetti, P.E.
Senior Structural Engineer
EXPERTISE
Mr Fischetti has over 30 years experience in civil and structural
engineering and project management His professional experience
encompasses strategic, operational and technical support roles, with
major emphasis leading structural engineering and design services
offered by NCI His broad range of project experience throughout
design, project scheduling, management and controls concerning large
and small projects like buildings, oil platforms, tanks, equipment
supports, treatment plants, pipelines, piers, wharfs and harbors, levees
His engineering expertise encompasses onsite investigations, modeling
and analysis of structures, and preparation of construction documents
for public works and private improvements
EXPERIENCE
U S Army Corps of Engineers, San Francisco District - Structural
Engineer on VE Team for the Pier 36 Removal and Environmental
Compliance project for the Port of San Francisco This VE Study
consisted of demolition of Pier 36, demolition of the marginal wharf
between Piers 30/32 and 38, and repairs to the concrete seawall The VE
study identified 14 alternatives that could potentially add value to the
project
City of Oxnard - Mandalay Bay Seawall Repair, Mandalay Bay, Ca —
Project Engineer for a 14 year on call contract with the City of Oxnard to
provide services for Mandalay Bay's 6 5 mile long seawall and watering
system These services have included seawall repair and maintenance,
plans, specifications and oversight of maintenance dredging, plan checks,
emergency responses to homeowners and storm damage, and
underwater survey oversight This project began in 1993 and is an
ongoing project Over $4,000,000 has been spent to date for various
seawall repairs and maintenance dredging work The contract also
included a multidiscipline Value Engineenng team to conduct a value
study of wastewater treatment plant expansion
Arques Shipyard - Project Manager/Structural Engineer for the Arques Shipyard and Marina in
Sausalito, California An alternative design was proposed for remedial work on two existing piers to
optimize steel pipe -pies with fixed -concrete caps, as well as sheet pile bulkhead and to reduce the
estimated construction cost from $4 5M to $2 3M Creative design solutions that efficiently constrained
construction activity within existing pier footprints not only reduced construction costs, but also simplified
permitting requirements for the project
• Seadrift Association — Project Manager/Civil Engineer for Seadrift Association Bulkhead Replacement
Project, California Prepared construction documents depicting alignment and coordination for existing
utilities and private property improvements for shoreline protection of the nearly 2 5 mile perimeter of
Seadrift Lagoon
• GP Gypsum — Project Manager/Civil Engineer over three tasks for GP Gypsum at their Port of Long
Beach Facility The first was the structural repair of an existing 50-year old concrete wharf that, due to
10/7/2013
Thomas J Fischetti
Page 1 of 3
11
1
G
1
1
NOBLEJ
SUL IAN IS, IN
.aGECc9mpany _
Thomas J. Fischetti, P.E.
Senior Structural Engineer
time and a corrosive environment, developed numerous cracks and spalls Following a comprehensive
inventory of structural damage, which included a digital photographic database Prepared contract
documents to strip, clean, patch and/or epoxy inject damage at roughly 150 locations The second task
was the repair of 18 existing budding piles, using fiber reinforced jackets, which were extensively
corroded around the piles The repair methods anticipated future repairs elsewhere on the structure to
reduce future repair costs The final task evaluated wharf fender alternatives, prepared cost estimates,
and provided recommendations to replace the deteriorated fenders
City of Emeryville - Civil Engineer for the replacement of a 1,200-foot long timber pile breakwater with a
prestressed concrete sheet pile breakwater laterally supported with prestressed concrete piles Other
project components consisted of a cast -in -place concrete public boardwalk for 665 feet of the structure, a
ap cap for the rest of the structure, an approach walkway to the boardwalk, and a windsurfer launching
ramp adjacent to the breakwater The work included inspection of the existing structure, plan formulation
and cost estimating, engineering analysis, design, assistance with permitting, preparation of construction
drawings and contract documents, resident inspection, and engineering during construction
U S Army Corps of Engineers, San Francisco District - Civil Engineer working under an on -call civil
engineering services contract, performed detailed design and prepared construction documents for four
levees totaling roughly 2-miles to contain pumped -in dredged material The owner is the California
Coastal Conservancy, but the work was done under contract to the San Francisco District Corps of
Engineers Design work included evaluating potential onsite borrow areas, demolition, design of drainage
culverts and access ramps, connections to an existing levees, design of the levee cross -sections for a
variety of slope for aesthetic considerations Prepared quality computations and construction cost
estimates using MCACES Specifications were prepared using SPECSINTACT
• Harbor Offshore, Inc. - Project Manager/Civil Engineer for the Bureau of Reclamation's fish bypass
facility rehabilitation Project in Tracy, California Performed structural engineering design for support of
temporary construction loads involving structural analysis of existing concrete pier structure and, where
needed, design of crane bearing pads for safe transfer of anticipated temporary construction loads while
the contractor replaced intake ducts Fabrication drawings and the finite element structural calculations
were submitted for Bureau approval before mobilizing the site
• Brown $ Caldwell, Oxnard, CA - Project Manager, Lead Civil Engineer and Lead Structural Engineer for
the San Luis Obispo Water Reuse Project Treatment and distribution facilities were designed and
constructed for the $13 6M project to allow the City of San Luis Obispo to deliver reclaimed water to
agricultural, recreational and industrial users, which included Value Engineering Study
• Brown $ Caldwell, Oxnard, CA - Project Manager/Civil Engineer for design of a $3 6M tilt -up concrete,
nine -bay truck maintenance shop and site improvements for the City of San Diego Vehicle Maintenance
Facility
• Central Coast Water Authority (CCWA) - Project Engineer for Central Coast Water Authority (CCWA)
assigned to the State Water Project constructed through San Luis Obispo and Santa Barbara counties
Managed the planning, design, construction and start-up of a 140 mile potable water pipeline, water
treatment plant and pump station Responsibilities included review of civil design calculations and
drawings, schedule and cost control to insure timely and effective completion of project activities,
identifying problems, alerting parties affected or involved in potential cost or schedule variances, following
up to resolve cost or schedule issues
• SP Inc Engineer's, Anchorage, AK - Principal Civil Engineer responsible for preparation of civil and
structural engineering designs and construction documents for architectural and civil works projects in
Alaska including Soldatna Medical Clinic, Valdez College Renovation, and design and construction
Thomas J Fischetti
10/7/2013 Page 2 of 3
G
F
1
A
�I
F
1
11
Thomas J. Fischetti, P.E.
Senior Structural Engineer
management of various projects at twenty-six facilities throughout the state of Alaska for the US Postal
Service
• Mueller Construction, Anchorage, AK - Engineering Manager for commercial and residential design /
build projects Responsible for production of civil and structural engineering design and drawings, and the
coordination of all other architectural engineering disciplines Also, implemented and managed personal
computer based project estimating/costing system
• CIF Brown Engineering & Construction, Alhambra, CA - Structural design of a multi -billion dollar
refinery project with modules constructed in Japan and shipped to Saudi Arabia Established modeling
techniques and input forms to streamline structural analysis Developed, documented, and trained a
mainframe database application to compute the center -of -gravity of each module
11 10/7/2013
Thomas J Fischetti
Page 3 of 3
11
EXHIBIT "B"
Payment Schedule (Hourly Payment)
A. Hourly
CONSULTANT'S fees for such services shall be based upon the following hourly rate and cost
schedule:
B. Travel Charges for time during travel are not reimbursable.
C. Billina
All billing shall be done monthly in fifteen (15) minute increments and matched to an
appropriate breakdown of the time that was taken to perform that work and who
performed it.
2. Each month's bill should include a total to date. That total should provide, at a glance,
the total fees and costs incurred to date for the project.
3. A copy of memoranda, letters, reports, calculations and other documentation prepared
by CONSULTANT may be required to be submitted to CITY to demonstrate progress
toward completion of tasks. In the event CITY rejects or has comments on any such
product, CITY shall identify specific requirements for satisfactory completion.
4 CONSULTANT shall submit to CITY an invoice for each monthly payment due.
Such invoice shall:
A) Reference this Agreement;
B) Describe the services performed;
C) Show the total amount of the payment due;
D) Include a certification by a principal member of CONSULTANT's firm that
the work has been performed in accordance with the provisions of this
Agreement; and
E) For all payments include an estimate of the percentage of work completed.
Upon submission of any such invoice, if CITY is satisfied that CONSULTANT is
making satisfactory progress toward completion of tasks in accordance with this
Agreement, CITY shall approve the invoice, in which event payment shall be made
within thirty (30) days of receipt of the invoice by CITY. Such approval shall not be
unreasonably withheld. If CITY does not approve an invoice, CITY shall notify
CONSULTANT in writing of the reasons for non -approval and the schedule of
performance set forth in Exhibit "A" may at the option of CITY be suspended until
the parties agree that past performance by CONSULTANT is in, or has been brought
into compliance, or until this Agreement has expired or is terminated as provided
herein.
1
Exhibit B
5. Any billings for extra work or additional services authorized in advance and in writing
by CITY shall be invoiced separately to CITY. Such invoice shall contain all of the
information required above, and in addition shall list the hours expended and hourly
rate charged for such time. Such invoices shall be approved by CITY if the work
performed is in accordance with the extra work or additional services requested, and if
CITY is satisfied that the statement of hours worked and costs incurred is accurate.
Such approval shall not be unreasonably withheld. Any dispute between the parties
concerning payment of such an invoice shall be treated as separate and apart from the
ongoing performance of the remainder of this Agreement.
2
Exhibit B
RIM It, 1911 all,
Labor* (per hour
Senior Principal Engineer
$310
Construction Cost Estimator
$150
Principal Engineer
260
Senior Survey Engineer
150
Senior Associate Engineer
228
Staff Engineer III
146
Associate Engineer
212
Staff Engineer 11
142
Associate Economist
212
Staff Engineer I
127
Senior Structural Engineer 11
198
Surveyor ll
122
Senior Structural Engineer I
184
Surveyor 1
108
Senior Engineer H
198
Senior Construction Inspector
118
Senior Engineer I
184
CARD Designer/Operator
118
Structural Engineer
172
Assistant Engineer
113
Project Engineer 11
162
Construction Inspector
108
Project Engineer 1
150
Technician
93
Construction Manager
158
Word Processing / Clerical
84
* Depositions, mediations, arbitrations, and court appearancdabor is two times the rate shown and billed in
1/2-day increments.
Reimbursable
F.xnenses*
In -home
Survey Vessel
$300 per day
CARD Plots
$2.00 per page
RTK-DGPS Surveying
375 per day
Imagenex Profiling Sonar
375 per day
Locus DGPS Surveying
275 per day
Imagenex Side Scan Sonar
375 per day
DGPS Navigation System
375 per day
Sparker Sub -bottom Profiler
400 per day
Gyro
25 per day
Uniboom Sub -bottom Profiler
350 per day
Motion Compensator
200 per day
3.5 Tuned Transducer System
250 per day
Precision Depth Sounder
75 per day
Marine Magnetometer
200 per day
Tide Gage
75 per day
Underwater Video System
125 per day
Theodolite/Total Station
150 per day
Truck
100 per day
Radios
15 per day
Generator
50 per day
Photocopying
0.30 per page
Inspector Boat
100 per day
Color Photocopy (8-1/2xI 1)
1.00 per page
Automobile
1.00 per mile
Color Photocopy (11x17)
125 per page
Qui-o&ocket
Travel, Subconsultants, Printing, Communication, etc.
In-house at scheduled rate
plus 15%. Out-of-pocket at cost plus 15%.
Invoices
Bills are due and payableon presentation. Interest at 1.5% per month (but not exceedingthe maximum rate
allowable by law) is payable
on any amounts not paid within 30 days.
January 2013
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
PROFESSIONAL SERVICES CONTRACT BETWEEN
THE CITY OF HUNTINGTON BEACH AND
NOBLE CONSULTANTS, INC
FOR
ON CALL CIVIL ENGINEERING SERVICES
Table of Contents
Scopeof Services .................... ............................. .............................................. ... I
City Staff Assistance.........................................................................................2
Term; Time of Performance...........................................................................2
Compensation...................................................................................................2
ExtraWork...........................................................................................................2
Methodof Payment.......................................................................................3
Disposition of Plans, Estimates and Other Documents
.......................................3
HoldHarmless......................................................................................................3
Professional Liability Insurance..........................................................................4
Certificate of Insurance ..............................................................................
5
Independent Contractor........................................................................................
6
Termination of Agreement....................................................................................6
Assignment and Delegation............................................................................6
Copyrights/Patents.................................................
......................................7
City Employees and Officials..........................................................................7
Notices........................................................................................7
Consent................................................................................................................8
Modification.......................................................................................................8
SectionHeadings.............................................................................................8
Interpretation of this Agreement.........................................................................8
DuplicateOriginal........................................................................................9
Immigration............................................................................
..................... 9
Legal Services Subcontracting Prohibited...............................................................9
Attorney's Fees........................................................................................................10
Survival...........................................................................................................10
GoverningLaw.................................................................................................10
Signatories................................................................................................................10
Entirety..............................................................................................................10
Effective Date ............................. ... ........................
................. I I
2015 List of Consultants Submitted RFQ
Vendor Name
Vendor Name
Advantec Consulting Engineers, Inc
KCG Consulting Group
AECOM Technical Services, Inc
Kleinfelder
AESCO, Inc
KOA Corporation
AKM Consulting Engineers
Koury Engineering & Testing, Inc
Albert Grover & Associates
KPFF Consulting Engineers
Alta Planning + Design
Langan Engineering and Environmental Inc
American Geotechnical, Inc
LEE & RO, Inc
Anchor QEA
Leighton Consulting, Inc
AndersonPenna Partners, Inc
MARRS Services, Inc
APA Engineering, Inc
McLean & Schultz
Axiom Corporation
Mirjahangir Engineering/Amiran Construction Co
BKF Engineers
Moffatt & Nichol
Case Land Surveying, Inc
MTGL, Inc
CivilSource, Inc
Myers Houghton & Partners, Inc
Civil Works Engineering
Ninyo & Moore
Converse Consultants
Noble Consultants, Inc
COWI Marine North America
Onward Engineering
CWE
Pacific Advanced Civil Engineering, Inc
D Woolley & Associates
PENCO Engineering, Inc
DKS Associates
Professional Service Industries
DMc Engineering
Psomas
ERSC Inc
Quantum Quality Consulting, Inc
FPL & Associates, Inc
RBF Consulting
Fugro Consultants, Inc
Richard Brady & Associates
Geocon West, Inc
SA Associates
Geo-Environmental, Inc
Sequoia Consultants
GeoLogic Associates, Inc
Stetson Engineers Inc
GEOSCIENCE Support Services, Inc
Tait & Associations, Inc
Geosyntec Consultants
Terracon Consultants, Inc
GHD
Tetra Tech
GMU Geotechnical, Inc
Towill, Inc
Group Delta Consultants, Inc
Transpo Group
Guida Surveying Inc
TTG Engineers
Gwynne Pugh Urban Studio
Twining, Inc
Harris & Associates, Inc
VA Consulting, Inc
IDS Group, Inc
W G Zimmerman Engineering, Inc
Interwest Consulting Group
West Yost Associates
Iteris
Westberg + White
Joseph C Truxaw and Associates, Inc
Willdan Engineering
1A" CERTIFICATE OF LIABILITY INSURANCE
D /DDIYYYY)
5/18/ 18/2015
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER THIS
CERTIFICATE DOES NOT AFFIRMATIVELY OR NEGATIVELY AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES
BELOW THIS CERTIFICATE OF INSURANCE DOES NOT CONSTITUTE A CONTRACT BETWEEN THE ISSUING INSURER(S), AUTHORIZED
REPRESENTATIVE OR PRODUCER, AND THE CERTIFICATE HOLDER
IMPORTANT If the certificate holder Is an ADDITIONAL INSURED, the pollcy(les) must be endorsed If SUBROGATION IS WAIVED, subject to
the terms and conditions of the policy, certain policies may require an endorsement A statement on this certificate does not confer rights to the
certificate holder in lieu of such endorsement(s)
PRODUCER
Alexander and Sanders Insurance Inc
4610 BLUEBONNET BLVD., SUITE A
BATON ROUGE LA 70809
CONTACT Alexander & Sanders
NAME
PHONE F�fl(225)295-2995 FAX No (225)368-2145
atMAILSsnfo@alexsand.coin
INSURERS AFFORDING COVERAGE
NAIC #
INSURER A Travelers Indemnxt:V CompanV of
25682
INSURED
NOBLE CONSULTANTS, INC
201 Alameda Del Prado, Suite 301
NOVATO, CA 94949
INSURER Travelers Property Casualty CO
25674
INSURER c Travelers Indenrixty CompanV
25658
INSURERDLWC - Louisiana Workers'
22350
INSURERE DPXL — XL Specxalty Insurance
37885
INSURER F
w=ran 151M.1■ �1111010 1,li 1M19]-lrrra■ 111\1111 -
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS
IITR
TYPE OF INSURANCE
ADULISUBR
D
POLICY NUMBER
MM/DD/YYYY
POLICY
M DDT
LIMITS
GENERAL LIABILITY
EACH OCCURRENCE
$ 1,000,000
X COMMERCIAL GENERAL LIABILITY
It IV HtNILD
PREMISES Min occurrence)
$ 300,000
A
CLAIMS -MADE OCCUR
X
6806D491705
4/11/2015
/11/2016
MED EXP (Any one person)
$ 5,000
PERSONAL & ADV INJURY
$ 1,000,000
GENERAL AGGREGATE
$ 2,000,000
GENT AGGREGATE LIMIT APPLIES PER.
PRODUCTS - COMP/OP AGG
$ 2,000,000
POLICY 7 PRO LOC
$
AUTOMOBILE
LIABILITY
COMBINED
Dt SINGLELIMIT
1,000,090
B
X
ANY AUTO
BODILY INJURY (Per person)
$
ALLOSNED SS,ICHEDULEDTOS
X
9303L407
4/11/2015
/11/2016
BODILY INJURY (Per accident)
$
NON -OWNED
HIRED AUTOS AUTOS
PROPERTY DAMAGE
Per accident
$
$
X
UMBRELLA LIAR
X
OCCUR
EACH OCCURRENCE
$ 5,000,000
C
EXCESS LIAR
CLAIMS -MADE
AGGREGATE
$ 5,000,000
DED I X RETENTION$ 10,00C
$
I
PUP8813T626
/11/2015
/11/2026
D
WORKERS COMPENSATION
115754 05
X WC STATU- OTH-
1
AND EMPLOYERS LIABILITY Y)N
EL EACH ACCIDENT
$ 1 000 000
ANY PROPRIETOR/PARTNER/EXECUTIVEIVE
N I A
ICERS INCLUDED
OFFICER/MEMBER EXCLUDED?ff](Mandatory In NH)
roFLICY # 77794
/1/2015
/1/2016
EL DISEASE - EA EMPLOYE
$ 1,000,000
If yes, describe under
E.L. DISEASE - POLICY LIMIT
$ 1,000,000
DESCRIPTION OF OPERATIONS below
E
Professional Liability
DPR9723644
/1/2015
/1/2016
PER CLAIM $ 4,000,000
Claims Made Form
Retro Date FES 23, 1987
AGGREGATE $ 4,000,000
DESCPJP71ON OF OPERATIONS I LOCATIONS I VEHICLES (Attach ACORD 101, Additional Remarks Schedule, If more space Is required)
CONSULTING ENGINEER - FOR PROFESSIONAL LIABILITY COVERAGE, THE AGGREGATE LIMIT IS THE TOTAL INSURANCE
AVAILABLE FOR ALL COVERED CLAIMS PRESENTED WITHIN THE POLICY PERIOD. THE LIMIT WILL BE REDUCED BY
PAYMENTS OF INDEMNITY AND EXPENSE
POLICIES INCLUDE 30 DAY NOTICE OF CANCELLATION PER ATTACHED ENDORSEMENTS
GENERAL & AUTO LIABILITY POLICIES INCLUDE CERTIFICATE HOLDER AS ADDITIONAL INSURED AS REQUIRED BY WRITTEN
CONTRACT
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE
THE EXPIRATION DATE THEREOF, NOTICE WILL BE DELIVERED IN
City of Huntington Beach ACCORDANCE WITH THE POLICY PROVISIONS
Tom Herbel
2000 Main Street AUTHORIZED REPRESENTATIVE
Huntington Beach, CA 92648
Wyatt Sanders/DRACH
A%,UKU Lb (Zulu/Ub) 01988-2010 ACORD CORPORATION All rights reserved
INIS025 (9n1nai) ni Tho Arewn nnmo nnri Innn aro rnnaafarad rltorlra of Arnpn
�
XLOPPROFESSIONAL LIABILITY �
This endorsement, efh*ubve12U1am. forms apart of `
Policy No issued to
THIS ENDORSEMENT CHANGES THE POLICY PLEASE READ [TCAREFULLY
POLICYCANCELLATON—NOTICETODESIGN
Thisendorsemantmodifiesmourance provided under the followingCONSULTANTS AND ENGINEERS
Section X OTHER CONDITIONS, B CANCELLATION is a 6'rided by the addifi- of the foil Ing
In the event that the Company cancels this Policy f9r ariy stalutonlylpermitted reason 6146rthan non-
payment of premium, the Company agrees to provide`� - ",C,,,),days'K6t1i;e of cancel0lo—n of this Policy
to any entity with whom the NAMED INSURED agr6ed in a written contr'a'ct-jor agreement would be
provided with notice of cancellation of this Policy, O�Aded thaF
• The Company receives, at least 15,days prior to tt�� date of cancellati6n, a written request from
the NAMED INSURED to provide nofj�6 6fcancellatjqn to entities designated by the NAMED
INSURED to receive such notice and—
• The written request m6lua6sj the name a6d add-r4s of ea�&`person or entity designated by the
This endorsement does, not apply to iion-re�&W-Pflhe policy, cancellation at the INSURED's request, or
to cancellation of th(k�61ic: - or non-payment of premlbi� to the Company or to a premium finance
company authorized tocancel the Policy.1k 'Iriothing contained in this endorsement shall be
construed to provide aqyfrighis�4der the PGfi�y,�o the entities receiving notice of cancellation pursuant to
this endorsement, nor sii�ll this endorsement �mend or alter the effective date of cancellation stated in
Ali other terms and co , ndifi6ris of the Policy remain unchanged
F-111! Will " M�,wwo ".." ':�V'u
01,
Michael Gates, City AttorwiW ___q
LOD4521O13 @2O13XL America, Inc All Rights Reserved Page 1of1
il
P
AV
City of HuntingtonBeach
2000 Main Street 0 Huntington Beach, CA 92648
(714) 536-5227 O www.huntingtonbeachca.gov
Office of the City Clerk
Joan L. Flynn, City Clerk
July 23, 2015
Noble Consultants, Inc
Attn Ronald M Noble
359 Bel Marin Keys Blvd #9
Novato, CA 94949
Dear Mr Noble
Enclosed for your records is a copy of the fully executed "Professional Services Contract
Between The City of Huntington Beach and Noble Consultants, Inc for On Call Civil
Engineering Services "
Sincerely,
Joan L Flynn
City Clerk
JF pe
Enclosure
Sister Cities Anjo, Japan 0 Wartakere, New Zealand
July 23, 2015
Noble Consultants, Inc
Attn Ronald M Noble
Novato, CA 94949
Dear Mr Noble
City Of Huntington Beach
2000 Main Street o Huntington Beach, CA 92648
(714) 536-5227 o www.huntingtonbeachca.gov
Office of the City Clerk
Joan L. Flynn, City Clerk
AL14- W E�,4 v &--z-
Enclosed for your records is a copy of the fully executed "Professional Services Contract
Between The City of Huntington Beach and Noble Consultants, Inc for On Call Civil
Engineering Services "
Sincerely,
9 AW
erp Qmd&14*^*%1
Joan L Flynn
City Clerk
JF pe
Enclosure
Sister Cities Anjo, Japan 0 Waitakere, New Zealand
Soot
L%-
's w t
ii
t
4^GN9�51"i
i"s�i'lY>+sirf� t�t�..Fty;SCCIr z x P. K ' V
gffi
� 5y�'�'��`T+`��`+�`�a. i�,`'rx?��.#��wM x�, s`�rr i��; ` •1�1
k T
�� 74J�
' sue=
"�„tn'
# g�4 4 - �r gar ,�a� Jai o
071,
�N w" W
, , -� 541
t s°
`..,"'"TZi,�;3.'yt^,,r nu �str� �Zr'+�,��"��x"<t�'.; ,.'� _ ••
ca
+i uti"� -+," p ON
>
v s,4 x *, sai 3 Rad a n
2 `$ iihe yr ss ina O +1 Lf1 O
':"I'V �d�''2r". `n�4 .. _ ' r z- .C4 C''i Z-
��"�� �,,�=��'�"-''"� � r'L��'' s�;"1^�K+s �z���`� ` �:• a � �J�a a,`s'��.`.'. �;�i �bs,� � i w` ,
'— • ti'`"r �,.'f �i":='-r' s�'yS,'_#`a�r„�c�'h'-'�%'':j`t�':-t."a..s "; _ s ®' . - • •
nra• ,�3 ryc sh x�„� .- � , '.t.'.+� Spa G;.�e . �c V �` .ix 5t.�` � ° N
`'`Y� sr ,
Ayy'j( _•-�K,�y,`a y'.+,+�µi,�y��k-;: d;- �1- s�..t- tS�i.>a}� �. �'�+a
r'rW� Sv R .,'S.'*!`'dt"�.++^
w {gym t'4 r��
�-t,4',� C ,rY`-�.->•. `� . ' `� r"" x� i'���ix•,,<,.r,� awn..-,.•,'° y .�'„,'° .,
z+4'3 ;'frj{
�M >��i „''-w „'� t°�`}€�,., $, 4 ,F.� rp iF�;'�s , a�er�-,+ �- = r � �.- r�F zx�'".r". � .�="vW ^;�; - {�� • � �s x t�<
';;cA..a<"r� -= ^' tw�aw.;1y5w :�,=='u,s,�t"c
m�+v�P,Ir A—
j't'�`'•`.,G'``t.r-•�4��"�i, '..,'r..'u,1
•.�. ��T,."i��, w.pb� �I�(�µ,�,b�n`*kf�,�' 2 7'i:rve �1� d^ � ��`"i �r:""T+°'� yy. ������ �y�
�` �, � ; � ?w y+slfv ,.,.^ F¢iF),� 1J �"'�h� � ",F; t�:%f ; >.:"`�,�.., • '=rir�F., -`� -v" '� 3 - ,�i ,,'`' y ,a ' u 'gyp'{ �y "�
y S'�tY,,`Y,fe - ,•�A�-
ii,z4 `=sxLv7NW6 a 'tyk 1`- t : kt, i 5` �r1 y
yµf'
lv
fn,
� ptyi 3
'� t � 'T, 7 "V'
f 2 k µ `V'Ra'
Sf»:p Y 1��a `;g,�`^,Kga ns,r���r�`L ry kT:`m'^i.'"' •E" �,_`'` a�j4 - �'`