Loading...
HomeMy WebLinkAboutWESTIN ENGINEERING, INC - 1998-11-16!�7 �(u//q 'TY OF HUNTINGTON BEAC 99 / MEETING DATE: DEPARTMENT ID NUMBER: PW 99-118 Council/Agency Meeting Held: 2pprov�l_ rred/Continued to: n ❑ Conditionally Approved ❑ Denied Council Meeting Date: V/OD.1d �o 1erk's Signature 45y r�C Department ID Number: PW 99-118 CITY OF HUNTINGTON BEACH �' REQUEST FOR ACTION'`'' SUBMITTED TO: HONORABLE MAYOR AND CITY COUNCIL MEMBERS > > �a c� SUBMITTED BY: ,, RAY SILVER, City Administratora,W PREPARED BY: ABERT F. BEARDSLEY, Director of Public Work SUBJECT: AMEND CONTRACT WITH WESTIN ENGINEERING, INC. SCADA SYSTEM MASTER PLAN FOR UPGRADING WATER SYSTEM OPERATIONS Statement of Issue, Funding Source, Recommended Action, Alternative Action(s), Analysis, Environmental Status, Attachment(s) Statement of Issue: It is necessary to perform additional engineering and field-testing to prepare the final radio design to prepare drawings and specifications as part of the Supervisory Control and Data Acquisition (SCADA) construction contract documents. Funding Source: Funds in the amount of $41,000 are available in the Water Capital Improvements budget. Recommended Action: Motion to: 1. Approve Amendment No. 1 to Professional Services Contract CC-1092 between the City of Huntington Beach and Westin Engineering, Inc.; and 2. Authorize the Mayor and City Clerk to execute the amendment. Alternative Action(s): Deny approval and direct the department to proceed with alternative action. Specifications for construction cannot be completed without design and field testing for spread spectrum radio system Analysis: The existing SCADA system installed in 1987 is not redundant, uses obsolete equipment, has limited data capability, and is subject to failure for the water system and flood control pump stations. The new SCADA system will provide a high level of reliability, enhance system functions, provide greater operational flexibility and reduce maintenance. The Master Plan report prepared by Westin Engineering, Inc. recommends spread spectrum radio as the most cost effective and reliable communication method. This result was not anticipated in the original agreement (CC-1992). Westin completed the Master Plan Phase I portion of their contract in a professional and efficient manner and can complete this additional work efficiently because of their intimate knowledge of the existing systems. Public Works Commission Review: Not required, per Municipal Code Chapter 2.111. Environmental Status: Not applicable for design services. Follow-up construction contracts will incorporate the necessary California Environmental Quality Act compliance. Attachment(s): Amendment No 1 to Agreement between the City of Huntington Beach and Westin Engineering, Inc. to Prepare a SCADA system Master Plan for Upgrading City's System for Water Operations (CC-1092). RCA Author: T. Rulla:jm #36577 RCA SCADA AMENDMENT NO. 1 -- 11/03/99 8:18 AM CJ Ljote CITY OF HUIVTINGTON BEACH 2000 MAIN STREET CALIFORNIA 92648 OFFICE OF THE CITY CLERK CONNIE BROCKWAY CITY CLERK LETTER OF TRANSMITTAL OF ITEM APPROVED BY THE CITY COUNCIL/ REDEVELOPMENT AGENCY OF THE CITY OF HUNTINGTON BEACH DATE: Qy'7qA, TO: ATTENTION: 11 ',t �& ah-d y1,5 Name i DEPARTMENT: .GGtSfYI r �zlFO:� Y1l lo�la�D REGARDI�i TG: 1�1��7aI 11��Y4C� City, State, Zip 41 See Attached Action AQenda.Item �'"!� Date of Approval !/ Enclosed For Your Records Is An Executed Copy Of The Above Referenced Agenda Item. Remarks: 1-� Connie Brockway City Clerk Attachments: Action Agenda Page Agreement Bonds Insurance RCA Deed Other CC: Nam D� men,t J F�tCA,/ Agreeme Insurance Other U D Nam Department RCA Agreement Insurance Other Name Department RCA Agreement Insurance Other Name Department RCA Agreement Insurance Other Risk Management Dept. Insurance Received by Name - Company Name - Date G:Followup/coverltr (Telephone: 714-536-62271 AMENDMENT NO. 1 TO AGREEMENT BETWEEN THE CITY OF HUNTINGTON BEACH AND WESTIN ENGINEERING, INC. TO PREPARE A SCADA SYSTEM MASTER PLAN FOR UPGRADING CITY'S SYSTEM FOR WATER OPERATIONS (CC-1092) THIS AMENDMENT is made and entered into the day of , 1999, by and between the CITY OF HUNTINGTON BEACH, a California municipal corporation, hereinafter referred to as "City", and WESTIN ENGINEERING, INC., a California corporation hereinafter referred to as "CONSULTANT." WHEREAS, CITY and CONSULTANT are parties to that certain agreement, dated November 16" 1998, entitled "Agreement Between the City of Huntington Beach and Westin Engineering, Inc., to Prepare a SCADA System Master Plan for Upgrading City's System for Water Operations" which agreement shall hereinafter be referred to as the "Original Agreement," and Since the execution of the Original Agreement, CITY has requested additional work from CONSULTANT and CONSULTANT has agreed to perform such work; and CITY and CONSULTANT wish to amend the Original Agreement to reflect additional work to be performed by CONSULTANT, and the additional compensation to be paid in consideration thereof by CITY to CONSULTANT, NOW, THEREFORE, it is agreed by CITY and CONSULTANT as follows: ADDITIONAL WORK CONSULTANT shall provide to CITY such additional services required for the PROJECT, described in CONSULTANT's letter to CITY dated September 17, 1999, a copy of which is attached hereto as Exhibit "A," and incorporated by this reference as though fully set forth herein. 2. ADDITIONAL COMPENSATION In consideration of the additional services to be performed hereunder as described in Section 1 above, CITY agrees to pay CONSULTANT, and CONSULTANT agrees to accept from CITY as full payment for services rendered, an additional sum not to exceed Forty One Thousand Dollars ($41,000). REAFFIRMATION Except as specifically modified herein, all other terms and conditions of the Original Agreement shall remain in full force and effect. agreement/westin amend #L/jmp/09/27/99 • • IN WITNESS WHEREOF, the parties hereto have caused this Agreement to be executed by and through their authorized offices the day, month and year first above written. WESTIN ENGINEERING, INC. By: v f/ print name ITS: (circle one) Chairma residen ice President CITY OF HUNTINGTON BEACH, a municipal corporation of the State of California Mayor ATTEST: 7/D .By: City Clerk erry W. Garrett, P.E. print name .APPROVED AS TO FORDf: ITS: (circle one) Secretary/Chief Financial _ Officer/Asst. Secretary easure elm' s "Z1 If City Attorney �1it_ .95&�-A V1 II�ITI /2: AND REVIEWED AND APPROVED: APPRO ED:y Director of Public Works City A ministrator 2 agreement/westin amend #1/jmp/09/27/99 OL • • Westin Engineering, Inc. 'y z 2512 Chambers Road, Suite 201 Tustin, California 92680 (714) 838-3620 Fax (714) 838-0853 µ 17 September 1999 . __..WEM008 City of Huntington Beach -_ Public Works Department 2000 Main Street Huntington Beach, California 92647 Subject: SCADA Radio Engineering Attn: Mr. Tom Rulla Attached to this letter is Westin Engineering's proposal for the Water SCADA System.Spread Spectrum Radio Engineering. Westin is -in -a unique position to perform this engineering work for the City.based on our having just completed the SCADA Master Plan, and our familiarity with the specific communication requirements for all of the field sites. The result of the spread spectrum radio engineering is a prerequisite for the completion of the SCADA Technical Specification. Based on the City'. s approval -of this proposal, Westin is prepared to start the work immediately, which will support the timely completion of the SCADA Technical Specification. Enclosurc Regards, William Gabris Principal Engineer An employee owned company Detroit • Houston • Los Angeles • Sacramento • San Jose Seattle • Sydney • City of Huntington Beach Proposal Spread Spectrum Radio System September 16,1999 Following is a summary of the tasks required for the design of the spread spectrum radio system and the development of the additional technical specifications to support the City of Huntington Beach Water Operations SCADA system. Task 1- Site isit A site visit will be conducted to become familiar with the surrounding area (general terrain and potential radio path obstructions) and the individual sites. Information will be gathered at each site that will be required in the design of the system and the development of the specification. An example of the type of information required is as follows: • Antenna mount location and height • Type of antenna mount required • Potential radio path obstructions _ • Identify potential locations for the radio equipment mounting • Determine possible antenna feedline routes and length of run • Identify possible grounding points for the equipment and antenna structure Task 2! PreliminarySystem Design The information gathered in Task I will be used, along with computer generated path profiles, to develop a preliminary system topology. During this process we will determine the number and location of the master radio sites, and make a preliminary assessment as to which master radio site that each remote radio should communicate with. A determination will also be made regarding the appropriate communications medium to use from each radio master radio site to the SCADA Master Station. The path profiles will be conducted using in-house radio system design software to determine if a clear line -of -sight path exists between each remote site and at least one of the master radio sites. T,gsk 3- Field Testing Field tests will be conducted to verify that the preliminary system design will provide reliable radio communications. All of the sites will be visited to determine building or other obstructions that would not show up on the topographic maps. Only long paths, and those paths that have been identified as questionable, will be tested. Short paths that are clearly line -of -sight will not be tested. Alternate paths will be tested if one of the initial paths is determined to be unreliable. This proposal is based on visiting approximately 25 sites. Tests will be conducted to determine the received signal level and path reliability. The path reliability will be measured by polling the remote site and determining the number of packets that arrived correctly. During the testing at each site, we will also identify possible radio frequency (RF) interference sources. juk 4 — Final System Design Using the information gathered. in tasks 1 through 3, a final system design will be developed. This design will be presented to the City for review and comment prior to the development of the specification and drawings. Task S — Procurement Speer ation Westin's current contract with the City includes the preparation of the Technical Specifications for the Water SCADA system. This work includes the modem communication interface to the existing leased telephone line. The spread spectrum radio communication system will require additional specifications for the radio equipment, software, and installation from the communication modems (originally interfaced to the leased telephone line) to the new radio system. The spread spectrum radio procurement specification will be developed and will include the following: a System Description General System Requirements • Product Specifications • Contractor Submittals • Radio System Installation • Radio System Testing • Radio System Training Task 6 - Drawings The following drawings will be created in support of the specification: • System Block Diagram • System Interconnect Diagram(s) • Typical Installation Detail Diagram(s) Westin Engineering, Inc. Proposal Costing Spreadsheet Client City of Huntington Beach - Water Operations Project Proposal No. Project Phase Fee Type Dade 9116/99 Terrain Data Teak T ask Usk Task Name Na of Na. of Sub- Task Task Cord Task slot End NO. Trips 0 Days e Contractors Subtotal kwo-Y 709W Date Oat a22224 13 Assoc N Cask SQUIaC-11 C..s PEae SSP4 A d Cuk I J -.-.-.-.-.---K-M 5K- O sbaom0.:ax UP ON 145 95 148 129 111 88 72 62 44 0% Xftl-rMAM/":A3�4 01 Site Visit a .40 1 5 6,974 .0% 6,974 02 Preliminary System Design 8 40 250 6.722 0% 5.722 03 Field Testing 8 56 1 5 4.000 12.750 0% 12.750 04 Final System Design 8 24 3.696 0% 3,696 05 Specitication a 4 40 a 6,636 0% 6.636 06 Drawings 4 24 40 5.780 0% 5.780 07 0 0% 0 08 0 0% 0 09 0 0% 0 10 0 0% 0 1 0 0% 0 12 0 0%. 0 13 0 0%, 0 14 0 0% 0 15 0 0% 0 16 0 0% 0 17 .0 0% 0 18 0 0% 0 19 0 0% 0 20 1 0 0% 0 Labor & CDC 0 0 0 0 24 24 224 0 0 0 40 8 0 2 0. Subtotal 1 0 0 0 0 3,552 3,096 24.864 0 a 0 2.600 496 0 1,200 1'5001 2501 4,000 . ft—M& MR 41,668 X, Sub I Doc project ........... ....... ... Labor Subtotal 34,W8 �' S.triotaij6.950 Total 41.568 .... .... Approved BY: Project Manager Sales Vdustribirector p . DOCUMENT: F.OP-SM-02:C ISSUE: 2.2 FILEProposaUds • • ATTACHMENT #1 RCA AOUTING SHEET INITIATING DEPARTMENT: Public Works SUBJECT: Amend Contract with Westin Engineering Inc. SCADA System Master Plan for Upgrading for Water System Operations COUNCIL MEETING DATE: November 15, 1999 RCA ATTACHMENTS STATUS Ordinance (w/exhibits & legislative draft if applicable) Not Applicable Resolution (w/exhibits & legislative draft if applicable) Not Applicable Tract Map, Location Map and/or other Exhibits Not Applicable Contract/Agreement (w/exhibits if applicable) (Signed in full by the City Attorney) Attached Subleases, Third Party Agreements, etc. (Approved as to form by City Attorney) Not Applicable Certificates of Insurance (Approved by the City Attorney) Not Applicable Financial Impact Statement (Unbudget, over $5,000) Not Applicable Bonds (If applicable) Not Applicable Staff Report (If applicable) Not Applicable Commission, Board or Committee Report (If applicable) Not Applicable Findings/Conditions for Approval and/or Denial Not Applicable EXPLANATION FOR MISSING ATTACHMENTS` EXPLANATION FOR RETURN OF ITEM: RCA Author: Tom Rulla #36577 ��easce�' ,pPr✓ ,#9QAfeAl W47 CITY OF HUNTINGTON BEA �cS MEETING DATE: November 16, 1998 DEPARTMENT ID NUMBER:PW-W- 98/99-01 Council/Agency Meeting Held: �Deferred/Continued to: (Id/Approved, ❑ Conditionally Approved ❑ Denied Qxz& &.4.4 ) PUTy C Jerk's Signature Council Meeting Date: November 16, 1998 1 Department ID Number: Pw-w-98/99-01 CITY OF HUNTINGTON BEACH REQUEST FOR ACTION SUBMITTED TO: HONORABLE MAYOR AND CITY COUNCIL ram, i SUBMITTED BY: RAY SILVER, CITY ADMINISTRATOR/ �i{' 7" PREPARED BY: ROBERT F. BEARDSLEY, DIRECTOR OF PUBLIC WORKS SUBJECT: APPROVAL OF CONTRACT FOR PROFESSIONAL CONSULTING SERVICES FOR UPGRADING OF WATER OPERATIONS SCADA SYSTEM Statement of Issue, Funding Source, Recommended Action, Alternative Action(s), Analysis, Environmental Status, Attachment(s) Statement of Issue: The Water Division of Public Works utilizes a supervisory control and data acquisition (SCADA) system to remotely monitor and control critical components of the water production and distribution and flood control systems located throughout the City. The SCADA system was last upgraded in 1989. Since that time, there have been many advances in technology that could offer the City many advantages. A Request for Proposals (RFP) for an engineering consulting firm to plan, design and oversee the selection, purchase and installation of a new state-of-the-art SCADA system was sent to a number of qualified firms. Westin Engineering of Tustin was selected as the desired consultant for these services. Fundling Source: The total contract amount is $125,675. Funds are available in Water Fund Account EW-PW-869-390-00 ($70,000) and General Fund Account AA-PW-591-390- 00 ($13,783) for the City's portion of the contract (two-thirds or $83,783). The remaining one- third ($41,892) would be funded by the West Orange County Water Board for which the City provides operations and maintenance, administration, engineering, secretarial and fiscal agent duties by contract. SCADARCA.DOC -2- 11/04/98 4:50 PM REQUEST FOR ACTION MEETING DATE: November 16, 1998 DEPARTMENT ID NUMBER:PW-W- 98/99-01 Recommended Action: Motion to: 1. Approve the selection of Westin Engineering Inc., Tustin, for the planning, design and installation oversight services for the upgrade of the Water Division's existing SCADA system; 2. Approve and authorize execution of the attached contract between the City and Westin Engineering, Inc., subject to the West Orange County Water Board approving the selection of Westin Engineering, Inc. and the expenditure of budgeted funds for their share of the project costs; = 3. Approve the Settlement Committee recommendation to modify the Indemnification and Hold Harmless paragraph of the attached agreement with Westin. Alternative Action(s): Deny approval and instruct staff on how to proceed. Analysis: The Water Division of Public Works utilizes a supervisory control and data acquisition (SCADA) system to remotely monitor and control electronic components and controls of the water production and distribution and flood control systems operated by the City. These control components are located in such facilities as ground water well facilities, booster pumping stations, import water feeder locations and flood control stations. Through signals currently transmitted via phone lines, Water Division staff is able to monitor the function of all these remote facilities from the Water Operations Yard and, via a paging and computer modem system, from the on -call employee's home. Information obtained from the system includes equipment status changes, engine run and failure status and flow and pressure changes. More importantly, the system allows for remote control of these components, which can be critical in cases of emergency. Roughly one-third of the locations included in the proposed project are part of the City's water production and distribution systems. Another one-third are flood control stations and the remaining one-third are imported water feeder facilities owned by the West Orange County Water Board (WOCWB). WOCWB is a joint powers agency comprised of the Cities of Huntington Beach, Garden Grove, Westminster and Seal Beach. Funds for WOCWB's portion of the upgrade and installation of the SCADA system are provided in its approved Fiscal Year 1998/99 budget. The WOCWB meets quarterly and their next meeting is scheduled on December 15, 1998. Since the Board only meets quarterly, it is proposed that the City Council take action on approving and authorizing the contract with Westin Engineering, Inc. subject to the WOCWB approving Westin and the expenditure of their budgeted funds for the project. Otherwise, the City would have to delay starting the project until January or February 1999, if the City Council's action on the matter is delayed until after the WOCWB takes it's action. The SCADA system was last upgraded in 1989. Since that time, there have been many advances in technology that could offer the City many advantages. The current hardware SCADA -3- 11/10/98 2:14 PM REQUEST FOR ACTION MEETING DATE: November 16, 1998 DEPARTMENT ID NUMBER:PW-W- 98/99-01 and remote terminal units (RTUs) are obsolete and no longer are supported by the manufacturer, which leaves no options should the equipment fail. In addition, the current system has a reading or "polling" cycle of about 4 minutes. New technology offers much shorter polling cycles, which in turn improves reliability of the entire system. On June 16, 1998, a Request for Proposals (RFP) for an engineering consulting firm to plan, design and oversee the selection, purchase and installation of a new state-of-the-art SCADA system was sent to a number of qualified firms. Each firm was asked to submit a written response by July 22, 1998. Proposals were received from three firms: Westin Engineering, Sun Engineering Services and Northern Digital. A three member committee prepared written evaluations of each proposal. On the basis of qualifications, meeting proposal requirements, and experience of project staff, Westin Engineering of Tustin was selected as the desired consultant for these services. Westin's insurance carrier cannot provide the coverage that meets the indemnification and Hold Harmless requirements of the City's contract. A request was submitted to the Insurance Settlement Committee for a waiver to our requirements and, on October 6, 1998, a waiver was recommended for approval. The following paragraph, approved by the Insurance Settlement Committee, shows the revised wording, with the addition of the word "negligent," approved by the Insurance Settlement Committee. Approved Clause CONSULTANT shall .protect, defend, indemnify and hold harmless CITY, its officers, officials, employees and agents from and against any and all liabilities, loss, damage, expenses, costs (including, without limitation, costs and `fees of litigation of every nature) arising out of or in connection with CONSULTANT'S negligent performance of this Agreement or its failure to comply with any of its obligations contained in this Agreement by CONSULTANT, its officers, agents or employees, except such loss or damage which was caused by sole negligence or willful misconduct of CITY. Environmental Status: Not applicable. Attachment(s): Agreement for Consultant Services 2 Scope of Services — Exhibit A Certificates of Insurance 3, Application for Insurance Requirements WaweR 00, SCADA -4- 11/10/98 2:16 PM REQUEST FOR ACTION RCA Author: Ken Dills , phone extension 5055 DEPARTMENT ID NUMBER:PW-W- SCADA -5- 11/10/98 2:16 PM 5.3.03 AI*MC' �oGvrr�e��ie�» REQUEST FOR ACTION MEETING DATE: November 16, 1998 DEPARTMENT ID NUMBER:PW-W- 98/99-01 and remote terminal units (RTUs) are obsolete and no longer are supported by the manufacturer, which leaves no options should the equipment fail. In addition, the current system has a reading or "polling" cycle of about 4 minutes. New technology offers much shorter polling cycles, which in turn improves reliability of the entire system. On June 16, 1998, a Request for Proposals (RFP) for an engineering consulting firm to plan, design and oversee the selection, purchase and installation of a new state-of-the-art SCADA system was sent to a number of qualified firms. Each firm was asked to submit a written response by July 22, 1998. Proposals were received from three firms: Westin Engineering, Sun Engineering Services and Northern Digital. A three member committee prepared written evaluations of each proposal. On the basis of qualifications, meeting proposal requirements, and experience of project staff, Westin Engineering of Tustin was selected as the desired consultant for these services. Westin's insurance carrier cannot provide the coverage that meets the indemnification and Hold Harmless requirements of the City's contract. A request was submitted to the Insurance Settlement Committee for a waiver to our requirements and, on October 6, 1998, a waiver was recommended for approval. The following paragraph, approved by the Insurance Settlement Committee, shows the revised wording, with the addition of the word "negligent," approved by the Insurance Settlement Committee. Approved Clause CONSULTANT shall protect, defend, indemnify and hold harmless CITY, its officers, officials, employees and agents from and against any and all liabilities, loss, damage, expenses, costs (including, without limitation, costs and fees of litigation of every nature) arising out of or in connection with CONSULTANT'S negligent performance of this Agreement or its failure to comply with any of its obligations contained in this Agreement by CONSULTANT, its officers, agents or employees, except such loss or damage which was caused by sole negligence or willful misconduct of CITY. Environmental Status: Not applicable. Attachment(s): 1. Agreement for Consultant Services 2 Scope of Services — Exhibit A 9- a Certificates of Insurance A3, Application for Insurance Requirements SCADA -4- 11/10/98 2:16 PM ATTACHMENT 1 PROFESSIONAL SERVICES CONTRACT BETWEEN THE CITY OF HUNTINGTON BEACH AND WESTIN ENGINEERING, INC. TO PREPARE A SCADA SYSTEM MASTER PLAN FOR UPGRADING CITY'S SYSTEM FOR WATER OPERATIONS (CC-1092)) THIS AGREEMENT, made and entered into this_Ljg=day of /V Dz,=,�7.P.t' , , 1998, by and between the City of Huntington Beach, a municipal corporation of the State of California, hereinafter referred to as "CITY", and a WESTIN ENGINEERING, INC. corporation, hereinafter referred to as "CONSULTANT." WHEREAS, CITY desires to engage the services of a consultant to provide engineering services for the planning, design, and oversight of the selection, purchase and installation of a computerized supervisory control and data acquisition (SCADA) system for the water operations (CC-1092) in the City of Huntington Beach; and Pursuant to documentation on file in the office of the City Clerk, the provisions of HBMC Chapter 3.03 relating to procurement of professional service contracts has been complied with; and CONSULTANT has been selected to perform said services, NOW, THEREFORE, it is agreed by CITY and CONSULTANT as follows: 1. WORK STATEMENT CONSULTANT shall provide all services as described in the Request for Proposal, and CONSULTANT's proposal dated July 23, 1998 (hereinafter referred to as Exhibit "A"), which is attached hereto and incorporated into this Agreement by this reference. Said services shall sometimes hereinafter be referred to as "PROJECT." CONSULTANT hereby designates William Gabris who shall represent it and be its project manager in all consultations, with CITY during the performance of this Agreement. &agree/j f/wells/ 10/27/98 2. CITY STAFF ASSISTANCE CITY shall assign a staff coordinator to work directly with CONSULTANT in the performance of this Agreement. 3. TIME OF PERFORMANCE Time is of the essence of this Agreement. The services of CONSULTANT are to commence as soon as practicable after the execution of this Agreement and all tasks specified in Exhibit "A" for Phases I and II shall be completed no later than six (6) months from the date of this Agreement. The commencement date and duration of services for Phase III will be mutually established by CITY and CONSULTANT following completion of Phase II. These times may be extended with the written permission of CITY. The time for performance of the tasks identified in Exhibit "A" are generally to be shown in the Scope of Services on the Work Program/Project Schedule. This schedule may be amended to benefit the PROJECT if mutually agreed by CITY and CONSULTANT. 4. COMPENSATION In consideration of the performance of the services described herein, CITY agrees to pay CONSULTANT a fee not to exceed One Hundred Twenty Five Thousand Six Hundred Seventy Five Dollars ($125,675). 5. PRIORITIES In the event there are any conflicts or inconsistency between this Agreement, CITY's RFP, or CONSULTANT's proposal, the following order of precedence shall govern: 1) Agreement, 2) CONSULTANT's proposal, and 3) CITY's RFP. 6. EXTRA WORK In the event CITY requires additional services not included in Exhibit "A," or changes in the scope of services described in Exhibit "A," CONSULTANT will undertake such work after receiving written authorization from CITY. Additional compensation for such extra work shall be allowed only if the prior written approval of CITY is obtained. E & agree/j f/wells/ 10/27/98 7, METHOD OF PAYMENT A. CONSULTANT shall be entitled to progress payments toward the fixed fee set forth herein in accordance with the progress and payment schedules set forth in Exhibit "A". B. Delivery of work product: A copy of every technical memo and report prepared by CONSULTANT shall be submitted to CITY to demonstrate progress toward completion of tasks. In the event CITY rejects or has comments on any such product, CITY shall identify specific requirements for satisfactory completion. Any such product which has not been formally accepted or rejected by CITY shall be deemed accepted. C. - CONSULTANT shall -submit to CITY an invoice for each progress payment due. Such invoice shall: 1) Reference this Agreement; 2) Describe the services, performed; 3) Show the total amount of the payment due; 4) Include a certification by a principal member of the CONSULTANT's firm that the work has been performed in accordance with the provisions of this Agreement; and 5) For all payments include an estimate of the percentage of work completed. Upon submission of any such invoice, if CITY is satisfied that CONSULTANT is making satisfactory progress toward completion of tasks in accordance with this Agreement, CITY shall promptly approve the invoice, in which event payment shall be made within thirty (30) days of receipt of the invoice by CITY. Such approval shall not be unreasonably withheld. If CITY does not approve an invoice, CITY shall notify CONSULTANT in writing of the reasons for non -approval, within seven (7) calendar days of receipt of the invoice, and the schedule of performance set forth in Exhibit "A" shall be suspended until the 3 & agree/j f/wells/ 10/27/9 S parties agree that past performance by CONSULTANT is in, or has been brought into compliance, or until this Agreement is terminated as provided herein. D. Any billings for extra work or additional services authorized by CITY shall be invoiced separately to CITY. Such invoice shall contain all of the information required above, and, in addition shall list the hours expended and hourly rate charged for such time. Such invoices shall be approved by CITY if the work performed is in accordance -with the extra work or additional services requested; and if CITY is satisfied that the statement of hours. worked and costs incurred is accurate. Such approval shall not be unreasonably withheld. Any dispute between the parties concerning payment of such an invoice shall be treated as separate and apart from the ongoing performance of the remainder of -this Agreement. 8. DISPOSITION OF PLANS, ESTIMATES AND OTHER DOCUMENTS CONSULTANT agrees that all materials prepared hereunder, including all original drawings, designs, reports, both field and office notices, calculations, maps and other documents, shall be turned over to CITY upon termination of this Agreement or upon PROJECT completion, whichever shall occur first. In the event this Agreement is terminated, said materials may be used by CITY in the completion of PROJECT or as it otherwise sees fit. Title to said materials shall pass to CITY upon payment of fees determined to be earned by CONSULTANT to the point of termination or completion of the PROJECT, whichever is applicable. CONSULTANT shall be entitled to retain copies of all data prepared hereunder. 9. HOLD HARMLESS CONSULTANT shall protect, defend, indemnify and hold harmless CITY, its officers, officials, employees and agents from and against any and all liability, loss, damage, expenses, costs (including, without limitation, costs and fees of litigation of every nature) arising out of or in connection with CONSULTANT's negligent performance of this Agreement, or its failure to comply with any of its obligations contained in this Agreement by CONSULTANT, its 4 g: agree/j f/wells/ 10/27/98 officers, agents or employees, except such loss or damage which was caused by the sole negligence or willful misconduct of CITY. 10. WORKERS' COMPENSATION INSURANCE 'Pursuant to California Labor.Code section 1861, CONSULTANT acknowledges awareness of section 3700 et seq. of said Code, which requires every employer to be insured against liability for workers compensation; CONSULTANT covenants -that it will comply.with such provisions prior.to.commencing performance of the work hereunder. CONSULTANT shall maintain workers' compensation insurance in an amount of not less than One Hundred Thousand Dollars ($100,000) bodily injury by accident, each .,occurrence, One Hundred Thousand Dollars ($100,000) bodily injury by disease, each employee, Two Hundred Fifty .Thousand Dollars ($250,000) bodily injury by disease, policy limit. CONSULTANT shall require all subcontractors to provide such workers compensation insurance for all of the subcontractors' employees. CONSULTANT shall furnish to CITY a certificate of waiver of subrogation under the terms of the workers compensation insurance and CONSULTANT shall similarly require all subcontractors to waive subrogation. 11. GENERAL LIABILITY INSURANCE In addition to the workers compensation insurance and CONSULTANT's covenant to indemnify CITY, CONSULTANT shall obtain and furnish to CITY, a policy of general public liability insurance, including motor vehicle coverage covering the PROJECT. Said policy shall indemnify CONSULTANT, its officers, agents and employees, while acting within the scope of their duties, against any and all claims of arising out of or in connection,with the PROJECT, and shall provide coverage in not less than the following amount: combined single limit bodily injury and property damage, including products/completed operations liability and blanket contractual liability, of $1,000,000 per occurrence. If coverage is provided under a form which includes a designated general aggregate limit, the aggregate limit must be no less than $1,000,000. Said policy shall name CITY, its officers, and employees as Additional 5 g:agree/j f/wells/ 10/27/98 0 Insureds, and shall specifically provide that any other insurance coverage which may be applicable to the PROJECT shall be deemed excess coverage and that CONSULTANT' insurance shall be primary. 12. PROFESSIONAL LIABILITY INSURANCE CONSULTANT shall furnish a professional liability insurance policy covering the - - work performed by it hereunder. Said policy shall provide coverage:for CONSULTANT'S professional liability in an amount not less than $1,000,000 per occurrence and in:the aggregate. A claims made policy shall be acceptable if the policy further provides that: 1. The policy retroactive date coincides with or precedes the professional services contractor's start of work (including subsequent policies purchased as renewals or replacements). 2. CONSULTANT will make every effort to maintain similar insurance .during the required'extended period of coverage following project completion,including the requirement of adding all additional insureds. 3. If insurance is terminated for any reason, CONSULTANT agrees to purchase an extended reporting provision of at least two (2) years to report claims arising from work performed in connection with this Agreement. 4. The reporting of circumstances or incidents that might give rise to future claims. 13. CERTIFICATES OF INSURANCE Prior to commencing performance of the work hereunder, CONSULTANT shall furnish to CITY certificates of insurance subject to approval of the City Attorney evidencing the foregoing insurance coverages as required by this Agreement; said certificates shall: a. provide the name and policy number of each carrier and policy; b. shall state that the policy is currently in force; and 6 & agree/j f/wells/ 10/27/98 C. shall promise that such policies shall not be suspended, voided or canceled.by either party, reduced in coverage or in limits except after thirty (30) days prior written notice; however, ten (10) days prior written notice in the event of cancellation for nonpayment of premium. CONSULTANT shall maintain the foregoing insurance coverages in force until the work under this Agreement is fully completed and accepted by CITY. The requirement for carrying the foregoing insurance coverages shall not derogate from the provisions for indemnification of CITY by CONSULTANT under the Agreement. CITY or its representative shall at all times have the right to demand the original or a copy of all said policies of insurance. CONSULTANT shall pay, in a prompt -and timely manner, the premiums on all insurance hereinabove required. 14. INDEPENDENT CONTRACTOR CONSULTANT is, and shall be, acting at all times•in the performance of this ,Agreement as an: independent contractor. CONSULTANT shall secure at its expense,:and be responsible for any and all payment of all taxes, social security, state disability insurance compensation, unemployment compensation and other payroll deductions for CONSULTANT and its officers, agents and employees and all business licenses, if any, in connection with the services to be performed hereunder. 15. THIRD PARTY BENEFICIARIES Nothing contained in this Agreement shall create a contractual relationship with or a cause of action in favor of a third party against either the CITY or the CONSULTANT. The CONSULTANT's services under this Agreement are being performed solely for the CITY's benefit, and no other entity shall have any claim against the CONSULTANT because of this Agreement or the performance or nonperformance of services hereunder. 7 g:agree/j f/wells/ 10/27/98 16. FIDUCIARY RELATIONSHIP Nothing contained in this Agreement or otherwise is intended to create a fiduciary relationship between the parties. 17. TERMINATION OF AGREEMENT All work required hereunder shall be performed in a good and workmanlike manner. CITY may terminate CONSULTANT's services hereunder at any time with or without cause, and whether or not PROJECT is fully complete. Any termination of this Agreement by CITY shall be made in writing, notice of which shall be delivered to CONSULTANT as provided herein. 18. ASSIGNMENT AND SUBCONTRACTING This Agreement is a personal service contract and the supervisory work hereunder shall not be delegated by CONSULTANT to any other person or entity without the written consent of CITY. 19. COPYRIGHTS/PATENTS CITY shall own all rights to any patent or copyright on any work, item or material produced as a result of this Agreement. 20. CITY EMPLOYEES AND OFFICIALS CONSULTANT shall employ no CITY official nor any regular CITY employee in the work performed pursuant to this Agreement. No officer or employee of CITY shall have any financial interest in this Agreement in violation of the applicable provisions of the California Government Code. 21. NOTICES Any notice or special instructions required to be given in writing under this Agreement shall be given either by personal delivery to CONSULTANT's agent (as designated in Section 1 hereinabove) or to CITY's Director of Public Works as the situation shall warrant, or 8 g:agree/j f/wells/10/27/98 by enclosing the same in a sealed envelope, postage prepaid, and depositing the same in the United States Postal Service, addressed as follows: TO CITY: Director of Public Works City of Huntington Beach 2000 Main Street Huntington Beach, CA 92647 22. IMMIGRATION TO CONSULTANT: William Gabris, Project Manager Westin Engineering, Inc. 25i c a jam iucrs Read, Suite 01 100 Park Center Plaza, Suite 500 San Jose, CA 95113 CONSULTANT shall be responsible for full compliance with the immigration and naturalization laws of the United States and shall, in particular, comply with the provisions of the United States Code regarding employment verification. 23. LEGAL SERVICES SUBCONTRACTING PROHIBITED CONSULTANT and CITY agree that CITY is not liable for payment of any subcontractor work involving legal services,,and.that-such legal services are expressly outside the scope of services contemplated hereunder. CONSULTANT understands that pursuant to . Huntington Beach City Charter Section 309, the City Attorney is the exclusive legal counsel for CITY; and CITY shall not be liable for payment of any legal services expenses incurred by CONSULTANT. 24. ATTORNEY'S FEES In the event suit is brought by either party to enforce the terms and provisions of this Agreement or to secure the performance hereof, each party shall bear its own attorney's fees. REST OF PAGE NOT USED 9 g:agree/j f/wells/ 10/27/98 25. ENTIRETY The foregoing, and Exhibit "A" attached hereto, set forth the entire Agreement between the parties. IN WITNESS WHEREOF the parties hereto have caused this Agreement to -be :. executed by and through their authorized offices the day, month and year: first above -written. WESTIN ENGINEERING, INC. By: De%4('J T- 6-.cu'l'Ql/ print name ITS: (circle one) Chairma Presiders ice President AND By: ITS: (circle one) SecretaryChief Financial Officer/Asst. Secretary - reasurer REVIEWED AND APPROVED: CITY OF HUNTINGTON BEACH, A municipal corporation of the State of Califon Mayor ATTEST: 4ofta G City Clerk 1 APPROVED AS TO FORM: Cit Administrator 1� City Attorney (�Oly/q� 1 to(�o�96 INIT ND APPROVED: Oti:I-mil Director of Public Works 617 10 &agree/j f/wells/ 10/27/98 PROFESSIONAL SERVICES CONTRACT BETWEEN THE CITY OF HUNTINGTON BEACH AND WESTIN ENGINEERING, INC. TO PREPARE A SCADA SYSTEM MASTER PLAN FOR UPGRADING CITY'S SYSTEM FOR WATER OPERATIONS (CC-1092)) Table of Contents 1 Work Statement................................................................................................... 1 2 City Staff Assistance............................................................................................ 2 3 Time of Performance........................................................................................... 2 4 Compensation......................................................................................................2 5 Priorities................................................................................................................2 6 Extra Work........................................................................................................... 2 7 Method of Payment.............................................................................................. 3 8 Disposition of Plans, Estimates and Other Documents ........................................ 4 9 Hold Harmless..................................................................................................... 4 10. Workers Compensation Insurance.............................................................5 11. General Liability Insurance.............................................................:..........5 12. Professional Liability Insurance............................................................................6 13 Certificates of Insurance..................................................................................... 6 14 Independent Contractor...................................................................................... 7 15. Third Party Beneficiaries...................................................................................... 7 16. Fiduciary Relationship........................................................................................ 8 17. Termination of Agreement.................................................................................. 8 18 Assignment and Subcontracting......................................................................... 8 19 Copyrights/Patents............................................................................................. 8 20. City Employees and Officials.............................................................................. 8 21. Notices................................................................................................................9 22. Immigration 23. Legal Services Subcontracting Prohibited........................................................... 9 24. Attorney Fees..................................................................................................... 9 25. Entirety.................................................................................................................10 - g: agree/j f/wells/ 10/27/98 EXHIBIT A SCOPE OF SERVICES e�lel7­ A INTRODUCTION The Work Statement defined in this section is the basis for the engineering services to upgrade the City of Huntington Beach's SCADA system and communication network. This Work Statement amends and supersedes Westin's proposal dated July 1998. OBJECTIVES The objectives for the SCADA System upgrade include: • Deliver to the City an upgraded SCADA system that takes advantage of the new technologies delivered by a modern SCADA system. • Employ the most effective communications media. Major considerations are reliability and cost. • Deliver a reliable, easy to use and maintain system, meeting both short and long-term needs. WESTIN APPROACH The upgrade to the water SCADA system is not an exceptionally large one, but has aspects that need to be managed carefully. Westin's Westin has been the SCADA specialist of choice for many major water utilities including • MWD • S. Nevada Water • California DWR • City of Pasadena • Mesa Consolidate experience has show that a teamed approach, where the consultant works closely with plant City of Huntington Beach, SCADA Upgrade staff, during all phases, results in a project that meets or exceeds expectations. Adding Westin's project management and SCADA technical expertise, Automation Services knowledge of the current installation, and the City staffs understanding of the water system and process needs — will create the team with the essential skills to deliver a successful project the utility can showcase to other departments and city visitors. s Project U M 0 a o Progress v aD IVITL11 F E m Review Meetings Participation The project will be executed in three phases: Phase 1 - System Master Plan Phase 2 - Specification and Bidding Documents Phase 3 - Bidding and Construction Services Westin's approach to each of these phases is detailed in the following paragraphs. TASK 1— SCADA SYSTEM MASTER PLAN Introduction Phase 1, the SCADA Master Plan when complete will serve as a roadmap for the Amendment to Proposal Dated July 1998 2-1 SCOPE OF SERVICES development of Phase 2, (specifications and bid documents) and the implementation Phase. It reviews the utilities existing system, and then through a number of workshops, determines the requirements for the new SCADA system. The workshops are one of the most important elements of the work. These "brainstorming" sessions generate the ideas which develop into the requirements specification for the new SCADA system. During the workshops the City's staff is encouraged to look ahead at how they see the utility operating in the next 5 to 10 years. The SCADA system can contribute to the efficient operation of the utility by providing easily accessible information to decision makers (operators and planners for example). The information (not just data!) must be in the form the user needs and must be available where it is needed. This may be at "central", in the field Modern SCADA systems are also important information systems that need to be integrated into a utilities information architecture. (mobile user), or at the home of an "on -call" operator. The plant staff s knowledge of the utility's processing and operational needs, together with Westin's expertise in SCADA and information systems, will allow Westin to determine and document the requirements for the new SCADA system. Jeff Adler of Automation Services is part of the Westin's team and will participate in most of the listed activities. The following paragraphs City of Huntington Beach, SCADA Upgrade describe Westin's approach to each task in detail. Task 1.1— Mobilization Obiectives The mobilization tasks will prepare the Westin and City's team for the project activities. At the end of his task all members will understand the projects objectives, terms of reference, scope and deliverables. The City of Huntington Beach's project manager will be Westin's primary contact. Methodoloizy As a first task Westin will prepare and distribute: • A project workplan • A list of a drawings and information needed from the City. After review of the above information Westin will hold a project kick-off meeting with the City. The agenda will include: Meeting No. 1 • Introduction of team members for Westin and the City • Review and confirm project objectives, scope, and terms of reference • Finalize administrative arrangements • Review project schedule • Set dates for initial workshops • Facility tour and field site visits. Task Output a. Project Work Plan b. Technical Specification Table of Contents c. Workshop schedule d. Meeting minutes. Amendment to Proposal Dated July 1998 2-2 SCOPE OF SERVICES Task 1.2 — Review Current System Ob'ecl tives The Westin team will become familiar with all parts of the existing SCADA system, in preparation for holding the first "requirements" workshop. Methodolozy An initial project database will be created for the SCADA system. This will detail the remote sites, locations, associated instruments and controlled devices, RTU inputs/outputs, RTU power source, existing control strategies and alarms, and lists of drawings..The input/output database will be directly extracted from the BIF RTUs as an electronic file. Meeting No. I To prepare for the first requirements workshop an initial meeting will held with City designated senior staff to list and discuss known future projects, expansions, and modifications that the SCADA will need to accommodate. The following approach will be followed: • Prepare draft project database • Visit "central' and typical remote sites. Compare existing drawings with site conditions and make markups/notes as necessary • Update database as a result of site visits • Prepare a block diagram of the existing system and "system operations" description Meeting N6.2 Meet with senior staff to discuss future expansions, updates and modifications to the water systems. Discuss and document City of Huntington Beach, SCADA Upgrade Task Output Project database • Meeting minutes • System block diagram • System Operations descriptions Task 1.3 — Conduct Requirements Workshops Obiectives Two workshops will be held to define the requirements for the new SCADA system. Methodolo1:y Westin, together with plant staff, will define the requirements and design of the SCADA system based on three factors: 1) The people and organizations who use the system to do their work 2) The functions and processes that are performed 3) The enabling technology. As input to this task, Westin will review any existing City utility strategic plans and other documents relevant to the SCADA system. This will include any existing City emergency planning documents. Workshop No. 1. — People and Organization Westin will conduct a requirements workshop for the major groups of the SCAD System. The workshop environment allows for a free flow of ideas, expands thinking beyond current practice, and introduces the capabilities of new technology. Amendment to Proposal Dated July 1998 2-3 SCOPE OF SERVICES At the completion of the workshop, Westin will: • Understand existing job assignments • Have determined current, desired, and future interaction with the new SCADA system • Obtained input into the Requirements Matrix. Workshop no. 2 — Processes and Technology This workshop will determine the required processes and performance of the Water SCADA System. These requirements will be understood by considering basic SCADA Only easily accessible data is valuable functions, and water applications. The SCADA software configuration requirements will be discussed. The "basic" SCADA functions consist of: • Data acquisition and processing • Real-time and historical data bases • Control functions • Operator interface functions. The "water applications" are system wide functions performed by the host system. Typically these include: • Weather Data • Dispatching, monitoring, and control • Long term historical data • Load management • Reservoir balancing • Reservoir turnover • Water quality • Pressure zones • Emergency management City of Huntington Beach, SCADA Upgrade • Planning data • Control strategy definition • Integrated Information system. The remote terminal units typically perform the following water applications: • Reservoir Level Control • Flow Totalization • PID Control • Alarms The SCADA "technology" and support requirements are important. They can determine the reliability, useful life of the SCADA system, and its ability to work with other (current and future) utility software applications. Issues that will be discussed include: • Open architecture • Hardware and software standards • Interface requirements • Redundancy • Vendor products — standard/customized • Proven technology (software/hardware) • Ease of use • Owner maintainability • Vendor support • Cut-over/transition considerations Summarizing the workshops Typically many ideas are generated during the course of brainstorming session. These need to be classified and evaluated in terms of their benefit to the City. To assist with this, the ideas will be rated by plant staff as "essential", "high priority", "medium usefulness"(nice to have), and "low priority" (useful if available at appropriate cost). Amendment to Proposal Dated July 1998 2-4 SCOPE OF SERVICES Westin will further evaluate these using the following criteria: • Availability from major system suppliers • Impact on system hardware configuration • Major performance parameters (e.g., response time, CPU utilization, etc.) • Estimated implementation cost (low/medium/high) • Maintenance costs • Required training. Task Output a. Agenda packages for two workshops. b. Requirements summary Technical Memorandum. Task 1.4 — Identify Alternatives and Candidates Obiectives This task will identify the. alternatives that meet the Cities requirements. This will be determined for: a. The communications media (between the central and 44 remote sites). b. The central host hardware and software. c. The remote terminal units (RTUs). An initial evaluation of the options will select the most likely candidates. These will undergo a more detailed analysis in Task 1.5. Methodolozy Communications option. Westin will consider the communications options to the 44 existing and any new planned remote sites. The evaluation will include: City of Huntington Beach, SCADA Upgrade • Radio — MAS, and spread spectrum • Telephone — leased lines, dial -up, centrix and cellular • Microwave • Cable TV • Fiber optics • Satellite Multiple options exist for some media, such as radio. Westin will prepare a Technical Memorandum listing the pros and cons of each approach, the availability in the city service area, and the order of probable cost. Host and RTUHardware/software options. Westin will evaluate the different types of hardware/software options available and how well they meet the City's requirements. The results will be summarized in a Technical Memorandum. Host software currently popular for water utilities include: "The Fix" from Intellution, "In Touch" from Wonderware, "Factory Link" from US Data, and "Look Out" from Westin's telecommunication expertise is provided by a group of ten Westin communications engineers dedicated to SCADA and network systems. Their experience will ensure that the most appropriate media is recommended to the City. National. Westin staff have worked with, and had hands on experience with many software packages, but have no preferences. Amendment to Proposal Dated July 1998 2-5 SCOPE OF SERVICES Workshop No. 3 —Alternatives Evaluation. A half day workshop will be held with Westin will hold a half day workshop with utility staff, to review the findings of the the City to review the results of Task 1.4 and analyses. Staff comments will be noted and agree on the most likely candidates for detailed any additional analysis needed, completed. analysis. The results of this workshop will be basis for preparing the Final Master Plan document. Task Output Task Output • Technical Memorandum indicating the communications and hardware/software a. Technical Memorandum with alternatives and summary of the pros analysis of most likely. candidate and cons technologies, and recommendations • Workshop No. 3 summary. for the new SCADA system, estimated costs, and operational description. Task 1.5 — Analyze Most Likely Candidates b. Workshop 4 agenda. and Make Recommendations c. Workshop results summary. Obiectives Task 1.6 — Prepare and Present Master This task analyses the most likely Plan Report communications and hardware/software candidate technologies, selected in Task 1.4. Obiectives SCADA recommendations based on the analysis will be provided. Complete and present final SCADA Master Plan Report. Methodolo zy Methodolot:y The likely candidate technologies will be analyzed and compared based on the following Westin will take the results of all Task 1 criteria: workshops and complete a final Master Plan Report. Six copies will be delivered to the • How well they meet the City's current City. and future needs • Estimated initial cost Workshop No. 5 • Estimated maintenance and training costs . The Master Plan will be presented to the • Operational cost. City at this workshop. A network diagram, operational description, and Task Output outline for possible phasing of the implementation will be prepared for the Six copies of the SCADA Master Plan recommended system. Report. Workshop No. 4. City of Huntington Beach, SCADA Upgrade Amendment to Proposal Dated July 1998 2-6 SCOPE OF SERVICES Task 1 Constraints and Assumptions To estimate the level of effort required for this task the following assumptions were made: a. b. C. d. Plans for the remote sites, showing major dimensions, are available from the City. Schematics for the existing RTUs are available. It is assumed that updating of these to show actual conditions is a minor task. The existing RTUs will be replaced "in kind", with the new RTU modules installed in the existing RTU cabinets. RTU installation can be done from connection lists and detailed installation drawings will not be required. That workshop dates agreed on, can be maintained. Changes may adversely affect schedule. No allowance has been made for Westin to complete radio frequency searches or radio path studies. These are significant tasks that will be necessary if a radio communications alternative is selected. Westin routinely provides both these services (see work sample in the Appendix) to clients. Should they be necessary for the City, Westin can negotiate to add the necessary additional hours . TASK 2 — SPECIFICATIONS AND BIDDING DOCUMENTS Introduction Phase 2, "Specifications and Bidding Documents", completes the new SCADA system design, based on the Master Plan document developed in Phase 1. It generates bid documents by combining the technical specification with City's front-end documents. City of Huntington Beach, SCADA Upgrade The tasks detailed in the following paragraphs indicate Westin's approach to completing this Phase. Task 2.1— Prepare 80% specification docu: - Methodolo�y Westin will prepare 80% design documents for review by the City, and lead an 80% design review workshop. The specifications will cover the work required by the Contractor to supply, configure, install and test the new SCADA system. The specifications will include requirements for the following : • SCADA system performance > system over -view > definitions > performance > block diagrams • System Functions > computation features > communications > control and monitoring > alarms > RTU control strategies > redundancy • System Software Configuration > redundancy > system database > historical database > historical data display > operator interface requirements, including alarm summaries, trends, menus, process displays, navigation, diagnostic displays > reports • Communications > Communications media > RTUs > remote access Amendment to Proposal Dated July 1998 2-7 SCOPE OF SERVICES > open standards > communications with other utility software applications • Host system hardware • RTU hardware • Equipment installation • Testing • Documentation and training • Project organization > schedule > project manager > monthly reports > correspondence > submittals > responsibilities Task Output 80% Specification Task 2.2 — Prepare Database for the New SCADA System Methodolo�y The database developed in Phase 1 of the project will be updated, to reflect the requirements of the new SCADA. Many of the tables required for the specifications are generated directly from this database. These include: • List of remote sites and locations • Instrument List, with range and alarms • Equipment • RTU I/O list • Control strategies • List of required Operator graphics Task Output Tables required for the 80% specifications City of Huntington Beach, SCADA Upgrade TASK 2.3 - 80% Submittal Drawings Methodolot?y Westin will prepare a set of drawings to include with the bid documents. The drawings will include: • Cover sheet • Legend sheet • Project location plan • SCADA system block diagram • RTU connection lists • RTU typical layout • Example displays (2) Westin understands that it is the City's intention to replace the existing RTUs and no (significant) additional instrumentation is required. For cost savings, our approach is based on installing the new RTUs in the existing RTU cabinets. Because of this simplified approach, Westin will not prepare detailed RTU site and installation drawings, but will provide connection lists for the new RTUs. However, in order for the bidders to develop a complete understanding of the new SCADA system and RTUs, we will prepare sketches for the following typical sites: 1. Well 2. Reservoir 3. Flood Control 4. West Orange County Water Board. Task Output The 80 % submittal drawings Amendment to Proposal Dated July 1998 2-8 SCOPE OF SERVICES TASK 2.4 — 80% Submittal Review TASK 3 — BIDDING AND Workshop CONSTRUCTION SUPPORT SERVICES Methodology Introduction A workshop will be held with the City to review the 80% submittal. Comments will be Phase 3, provides the City with bidding and incorporated into the Final documents. construction support services. Westin will Task Output support the City during these critical phases and assist in making sure new SCADA Workshop summary system is built, installed, tested and documented as required by the specifications. TASK 2.5 - Prepare 100% Bid Documents This task brings the 80% specifications and TASK 3.1— Bid Services drawings to the 100% level. Work required as a The following bid services, and level of result of the comments from the 80% review effort have been allowed for: workshop is included. Methodology a) Answering questions from bidders. (Up to 6 hours) Complete drawings and specifications to the b) Conduct pre -bid conference and 100% level. facility tour. ( 8 hours) c) Assist City evaluate bids. Includes Task Output preparing bid evaluation criteria. (Up to 34 hours) Final bid documents d) Make recommendation to the City. (Up to 4 hours) TASK 2.6 - Estimate of Probable TASK 3.2 - Construction Services Construction Cost The following construction services, and Methodology level of effort have been allowed for: Westin will estimate the probable construction a) Answer Contractor's requests forclarification. cost and present the results in an Microsoft (Up to 24 hours) Excel spreadsheet. The project database will be b) Review submittals. (Up to 24 hours). used to assist with the estimate. � c) Field inspections and reports. (Up to 40 hours.) Task Output d) Review requests for change -orders. (Up to 24 hours.) Probable Construction Cost estimate e) Assist City with Factory testing. (Up to 32 hours) f) Assist City during final inspection. (Up to 16 hours). City of Huntington Beach, SCADA Upgrade Amendment to Proposal Dated July 1998 2-9 SCOPE OF SERVICES TASK 3.3 - Record Drawings and O&M Manuals. Our proposal is based on including in the specification the requirement that the Contractor generate the "as -built" RTU site drawings. Westin will review contractor's as-builts. (Up to 60 hours effort). City of Huntington Beach, SCADA Upgrade Amendment to Proposal Dated July 1998 2-10 PROFESSIONAL FEE SUMMARY OF FEE Westin's Professional Fee for the City of Huntington Beach's Water SCADA System upgrade, is as follows: Phase 1, Master Plan $ 50,311 Phase 2, Bid Documents $ 40,803 Phase 3, Construction and Bid Services $ 34,561 TOTAL 125,675 For each Phase, payments shall be monthly based on the percentage completion of the effort expended on the Tasks on the Cost Spreadsheets. City of Huntington Beach, SCADA Upgrade Amendment to Proposal Dated July 1998 ' ,P ;City of=Hur>tin§" Beach SC ' A Upgrade Client: City of Huntington Beach Project Water SCADA Upgrade / Replacement 98 -127 Project Phase: Phase I Fee Type: Fixed/ Not to exceed 4/9/98 Task Task Name s �; ." .:3. , ...��€ Staff:an Rate Schedu a „ g i. No. of No. of Other direct Task Task Task No. Trips @ Days g Subtotal Cont Total ° costs J ".. Quality SCADA Comminic CAD Pmj Mgr Control ENGR Engr Terhn Proj Admin Admin Asst Clerk 220 145 Incl. ODc Markup §. 125 125 85 105 60 71 65 40 - . ' 0% 0 0 PHASE 1 SCADA SYSTEM MASTER PLAN 0 0 Task 1.1 Mobilisation 0 0 a. Generate project plan, billing requirements 8 1,000 1.000 b. Conclude subcontract with Automation Services 4 500 500 c. Internal meeting with AS 0 0 0 0 d. Orientation meeting with City and minutes 4 0 500 500 0 0 Task Outputs 0 0 > Project Plan 0 0 > Meeting minutes 0 0 > Subcontract agreement 0 0 0 0 Task 1.2 Review Current System 0 0 a. Obtain & review existing documentation in detail 8 8 1,680 1,680 b. Prepare database of remotes sites, detailing all 16 1,360 1.360 instruments, ranges, alarm limits, 1/0 points to be 0 0 monitored or controlled. Include control strategys 0 0 c. Visit central. Discuss current operations approach 4 4 840 840 with City staff. 0 0 d. Visit typical remote sites, and validate connection lists. 40 1 5 200 4,545 4,545 Check accuracy / markup drawings that are 0 0 available. 0 0 e. Obtain from City staff listing of know expansions 8 1,000 1,000 upgrades and additions needed at the remote 0 0 sites. Document 0 0 f. Prepare updated block diagram showing central, 8 4 16 2,300 2,300 all remotes and communications media 0 0 g. Prepare "System Operations" descriptions 8 4 1,340 1,340 0 0 Task Outputs 0 0 > Updated SCADA database 0 0 > System Block Diagram 0 0 revcost.xls, Phase 1 WBS PHASE 1 - Pagel 10/13/98 Task Task Name v ' Staff 'ate Schedule No. of No. of Other dire« Task Task Task No. an., Trips Days Subtotal Cont Total ' � . � � .., T.:-. � costs ... ,:., IN& "�: �' •� ::..; :_ _ -""';.;,_:•ProjMgr Quality SCADA Comminic CAD Control ENGR Engr Techn ProjAdmin AdminAsst Clerk 220 145 Incl. oDC Markup ,Fa; " 0% i:y:"' 125 125 85 105 60 71 65 40 :"� > "System Operations descriptions" 0 0 0 0 Task 1.3 IConduct a Requirements Workshop 0 0 a. Prepare an agenda and "information package" for 16 4 2,340 2,340 the meeting. Distribute to attendees prior to 0 0 workshop 0 0 b. Conduct two, one -day meeting with Operations, 16 16 1 2 3.870 3,870 Maintenance and Management to brainstorm and 0 0 agree on SCADA requirements 0 0 c. Prepare Tech Memo summarizing City's 16 0 2,000 2,000 requirements 0 0 Task Outputs 0 0 > Agenda and information package 0 0 > Requirements Technical Memorandum 0 0 0 0 Task 1.4 Identity Alternative Approaches & Evaluate 0 0 a. Based on determined SCADA requirements and 0 0 existing SCADA, identify aftematives which will 0 0 meet the City's needs. 0 0 > RTU/ HMI options 16 2,000 2,000 > Communications media 40 1 3 200 5,055 5,055 b. Evaluate aftematives and prepare draft Tech 24 2 3,250 3,250 Memo for review by the City 0 0 c. Hold a half day workshop with City staff to discuss 8 8 1 1 2,205 2,205 the alternatives and initial evaluation. Identify the 0 0 candidate approaches for detailed analysis. 0 0 Task Outputs 0 0 > Draft AftemativesTechnical Memorandum 0 0 > Workshop Summary 0 0 0 0 Task 1.5 Analyse candidate Systems, Make 0 0 Recommendations and Brief City 0 0 a. Analyse - 0 0 > Pros and cons 16 2,000 2,000 > Probable cost for purchase and installation 8 1,000 1,000 > Requirements for operation and maintenance 8 1,000 1,000 b. Write-up recommendations 16 2 2,250 2,250 c. Brief City on recommendations and analysis. 4 Soo 500 0 0 Task Outputs 0 0 revcost.xls, Phase 1 WBS PHASE 1 - Page 2 10/13198 Task ,, ,,;. Other Task Name Staff..and` Rate Schedule, ; , No. of No. of direct Task Task Task No. .x• i • „;;<.. , ."-�p Trips Days Costs Subtotal Cont Total r < .. _ + .;9'n_,; - - Quality tySCADA Comminic CAD" Proj Mgr Control ENGR Engr Tetlm Proj Atlmin Admin Asst Clerk 220 145 Incl. ODC Markup '--.�:.. `�,a, t - .. .,_, :.�:. .,.:..s:<:... .-." .. ...., :: ,-...:.:; .,;.: w. :.",:: ..fey: ::•.,:a• A .rA: 125 125 85 105 60 71 65 40:a > Recomendations Tech Memo 0 0 0 0 0 0 Task 1.6 Prepare and Present Master Plan Report 0 0 a. Prepare final Masterplan 30 2 4.000 4,000 Task Outputs 0 0 Deliver six copies of the Master Plan to the City 0 0 Task 1.7 Project Management a. Monthly progress report 1b. Monthly billing 8 8 16 Labor & ODC 1 246 1 6 1 96 1 48 1 16 16 1 0 Subtotal$ 30.750 750 8,160 5,040 960 1.136 0 Labor Hour Total 444 Hours Labor Subtotal (1) The spreadsheet automatically adds to the Task Subtotal the Markup to Air/Ground Travel, Cost per Diem and Telephone Cost. (2) The spreadsheet automatically adds to the Task Total the Contingency. Approved By: Project Manager 16 16 4 1 11 640 880 1,595 41 47,436 ODC Subtotal 2,875 Regional Sales Manager 1,0001 I 1.000 2,776 2.776 Total $ 50,311.00 1 revcost.xls, Phase 1 WBS PHASE 1 - Page 3 10/13/98 . r s pp .:. :-• . "�\ 'X..&„u".r«bv..a'*.,, i,..- sw, d R ... :. f- utrttngton Beach SCADA U rade '° e `-::»a °`�aa '.�'?. .`^.°"iaSai, .a.y. _ Client: City of Huntington Beach Project: Water SCADA Upgrade / Replacement Proposal 98-127 Project Phase: Phase 2 Fee Type: Fixed/ Not to exceed Date 4/9/98 Task j +fix. Other Task Name y Staff and Rate Seheduli No. of No. of direct Task Task Task No. ' .'rgX xx Trips Days costs Subtotal Cont Total : `CAD.,, ;e ..,�r .. ....... ...... .. 3. %^ w..o:. omms� Proj Mgr Control ENGR Engr Techn Staff Eng Proj Admin Gerk 125 125 85 105 60 105 71 40 220 145 Incl. oDC Markup .. .. -� ,„. 0 PHASE 2 Specifications & Bidding Documents Task 2.1 Prepare Design specifications Prepare 80% submittal 120 4 Task Outputs 80% submittal Task 2.2 Prepare Final Database a. Update database developed during Phase 1 Task Outputs Final database Task 2.3 Prepare Drawings Drawing List Sheets 1 Cover sheet 1 2 Legend sheet 1 3 Project location plan 1 2 4 SCADA system block diagram 1 5 Central - plan and electrical schematic 1 4 6 Remote site sketches (4 typical) 4 7 RTU panel - typical aramgement and mounting 1 8 Typical graphic over -view screen 8 9 Typical pump station graphic screen 8 Task Outputs Typical Site Sketches (4) RTU Connection Lists Develop data to be displayed on the operator screens a. Obtain copies of all current graphic screens and review 4 b. Half day meeting. Meet with plant operations to 8 discuss display needs, standard symbols, color conventions, screen navigation, menus, 8 8 4 20 8 0 0 2 4 4 6 8 40 8 15.500 0 0 F 1,660 1.6 5,110 5.1 1,160 1,1 1,000 1,0 1.000 1.0 500 1,000 1 0 0 —. .K Ph.-2wes PHASE 2 - page 1 10/13/98 Task Task Name No. '�' W"4 an reports, and trends Task 2.4 80% Submittal Review Workshop 80% review meeting with the City Task 2.5 100% Bid Documents a. Add to design specifications b. Prepare final specifications c. Check specifications compatible with general provisions. Correct if necessary Task Outputs Integrated bid documents Task 2.6 Prepare Estimate of Construction Costs Prepare estimate Task Outpuls Estimate Task 2.6 Project Management a. Monthly progress reports b. Billings c. Bi-weekly progress meetings with the City Offer " No. of No. of Task Task Task . SQtaff andRate Schedule Trips Days direct Subtotal Cont Total .. ..< _ •,.'rs costs Quality SCADA mms��....AD Incl. ooc ...• . . Proj Mgr Control ENGR Engr Techn StaftEng ProjAdmin Clerk 220 145 " Markup`::,`;.:a..:` ys,: e 125 125 85 105 60 105 71 40 0% - 8 4 1 20 4 8 8 2 4 8 24 4 4 Labor 8, ODC 234 1 15 1 48 1 0 1 72 0 1 8 1 0 1 1 2 Subtotal$ 29,250 1,875 4,080 0 4,320 0 568 0 220 Labor Hour Total 377 Hours Labor Subtotal 40,093 ODCSubtot (1) The spreadsheet automatically adds to the Task Subtotal the Markup to Air/Ground Travel, Cost per Diem and Telephone Cost. (2) The spreadsheet automatically adds to the Task Total the Contingency. 200 1 1 200 710 1,000 1.590 0 0 0 0 1,284 Total $ 1.2001 1.0001 1.5901 1.2841 Approved By: Project Manager Regional Sales Manager —tx1., Phaw 2wes PHASE 2 - page 2 10/13198 Project• City of Huntington Beach SCADA Upgrade :, a• �,�.�� ,�. _.�. .� Client: City of Huntington beach Project: Water SCADA Upgrade / Replacement Proposal 98-127 Project Phase: Phase 3 Fee Type: Fixed/ Not to exceed Date 4/9/98 ,. -''::• s _ ��-• - Other Task Task Name MOH Staff and Rate�Schetlule No. of No. of direct Task Task Task No. _ •. Trips @ Days costs Subtotal Cont. Total ... .., ,' ...,a�A3 ;yy :' •iyi y�,. • I afr:;,'•- t•:•cv ,*w+.+ ,gar .w: ,r rrsr •�F •:r^ y a� • - Quality SCADA Comms Stall Pmj Mgr Control ENGR Engr Engr CAD Terh Pmj Admin Clerk 220 145 IncL ODC Markup •-p..: 125 125 85 104 104 60 71 40 10% � 0 0 PHASE 3 Bidding & Installation Technical 0 0 Supporft Services 0 0 0 0 Task 3.1 PrebidBid Services 0 0 a. Conduct Pre -bid conference and tour of facility 8 1,000 1,000 b. Answer bidders questions 6 750 750 c. Assist City evaluate bids. Prepare evaluation 24 8 2 3.888 3,888 criteria document. 0 0 d. Make recommendation to City for contract 4 500 500 award 0 0 0 0 Task 3.2 Construction Services 0 0 a. Answer contractors requests for clarification 0 0 > allow up to 24 mhrs 16 4 4 2.756 2.756 b. Review submittals 0 0 > allow up to 24 mhrs 24 3,000 3,000 c. Field inspection and reports 0 0 > allow for 8 site visits and prpare 8 reports 40 2 2 200 6,023 6,023 d. Review requests for change -orders and make 0 0 recommendation to city 0 0 > allow for up to 24 mhrs 24 3,000 3.000 e. Assist City during Factory Test 0 0 > allow for up to 32 mhrs testing and 1 report 32 4,000 4.000 f. Assist City during final Inspection/ acceptance 0 0 > allow for 16 mhrs for final inspection, and 16 2.000 2.000 preparation of one report. 0 0 0 0 Task 3.3 Record Drawings & Operations and Maintenance 0 0 Manual 0 0 a. Prepare record drawings of constructed facilities 0 0 > Obtain redlined drawings from contractor 0 0 showing all field modifications Sheets 0 0 > Revierw update RTU connection diagrams 44 8 8 2 4 2,282 2,282 > Review update remote site plan drawings and 44 8 8 1,160 1,160 schematics 0 0 ..* Ph— 3VMS PHASE 3 - page 1 10n3/98 Task Task Name Staff antl Rate Schetlule No. of No. of diirrecct Task Task Task No. Trips @ Days 0 Subtotal Cont. Total costs R.— •� r �II Duality SCADA Comms Staff Proj Mgr Control ENGR Engr Engr CAD Tech Proj Admin Clerk 220 145 Ind. ODC Markup 125 125 85 104 104 60 71 40 . V 10% > Update system block diagram 1 2 4 410 410 > Update central host system plan and 1 2 4 410 410 schematic 0 0 0 0 b. Assemble the Operations and Manintenance 16 1,360 1,360 Manual for the components, from material 0 0 provided by the Contractor.0 0 Task 3.4 Project management 0 0 a. Attend up to four site construction meetings 16 2,000 2.000 b. Billings 20 22 22 0 0 Labor & ODC 210 1 0 48 6 0 24 0 0 4 Subtotal$ 26,250 0 4,080 624 0 1,440 0 0 880 870 220 1— Laor bHour Total 288 Hours Labor Subtotal 32,394 ODC Subtotal 2,167 Project Total $ 34,561.00 $ 34.561.00 (1) The spreadsheet automatically adds to the Task Subtotal the Markup to Air/Ground Travel, Cost per Diem and Telephone Cast. (2) The spreadsheet automatically adds to the Task Total the Contingency. Approved By: Project Manager Regional Sales Manager m ..n, Ph —awes' PHASE 3 - page 2 10/13/98 ATTACHMENT 2 -71LI 3744673 C/1 9 9 ;4I mega DATE (MN/W!W) i. ■10 11n� ■.� iYn: ' L i....; ...._ ... .... .r r :_.. 'r'r".'...r • .4..i}:::Yi'i3i.�.1_ THIS Ck:RIIVK;A]E. IS mauLD AS A MAT CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE Oc a I ey Renton & AS S oc i a tes ////(p�g P DOES NOT AMEND, EXTEND OR ALTER THE CO VERAGE AFFORDED BY THE , P.O. Box 12675 7_«O POLICIES BELOW, Oak I and, CA 94604-2675 WL— (0DO.1 D COMPANIES AFFORDING COVERAGE Barrow C rp 1? Le�L. vlidLr 610-455-3D90 510-5-�rEp� A F/Le- Hartford Fire Insu ante Co. CoAPANY B WSURED LEILER -Hartford Casualty Ins. Co. -_ Westin Engineering, Inc. COWANY C 100 Park Center Plaza Sta 500 LEILER Firaman's Fund �Insurance Co. San Jose, CA 95113 CowANY D LEITER The A„IMerican Auto InCompany CO►PANY LEILER E SocuCltX Ins. Co. of Hartford .CQ:YEHAQES:....;::r' , ' '''-: t • ;; . � . ' ,.r:;_ =.,.• J. ';t�.. t ;:±; r.:.,..> ...:. ..r_r' rHSISTOCERTIFY THAT THEPOLI05S OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO 1HEiNSUAW NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTwITHST ANOING ANY REOUIREMENT, TERM ORCONOITEON OF ANY CONTRACT OROTHER DOCUMENT WITHRESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORCE.O BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LMITS SHOWNMAY HAVE BEEN REDUCED BY PAID CLAus. CO lT TYPEOFINSURANCE POLVVNUMBER POLIMVP"OTNE POLICY EXPI14010h LIMITS OATE(NNi00rYV) oATE(Mw1=YY) GENERAL LIAe11ITY GENERAL AGGREGATE = 2 _ 0 0 0.0 0 0 . A COMWRC1AL GENlAAL LIAOILIN 57CESSS9402 3/31/90 3/31/99 X PRODUCTS-CWP/OPAGG. t 2. 000.000 PERSONAL & ACV. INJURY t 1 OOD 000 CLAIMS MADE a OCCUR. X IIACN OCCURRENCE = t 000 ODD OWNfR'S & CONTRACTOR-S PROT. X FIRE DAMAGE EA one6(d f _ ContfaetualLiab Mfb. IXPENSE [Any one pettoft ti AUTOMOOILE LIABILITY COMBINED SINGLE B ANY AUTO 57UENGGZ704 3/31/98 3/31/99 LLulr 1 000 000 X B001LY INJURY lPc1 person) t ALI OWNEO AUTOS t;=Yt•:.iL,"..�IJ :�'. � SCH(OULEO AUTOS BODILY INJURY t IIIA(p AUTOS GA-r NON-OwH(0 AUTOS " CITY Li"i: __'T IPer AGcidenU pX PRCPIRTY DAMAGE GARAGE LIABILITY 3y : EXCESSLIAWLTTY EACH OCCURRENCE t 1 000 O00 AGGREGATE 1 000 000 C X UMBRELLA IORN XSC0008 51 3/31/98 3/31/99 OINFA THAN LjMBAfLLA FORM WORKER'S COMPENSATION X_ STATUTORY LIMITS EACH ACCIOINI = 1 000 000 0 WP80777248 7/01/98 7/01/g9 OISEASF-POLICY IIM1F ! 0 0 000 AND WA&NV STOP GAP OISEASE-EACH EMPLOYEE t 000,000 EMPIOVEAs'IIABILRY OTHER E PROFESSIONAL PL700832 3/31/90 3/31/99 S2,000,000/claim LIABILITY — & aggregate, DESCRIPTION Or OPERATIONSILOCATIONSIYEHIM9315PEDJAL ITEMS RE: SCADA project. City of Huntington Beach Its officers & omplOyees are additional insured to genora) & auto liability, coverage Is primary. r ,,.: ,..... :..,........:: .:.. . ..... ..... ..:-:.: .........:.:'.. .:.: .: ...:: :.: cEI:r1�Ic�tr�•Ho o Y cArlcsL,u� 51­101J ANY CF THE ABOVE DESCRIBED POLICIES SE CANCELLED 6EFORE THE .I) EXPIRATION DATE THEREOF. THE ISSUING COMPANY WILL E48E'14VeR-48 ;. MAIL DAYSWRITTENNOTICE TOT HECERT:FICAtEHOLDERNAMEDTOTHE 30 City of Huntington Beach x L Dept. of Public Works/Ens. Div Attn: Gar P. OysAr-t y AUTMORCM REPRESENTATIVE 2000 Main Street 532000 S `• Huntington Beach, CA 92648 .G=�� ...: ,.. ACORt125-S.:7.9 10 'd 'Old XVJ WV 85 : 80 I Nd H-9Z-M ATTACHMENT 3 CITY OF HUNTfNGTON BEACH APPLICATION FOR INSURANCE REQUIREMENTS WAIVER OR MODIFICATION 1. Name/Title/Department of Requesting Staff MemberI' "ZO 15e &,6i.14 /-q4.�/� c Gf4rr6f-e.z%• 2. Date of Request 2Ft;o 3. Name of Contractor/Permittee ,` t rll 4�i,j 4. Description of work to be performed �`ngiric�vrt� fir✓/ceJ �o a.-c a. S�[�q &r�,F� /✓l�t�e✓ f rh and ,D•vYI,/L t1.r-,i i+Vc..a.. u�yr��i,e�q C Csi�js 5. Length of Contract .4O,oroyl.�+'� /yt.�, Irzi,,,�X 6. Type of Insurance Waiver or Modification Requested: Al oe llC.A, -4, (a) Limits: (b) Coverage 7. Reason for Request for Waiver or Reduction of Limits 1n1�•-rae e _ �o�.�rva�,��t tui//nod G•��ra I/e. e1- 8. Id-enttif`y the risks to the City if this request for waiver or modifications granted %X 06,Q me.., a lrwt� Department Head Signature 04W (Thu section to be completed by the Risk Manager) Recommendation: Approve Deny Risk Manager's Signature/Date (Thu section to be completed by the City Attorne)) Recommendation: Approve Deny City Attorney's Signature/Date Settlement Committee appro Jle�to% ] required for this waiver. If Settlement Committee approval is required, submit form to City Attorneysplaced on the agenda. Recommendation: Approve c Deny City Council approv [is] is ot] required for this waiver. 1f City Council a oN 1 is required, attach this form to the RCA after considerate the ttlement Committee. This insurance waive [is] s not] on City Council agenda. jmp/k/resouGonrnsreq/9/11 /97 7 ATTACHMENT 4 Westin Engineering, Inc C _ 2512 Chambers Road, Suite 201 Tustin, California 92780 (714) 838-3620 Fax (714) 838-0853 23 July 1998 Engineering Division Department of Public Works City of Huntington Beach City Hall 2000 Main Street Huntington Beach, California 92648 Subject: Request for Proposal for Professional Consulting Services for Water Operations SCADA System Attn: Mr. Gary P. Dysart Dear Mr. Dysart, Westin Engineering is excited about the: opportunity to submit a proposal for the City of Huntington Beach's Water Operations SCADA System Project. We have assembled a project team that combines Westin's expertise in Project Management, PC,based SCADA Systems, and telecommunications with Mr. Jeff Adler's experience in PC based SCADA systems and his knowledge of the City's facilities and operations. The City will be able to draw upon the project team's experience with both large and small Water SCADA projects to ensure a successful project, completed on time and within budget. With Westin's local office in Southern California, we are able to have frequent project meetings and provide prompt response to the project needs. Our proposal has been prepared to be 100016responsive to the City's requirements as stated in the Request for Proposal. As requested by the City, we have included our Professional Fee in a separate sealed envelope. Attachments Regards, William Gabris Principal Engineer An Employee Owned Company Offices Worldwide \ Westin Engineering, Inc. 2512 Chambers Road Suite 201 Tustin, California 92780 PHONE (714) 838-3620 FAX (714) 838-0853 TECHNICAL PROPOSAL FOR CITY OF HUNTINGTON BEACH FOR ENGINEERING SERVICES FOR THE UPGRADING OF WATER OPERATIONS SCADA SYSTEM July 22, 1998 WESTIN ENGINEERING, INC. PROPOSAL NO. 98-127 This document is confidential between the City of Huntington Beach and Westin Engineering, Inc. for the unrestricted internal use by the City in selecting a specialized consulting and engineering firm. Approved by: William Gabris Director Southern California Operations ME: M:\PROPOSAL\HuntgBch\ProposalU-ID_Sign.doc ;NTS INTRODUCTION . PAGE SECTION 1. Executive Summary.....................................1-1 SECTION 2. Scope of Services...........................................2-1 SECTION 3. Statement of Qualifications .........................3-1 SECTION 4. Project Team..................................................4-1 SECTION 5. Project Schedule...........................................5-1 Insurance Certificate Contract comments APPENDIX Additional Material.......................................6-1 07122198 EXECUTIVE SUMMARY INTRODUCTION The City of Huntington Beach Water Operations Division, is commencing a project to upgrade its existing Water SCADA System. This project will enable the City to take advantage of current technology, improve maintainability and ensure that the most appropriate telecommunication media is employed. The Engineering consultant will perform the work in three phases: • Phase 1 - Preparation of a SCADA master plan • Phase 2 - Design and preparation of bid documents • Phase 3 - Bidding and Construction Services Westin has taken a "teamed" approach to this project. This will allow the City water staff to participate in the planning and design process, along with Westin's design engineers and technical specialists. During Phase 1, Westin has successfully (the Master Plan), this will completed over 400 Water Utility automation projects. This experience will ensure that the Water SCADA Project is completed to the City's satisfaction. be achieved through a series of "requirements" workshops. Westin and the City's staff will get together and "brainstorm" ideas. The results will guide Westin during the planning stage. During the design phase City staff will have an opportunity to review draft documents and discuss them with Westin designers at "review" meetings. The benefits to the City include: • A completed project which fully meets the water utility's needs. • A cost-effective, reliable SCADA system • Minimum disruption to the water system during installation, testing and cut over. City of Huntington Beach, SCADA Upgrade • SCADA able to be integrated with future utility software applications. • City staff familiar with the system at the time it is taken over from the contractor. The modern SCADA system is no longer a stand-alone application. It is capable of being integrated with other utility applications such as planned maintenance, laboratory information systems, engineering drawings, on-line O&M manuals etc., to provide utility users with easily accessible, current and relevant information. Although these other applications may not currently be in place, the SCADA needs to be designed to be compatible and easily integrated when they are introduced. WESTIN'S PROJECT TEAM The selection of the engineer and the methodology to achieve the City's .goals are critical to the project's success. A project team is needed with the following experience: • Project Management • PC Based SCADA • Telecommunications • Local SCADA Vendors. Westin specializes in instrumentation, control, and information systems for the water utility industries. Westin's project team consists of experienced senior personnel in each of the required technical areas. Each project team member specializes in, and is recognized as a leader in, one or more of the required skills for the SCADA System project. Mr William Gabris, the Director of Westin Engineering's Southern California Operations, will be the Project Manager. In 1-1 EXECUTIVE SUMMARY this role he will ensure that the City's project receives the attention of Westin's management, and that the engineering resources needed, are applied to the project. Mr. Russ Collins, the Telecommunications Manager for Westin, will be responsible for the communications analysis, design, and specifications. He has over 20 years experience in telecommunications management. Mr. Alan Carrie, a Principal Engineer with Westin Engineering, will be the alternate Project Manager and responsible for Quality Control (QC). He has over 25 years of experience in the fields of instrumentation, automation, and information systems, for both industrial and municipal clients Teaming With Automation Services To enable Westin to be immediately effective on this SCADA project we have teamed with Jeff Adler of Automation Services. Jeff was involved with the installation of the City's original BIF SCADA system and has assisted the City since then with changes and improvements. Jeff's knowledge of the system and operation will be valuable in putting together the databases and control strategies needed for the new system. OPTIONS, ADDED VALUE Cost reductions. This proposal has been prepared to respond to the methodology and requirements detailed in the Request for Proposal. Westin's experience has shown that costs can often be reduced by making small changes to the requirements. Westin would like the opportunity to discuss these changes during fee negotiations. It is anticipated that significant savings can be achieved. City of Huntington Beach, SCADA Upgrade Added value. Westin can provide additional services outside the scope requested in the RFP. These may have significant benefits to the City. These include: . • Generate Process and Instrumentation drawings (P&IDs) • Include software configuration as part of the professional services scope of work • Integrate the SCADA software with other utility applications, such as on- line O&M manuals. • Employing a "partnering" approach to the construction phase. This methodology is designed to deliver a project as a team (City, Westin and Contractor). This avoids defaulting to an adversarial relationship that often occurs between Owner and Contractor. Westin looks forward to discussing these opportunities with the City. ORGANIZATION OF THIS PROPOSAL The proposal is organized to reflect the required content indicated in the Request for Proposal. The Fee proposal has been included in a separate sealed envelope as requested by the City. SUMMARY Westin looks forward to working with the City of Huntington Beach on the SCADA project. All of the project team members will be committed to the project for its entire duration. For a detailed description of Westin's project approach, please see the Work Statement. 1-2 SCOPE OF SERVICES .4 INTRODUCTION The Work Statement defined in this section is the basis for the engineering services to upgrade the City of Huntington Beach's SCADA system and communication network. This Work Statement amends and supersedes Westin's proposal dated July 1998. OBJECTIVES The objectives for the SCADA System upgrade include: Deliver to the City an upgraded SCADA system that takes advantage of the new technologies delivered by a modern SCADA system. Employ the most effective communications media. Major considerations are reliability and cost. Deliver a reliable, easy to use and maintain system, meeting both short and long-term needs. WESTIN APPROACH The upgrade to the water SCADA system is not an exceptionally large one, but has aspects that need to be managed carefully. Westin's Westin has been the SCADA specialist of choice for many major water utilities including: • MWD • S. Nevada Water • California DWR • City of Pasadena • Mesa Consolidate experience has show that a teamed approach, where the consultant works closely with plant City of Huntington Beach, SCADA Upgrade staff, during all phases, results in a project that meets or exceeds expectations. Adding Westin's project management and SCADA technical expertise, Automation Services knowledge of the current installation, and the City staff s understanding of the water system and process needs — will create the team with the essential skills to deliver a successful project the utility can showcase to other departments and city visitors. L U tU 0 n Q M v a) E m a� F- Project Participation The project will be executed in three phases: Phase 1 - System Master Plan Phase 2 - Specification and Bidding Documents Phase 3 - Bidding and Construction Services Westin's approach to each of these phases is detailed in the following paragraphs. TASK 1— SCADA SYSTEM MASTER PLAN Introduction Phase 1, the SCADA Master Plan when complete will serve as a roadmap for the Amendment to Proposal Dated July 1998 2-1 SCOPE OF SERVICES :4 development of Phase 2, (specifications and bid documents) and the implementation Phase. It reviews the utilities existing system, and then through a number of workshops, determines the requirements for the new SCADA system. The workshops are one of the most important elements of the work. These "brainstorming" sessions generate the ideas which develop into the requirements specification for the new SCADA system. During the workshops the City's staff is encouraged to look ahead at how they see the utility operating in the next 5 to 10 years. The SCADA system can contribute to the efficient operation of the utility by providing easily accessible information to decision makers (operators and planners for example). The information (not just data!) must be in the form the user needs and must be available where it is needed. This may be at "central", in the field Modern SCADA systems are also important information systems that need to be integrated into a utilities information architecture. (mobile user), or at the home of an "on -call" operator. The plant staff s knowledge of the utility's processing and operational needs, together with Westin's expertise in SCADA and information systems, will allow Westin to determine and document the requirements for the new SCADA system. Jeff Adler of Automation Services is part of the Westin's team and will participate in most of the listed activities. The following paragraphs City of Huntington Beach, SCADA Upgrade describe Westin's approach to each task in detail. Task 1.1— Mobilization Obiectives The mobilization tasks will: prepare the Westin and City's team for the project activities. At the end of his task all members will understand the projects objectives, terms of reference, scope and deliverables. The City of Huntington Beach's project manager will be Westin's primary contact. Methodolotjy As a first task Westin will prepare and distribute: • A project workplan • A list of a drawings. and information needed from the City. After review of the above information Westin will hold a project kick-off meeting with the City. The agenda will include: Meeting No. I Introduction of team members for Westin and the City • Review and confirm project objectives, scope, and terms of reference • Finalize administrative arrangements • Review project schedule • Set dates for initial workshops • Facility tour and field site visits. Task Output a. Project Work Plan b. Technical Specification Table of Contents c. Workshop schedule d. Meeting minutes. Amendment to Proposal Dated July 1998 2-2 SCOPE OF SERVICES :4 Task 1.2 — Review Current System Objectives The Westin team will become familiar with all parts of the existing SCADA system, in preparation for holding the first "requirements" workshop. MethodoloQy An initial project database will be created for the SCADA system. This will detail the remote sites, locations, associated instruments and controlled devices, RTU inputs/outputs, RTU power source, existing control strategies and alarms, and lists of drawings. The input/output database will be directly extracted from the BIF RTUs as an electronic file.. MeetingNo.1 To prepare for the first requirements workshop an initial meeting will held with City designated senior staff to list and discuss known future projects, expansions, and modifications that the SCADA will need to accommodate. The following approach will be followed: • Prepare draft project database Visit "central' and typical remote sites. Compare existing drawings with site conditions and make markups/notes as necessary • Update database as a result of site visits • Prepare a block diagram of the existing system and "system operations" description Meeting No.2 Meet with senior staff to discuss future expansions, updates and modifications to the water systems. Discuss and document City of Huntington Beach, SCADA Upgrade Task Output • Project database • Meeting minutes • System block diagram • System Operations descriptions Task 1.3 — Conduct Requirements Workshops Objectives Two workshops will be held to define the requirements for the new SCADA system. MethodoloQv Westin, together with plant staff, will define the requirements and design of the SCADA system based on three factors: 1) The people and organizations who use the system to do their work 2) The functions and processes that are performed 3) The enabling technology. As input to this task, Westin will review any existing City utility strategic plans and other documents relevant to the SCADA system. This will include any existing City emergency planning documents. Workshop No. 1. — People and Organization Westin will conduct a requirements workshop for the major groups of the SCAD System. The workshop environment allows for a free flow of ideas, expands thinking beyond current practice, and introduces the capabilities of new technology. Amendment to Proposal Dated July 1998 2-3 SCOPE OF SERVICES At the completion of the workshop, Westin will: • Understand existing job assignments • Have determined current, desired, and future interaction with the new SCADA system • Obtained input into the Requirements Matrix. Workshop no. 2 — Processes and Technology This workshop will determine the required processes and performance of the Water SCADA System. These requirements will be understood by considering basic SCADA Only easily accessible data is valuable functions, and water applications. The SCADA software. configuration requirements will be discussed. The "basic" SCADA functions consist of: • Data acquisition and processing • Real-time and historical data bases • Control functions • Operator interface functions. The "water applications" are system wide functions performed by the host system. Typically these include: • Weather Data • Dispatching, monitoring; and control • Long term historical data • Load management • Reservoir balancing • Reservoir turnover • Water quality • Pressure zones • Emergency management City of Huntington Beach, SCADA Upgrade • Planning data • Control strategy definition • Integrated Information system. The remote -terminal units typically perform the following water applications: • Reservoir Level Control • Flow Totalization • PID Control • Alarms The SCADA "technology" and support requirements are important. They can determine the reliability, useful life of the SCADA system, and its ability to work with other (current and future) utility software applications. Issues that will be discussed include: • Open architecture • Hardware and software standards • Interface requirements • Redundancy • Vendor products — standard/customized • Proven technology (software/hardware) • Ease of use • Owner maintainability • Vendor support • Cut-over/transition considerations Summarizing the workshops Typically many ideas are generated during the course of brainstorming session. These need to be classified and evaluated in terms of their benefit to the City. To assist with this, the ideas will be rated by plant staff as "essential", "high priority", "medium usefulness"(nice to have), and "low priority" (useful if available at appropriate cost). Amendment to Proposal Dated July 1998 2-4 SCOPE OF SERVICES A Westin will further evaluate these using the ` following criteria: • Availability from major system suppliers • Impact on system hardware configuration • Major performance parameters (e.g., response time, CPU utilization, etc.) • Estimated implementation cost (low/medium/high) • Maintenance costs • Required training. Task Output a. Agenda packages for two workshops. b. Requirements summary 'Technical Memorandum. Task 1.4 — Identify Alternatives and Candidates Ob'ectives This task will identify the alternatives that meet the Cities requirements. This will be determined for: a. The communications media (between the central and 44 remote sites). b. The central host hardware and software. c. The remote terminal units (RTUs). An initial evaluation of the options will select the most likely candidates. These will undergo a more detailed analysis in Task 1.5. Methodolo�y Communications option. Westin will consider the communications options to the 44 existing and any new planned remote sites. The evaluation will include: City of Huntington Beach, SCADA Upgrade • Radio — MAS, and spread spectrum • Telephone — leased lines, dial -up, centrix and cellular • Microwave • Cable TV • Fiber optics • Satellite Multiple options exist for some media, such as radio. Westin will prepare a Technical Memorandum listing the pros and cons of each approach, the availability in the city service area, and the order of probable cost. Host and RTUHardware/software options. Westin will evaluate the different types of hardware/software options available and how well they meet the City's requirements. The results will be summarized in a Technical Memorandum. Host software currently popular for water utilities include: "The Fix" from Intellution, "In Touch" from Wonderware, "Factory Link" from US Data, and "Look Out" from Westin's telecommunication expertise is provided by a group of ten Westin communications engineers dedicated to SCADA and network systems. Their experience will ensure that the most appropriate media is recommended to the City. National. Westin staff have worked with, and had hands on experience with many software packages, but have no preferences. Amendment to Proposal Dated July 1998 2-5 SCOPE OF SERVICES :t Workshop No. 3 —Alternatives Evaluation. Westin will hold a half day workshop with the City to review the results of Task 1.4 and agree on the most likely candidates for detailed analysis. Task Output • Technical Memorandum indicating the communications and hardware/software alternatives and summary of the pros and cons • Workshop No. 3 summary. Task 1.5 — Analyze Most Likely Candidates and Make Recommendations i Objectives This task analyses the most likely communications and hardware/software candidate technologies, selected in Task 1.4. SCADA recommendations based on the analysis will be provided. MethodoloQ-y The likely candidate technologies will be analyzed and compared based on the following criteria: • How well they meet the City's current and future needs • Estimated initial cost • Estimated maintenance and training costs • Operational cost. A network diagram, operational description, and outline for possible phasing of the implementation will be prepared for the recommended system. Workshop No. 4. City of Huntington Beach, SCADA Upgrade A half day workshop will be held with utility staff, to review the findings of the analyses. Staff comments will be noted and any -additional analysis needed, completed. The results of this workshop will be basis for preparing the Final Master Plan document. Task Output a. Technical Memorandum with analysis of most likely candidate technologies, and recommendations for the new SCADA system, estimated costs, and operational description. b. Workshop 4 agenda. c. Workshop results summary. Task 1.6 — Prepare and Present Master Plan Report Ob 'ectives Complete and present final SCADA Master Plan Report. Methodolo�y Westin will take the results of all Task 1 workshops and complete a final Master Plan Report. Six copies will be delivered to the City. Workshop No. S . The Master Plan will be presented to the City at this workshop. Task Output Six copies of the SCADA Master Plan Report. Amendment to Proposal Dated July 1998 2-6 SCOPE OF SERVICES _t Task 1 Constraints and Assumptions To estimate the level of effort required for this task the following assumptions were made: a. b. d. Plans for the remote sites, showing major dimensions, are available from the City. Schematics for the existing RTUs are available. It is assumed that updating of these to show actual conditions is a minor task. The existing RTUs will be replaced "in kind", with the new RTU modules installed in the existing RTU cabinets. RTU installation can be done from connection lists and detailed installation drawings will not be required. That workshop dates agreed on, can be maintained. Changes may adversely affect schedule. No allowance has been made for Westin to complete radio frequency searches or radio path studies. These are significant tasks that will be necessary if a radio communications alternative is selected. Westin routinely provides both these services (see work sample in the Appendix) to clients. Should they be necessary for the City, Westin can negotiate to add the necessary additional hours . TASK 2 - SPECIFICATIONS AND BIDDING DOCUMENTS Introduction Phase 2, "Specifications and Bidding Documents", completes the new SCADA system design, based on the Master Plan document developed in Phase 1. It generates bid documents by combining the technical specification with City's front-end documents. City of Huntington Beach, SCADA Upgrade The tasks detailed in the following paragraphs indicate Westin's approach to completing this Phase. Task 2.1— Prepare 80% specification documents Methodolo�y Westin will prepare 80% design documents for review by. the City, and lead an 80% design review workshop. The specifications will cover the work required by the Contractor to supply, configure, install and test the new SCADA system. The specifications will include requirements for the following: SCADA system performance > system over -view > definitions > perfonnance > block diagrams System Functions > computation features > communications > control and monitoring > alarms > RTU control strategies > redundancy System Software Configuration > redundancy > system database > historical database > historical data display > operator interface requirements, including alarm summaries, trends, menus, process displays, navigation, diagnostic displays > reports Communications > Communications media > RTUs > remote access Amendment to Proposal Dated July 1998 2-7 SCOPE OF SERVICES > open standards > communications with other utility software applications • Host system hardware • RTU hardware • Equipment installation • Testing Documentation and training • Project organization > schedule > project manager > monthly reports > correspondence > submittals > responsibilities Task Output 4 80% Specification Task 2.2 — Prepare Database for the New SCADA System Methodolo�v The database developed in Phase 1 of the project will be updated, to reflect the requirements of the new SCADA. Many of the tables required for the specifications are generated directly from this database. These include: • List of remote sites and locations • Instrument List, with range and alarms • Equipment • RTU I/O list • Control strategies • List of required Operator graphics Task Output Tables required for the 80% specifications City of Huntington Beach, SCADA Upgrade TASK 2.3 - 80% Submittal Drawings MethodolotJy Westin will prepare a set of drawings to include with the bid documents. The drawings will include: • Cover sheet • Legend sheet Project location plan • SCADA system block diagram • RTU connection lists • RTU typical layout • Example displays (2) Westin understands that it is the City's intention to replace the existing RTUs and no (significant) additional instrumentation is required. For cost savings, our approach is based on installing the new RTUs in the. existing RTU. cabinets. Because of this simplified approach, Westin will not prepare detailed RTU site and installation drawings, but will provide connection lists for the new RTUs. However, in order for the bidders to develop a complete understanding of the new SCADA system and RTUs, we will prepare sketches for the following typical sites: 1. Well 2. Reservoir 3. Flood Control 4. West Orange County Water Board. Task Output The 80 % submittal drawings Amendment to Proposal Dated July 1998 2-8 SCOPE OF SERVICES :4 TASK 2.4 — 80% Submittal Review Workshop MethodoloQy A workshop will be held with the City to review the 80% submittal. Comments will be incorporated into the Final documents. Task Output Workshop summary TASK 2.5 - Prepare 100% Bid Documents This task brings the 80% specifications and drawings to the 100% level.. Work required as a result of the comments frorp the 80% review workshop is included. MethodoloQy Complete drawings and .specifications to the 100% level. Task Output Final bid documents TASK 2.6 - Estimate of Probable Construction Cost MethodoloQy Westin will estimate the probable construction cost and present the results in an Microsoft Excel spreadsheet. The project database will be used to assist with the estimate. Task Output Probable Construction Cost estimate City of Huntington Beach, SCADA Upgrade TASK 3 — BIDDING AND CONSTRUCTION SUPPORT SERVICES Introduction Phase 3, provides the City with bidding and construction support services. Westin will support the City during these critical phases and assist in making sure new SCADA system is built, installed, tested and documented as required by the specifications. TASK 3.1— Bid Services The following bid services, and level of effort have been allowed for: a) Answering questions from bidders. (Up to 6 hours) b) Conduct pre -bid conference and facility tour. ( 8 hours) c) Assist City evaluate bids. Includes preparing bid evaluation criteria. (Up to 32 hours) d) Make recommendation to the City. (Up to 4 hours) TASK 3.2 - Construction Services The following. construction services, and level of effort have been allowed for: a) Answer Contractor's requests for clarification. (Up to 24 hours) b) Review submittals. (Up to 24 hours). c) Field inspections and reports. (Up to 40 hours.) d) Review requests for change -orders. (Up to 24 hours.) e) Assist City with Factory testing. (Up to 34 hours) f) Assist City during final inspection. (Up to 16 hours). Amendment to Proposal Dated July 1998 2-9 SCOPE OF SERVICES :4 TASK 3.3 - Record Drawings and O&M Manuals. Our proposal is based on including in the specification the requirement that the Contractor generate the "as -built" RTU site drawings. Westin will review contractor's as-builts. (Up to 60 hours effort). City of Huntington Beach, SCADA Upgrade Amendment to Proposal Dated July 1998 2-10 PROFESSIONAL FEE :4 SUMMARY OF FEE Westin's Professional Fee for the City of Huntington Beach's Water SCADA System upgrade, is as follows: Phase 1, Master Plan $ 50,311 Phase 2, Bid Documents $ 40,803 Phase 3, Construction and Bid Services $ 34,561 TOTAL $125,675 For each Phase, payments shall be monthly based on the percentage conipletion of the effort expended on the Tasks on the Cost Spreadsheets. City of Huntington Beach, SCADA Upgrade 1 Amendment to Proposal Dated July 1998 x-Y yy- .w.s �-. _ ��. L� . � 5°•� E C' :"�' 3;F1- '.'xx� -, �; �:e..c.�.. .., ,�...o-....... -. 'cPco_Iect 1�. C ty�ofkHuntington Bea Client: City of Huntington Beach Project Water SCADA Upgrade / Replacement 98 -127 A Project Phase: Phase I Fee Type: Fixed/ Not to exceed 4/9/98 Task NO. Task Name s Staff anti Rate Schedul: No. of Trips No. of Days dreer Task Task Task , @ @ costs Subtotal Cont. Total A'Y £ Quality SCADA mminic CAD Proj Mgr Control ENGR Engr 7echn Proj Admin Admin Asst Clerk 220 145 " 3. • ' Ind. ooc Markup Y 125 125 85 105 60 71 65 40 0% 0 0 PHASE 1 SCADA SYSTEM MASTER PLAN 0 0 Task 1.1 Mobilisation 0 0 a. Generate project plan, billing requirements 8 1,000 1,000 b. Conclude subcontract with Automation Services 4 500 500 c. Internal meeting with AS 0 0 0 0 d. Orientation meeting with City and minutes 4 0 500 500 0 0 Task Outputs 0 0 > Project Plan 0 0 > Meeting minutes 0 0 > Subcontract agreement 0 0 0 0 Task 1.2 Review Current System 0 0 a. Obtain & review existing documentation in detail 8 8 1,680 1,680 b. Prepare database of remotes sites, detailing all 16 1,360 j' 1,360 Instruments, ranges, alarm limits, 110 points to be 0 0 monitored or controlled. Include control strategys 0 0 c. Visit central. Discuss current operations approach 4 4 840 840 with City staff. 0 0 d. Visit typical remote sites, and validate connection lists. 40 1 5 200 4,545 4.545 Check accuracy / markup drawings that are 0 0 available. 0 0 e. Obtain from City staff listing of know expansions 8 1,000 1.000 upgrades and additions needed at the remote 0 0 sites. Document 0 0 f. Prepare updated block diagram showing central, 8 4 16 2,300 2.300 all remotes and communications media 0 0 g. Prepare "System Operations" descriptions 8 4 1,340 1,340 0 0 Task Outputs 0 0 > Updated SCADA database 0 0 > System Block Diagram 0 0 revcost.xls, Phase 1 WBS PHASE 1 - Pagel 10/13198 Task Task Name k.r; s r r �` ' " Staffand Ra a°=Schedule - '" No. of No. of der direct Task Task Task NO. • �>�..` � . �^ Trtps Days costs Subtotal Cont Total .� ��, . �: �� . r T � s! c; a ��� :r „ "'- Quali SCADA mminic AD ty Incl. ooC Proj Mgr Control ENGR Engr Techn Prof Admin Admin Asst Clerk 220 145 Markup N'011 'r_ . a .. ` 125 125 85 105 60 71 65 40 �. .. y 0% > "System Operations descriptions" 0 0 0 0 Task 1.3 Conduct a Requirements Workshop 0 0 a. Prepare an agenda and "information package" for 16 4 2,340 2,340 the meeting. Distribute to attendees prior to 0 0 workshop 0 0 b. Conduct two, one -day meeting with Operations, 16 16 1 2 3,870 3,870 Maintenance and Management to brainstorm and 0 0 agree on SCADA requirements 0 0 c. Prepare Tech Memo summarizing City's 16 0 2,000 2,000 requirements 0 0 Task Outputs 0 0 > Agenda and information package 0 0 > Requirements Technical Memorandum 0 0 0 0 Task 1.4 Identity Alternative Approaches & Evaluate 0 0 a. Based on determined SCADA requirements and 0 0 existing SCADA, Identify a@ematives which will _ 0 0 meet the Citys needs. 0 0 > RTU/ HMI options 16 2.000 2,000 > Communications media 40 1 3 200 5,055 5,055 b.. Evaluate alternatives and prepare draft Tech 24 2 3,250 3,250 Memo for review by the City 0 { 0 c. Hold a halt day workshop with City staff to discuss 8 8 1 1 2,205 2,205 the alternatives and Initial evaluation. Identify the 0 0 candidate approaches for detailed analysis. 0 0 Task Outputs 0 0 > Draft AftemativesTechnical Memorandum 0 0 > Workshop Summary 0 0 0 0 Task 1.5 Analyse candidate Systems, Make 0 0 Recommendations and Brief City .0 0 a. Analyse - 0 0 > Pros and cons 16 2,000 2.000 > Probable cost for purchase and installation 8 1,000 1,000 > Requirements for operation and maintenance 8 1,000 1'000 b. Write-up recommendations 16 2 2,250 2,250 c. Brief City on recommendations and analysis. 4 500 500 0 0 Task Outputs 0 0 revcost.xls, Phase t WBS PHASE 1 - Page 2 10/13198 Task Task Name " , ' _ : tall andRafe Schedule No. of No. of Other direct Task Task Task NO. Trips @ Days @ costs Subtotal Cont Total } =Quality SCADAComminic CAD Proj Mgr Control ENGR Engr Techn ProjAtlmin AdminAsst Gerk 220 145Markup IncL ODC' Will 125 125 85 105 60 71 65 40 0% t� ,y 5 .;EN > Recomendations Tech Memo 0 0 0 0 0 0 Task 1.6 Prepare and Present Master Plan Report 0 0 a. Prepare final Masterplan 30 2 4,000 4,OD0 Task Outputs 0 0 Deliver six copies of the Master Plan to the City 0 0 0 0 0 0 Task 1.7 Project Management ' 0 0 a. Monthly progress report 8 1,0D0 1,000 b. Monthly billing 8 16 16 2,776 2,776 0 0 0 0 0 0 Labor B ODC 246 1 6 1 96 1 48 1 16 16 1 0 1 16 1 4 1 11 Subtotal $ 30,750 750 8,160 5,040 960 1,136 0 640 880 1,595 400 11�M M 7,4 Labor Hour Total 444 Hours Labor Subtotal 436 ODC Subtotal 2,875 Project Total $ 5d,311.00 (1) The spreadsheet automatically adds to the Task Subtotal the Markup to Air/Ground Travel, Cost per Diem and Telephone Cost. (2) The spreadsheet automatically adds to the Task Total the Contingency. Approved By: Project Manager Regional Sales Manager revcostxls, Phase 1 W6S PHASE 1 - Page 3 10/13/98 `•yam •' � • " e<Z"'�:. ,3^' '"`' '%�",y^ _ - ^i i`baae6 5 `�`„3w ih+ of Huntingtpni3eacfiuCADA y xpgralie Client: City of Huntington Beach Project: Water SCADA Upgrade / Replacement Proposal 98.127 Project Phase: Phase 2 Fee Type: Fixed/ Not to exceed Date 4t9t98 Task. Task Name '' a taffand Rate Sche, ule No. of No. of Other direct Task Task Task No. a a, - Trips @ Days Subtotal Cont. Total c rx c�� } " r aim �— a"4w uaily mms AD Proj Mgr Control ENGR Engr Techn Staff Eng Prof Admin Clerk 220 145 Incl ooc Markup 125 85 105 60 105 71 40 0% 0 0 PHASE 2 Specifications & Bidding Documents 0 0 0 0 Task 2.1 Prepare Design specifications 0 0 Prepare 80% submittal 120 4 15,500 15,500 Task Outputs 0 0 80% submittal 0 0 0 0 Task 2.2 Prepare Final Database 0 0 a. Update database developed during Phase 1 8 680 680 Task Outputs 0 0 Final database 0 0 0 0 Task 2.3 Prepare Drawings 0 0 Drawing List Sheets 0 0 1 Cover sheet 1 2 120 120 2 Legend sheet 1 4 240 I' 240 3 Project location plan 1 2 4 490 490 4 SCADA system block diagram 1 6 360 360 5 Central - plan and electrical schematic 1 4 8 8 1.660 1,660 6 Remote site sketches (4 typical) 4 4 20 40 1 2 5,110 5,110 7 RTU panel - typical aramgemenl and mounting 1 8 8 1.160 1,160 8 Typical graphic over -view screen 8 0 1,000 1,000 9 Typical pump station graphic screen a 0 1,000 1,0m 0 0 Task Outputs 0 0 Typical Site Skelches (4) 0 0 RTU Connection Lists 0 0 0 0 Develop data to be displayed on the operator screens 0 0 a. Obtain copies of all current graphic screens and 0 0 review 4 500 500 b. Half day meeting. Meet with plant operations to 8 1,000 1,000 discuss display needs, standard symbols, color 0 0 conventions, screen navigation, menus, 0 0 m. xis. Ph , 2WBs PHASE 2 - page 1 10/13/98 Task I Task Name No. reports, and trends Task 2.4 80% Submittal Review Workshop 80% review meeting with the City Task 2.5 100% Bid Documents a. Add to design specifications b. Prepare final specifications c. Check specifications compatible with general provisions. Correct if necessary Task Outputs Integrated bid documents Task 2.6 Prepare Estimate of Construction Costs Prepare estimate Task Outputs Estimate Task 2.6 Project Management a. Monthly progress reports b. Billings c. Bi-weekly progress meetings with the City Staff'and Rate Schedule : No. of No. or d ret Task Task Task „ Trips Q Days LID costs Subtotal Cont. Total �P $ ,.CAD Quality SCADA Comma Ind. ODC Proj Mgr Control ENGR Engr Techn Staff Eng Proj Admin Clerk 220 145 Markup 125 125 85 105 60 105 71 40 _ ; , :" , , 0% 0 0 8 200 1,200 4 1 20 4 8 8 2 4 8 24 4 4 Labor 8: ODC 1 234 1 15 148 0 72 0 1 8 1 0 1 1 2 Subtotals 1 29.250 1,875 4.080 0 4.320 0 568 0 220 290 200 Labor Hour Total 377 Hours Labor Subtotal 40,093 ODC Subtotal 710 (1) The spreadsheet automatically adds to the Task Subtotal the Markup to Air/Ground Travel, Cost per Diem and Telephone Cost. (2) The spreadsheet automatically adds to the Task Total the Contingency. 3.0 OI I 3,0001 1,000 1,000 1.590 1,590 0 0 0 0 0 0 0 0 1,284 1,284 284 284 3,000 3.000 0 0 Total $ 40,803.001 Approved By: Project Manager Regional Sales Manager r...�.i.k.. P.-ewes PHASE 2 - page 2 10/13/98 _: , •• ,u Nw{.. _, f......, a .'�.✓. ... ej�'.1t._1'„ _ _ ....�1l.. '`�••., i'+: ' _ _ arm ..ia _ T+�Y�r.... :.y.=f - 1 N :. ~a •jai. r :''4r tY F•µi(1Y . M,t "1 :d'C of I n itt gtor Beach SC�A•ftJ ;.;,: { q}'a grade _.. Pa+Fs,Bx:'.• M' �• .r. •.'- 7: :iri`r.+fr•�" 1.a�ia; Ss .. r1. �.e 8,.-. S Y:RLyea'_. S1AS W {'aS�l!A•i•'s �.'�'h.. Client: City of Huntington Beach Project: Water SCADA Upgrade / Replacement Proposal go-127 :w Project Phase: Phase 3 Fee Type:i Fixed/ Not to excelled Data 4/9/98 Task Task Name' E-kEz'S'Ji=-4 '.T , r`[f j,�'F•., :i.E�.t: ��WSr;'r _\K. •-e=.lF� F ``'''`""'$`L1,11ff-�j�dRate S�cfh�eclule� s h No. of No. of Other direct Task Task Task No. [a s. �r .d3a�"�stiyr. 4 Trips @ Days costs Subtotal Cont. Total >1LL1yy Way �.N _ S.j'rii - ":: q • : ,f'= „i= - ; r..;; `"i:..'{?:_...r7:.'s%: ''.:,,t:" .°�s: �"'q.:'.ih�'.•+w�:' f:`d. .�9'!: '-';5 ..i°`,.:'4:p!:.:: ;•:y ` =- .>.E:=:' • 4.. T , :. .�,r:: _ i `� `4:y `M :>Si=•.S...N *.'-NS_,� • a r- . Quality SCADA Comms Staff P ' Mgr Control ENGR n r 7 roJ g E gr Eng CAD ech Proj Admin Clerk 220 145 .:�'.�:..�4 IneL ODC Mukup :S- *':•+�-•�::•`-+ };.- ^i �."k:t't'%.'4"'•iz"' :';F.:z' WrL''�; _ _F.�i .•" _ t ':-TPt:%+•--Y,; '..i;:.i` . rG1." ii:1. d t r yt� ..�.,.';3:4iu;;;;,�:,�'-;;.:_<„•,;.r .,.sat 125 125 85 104 104 60 71 40 ��rk�.-�isi�%"" 10°6 �:" �� -� 0 0 PHASE 3 Bidding & Installation Technical 0 0 Supporft Services 0 0 0 0 Task 3.1 Prebid/Bid Services 0 0 a. Conduct Pre -bid conference and tour of facility 8 1.000 1,000 b. Answer bidders questions 6 r 750 750 c. Assist City evaluate bids. Prepare evaluation 24 8 2 3,888 3,888 criteria document. 0 0 d. Make recommendation to City for contract 4 500 500 award 0 0 0 0 Task 3.2 Construction Services 0 0 a. Answer contractors requests for clarification 0 0 > allow up to 24 mhrs 16 4 4 2,756 2.756 b. Review submittals 0 0 > allow up to 24 mhrs 24 3.000 3.000 i c. Field inspection and reports 0 0 > allow for 8 site visits and prpare 8 reports 40 2 2 200 6,023 6,023 d. Review requests for change -orders and make 0 0 recommendation to city 0 0 > allow for up to 24 mhrs 24 3,000 3,000 e. Assist City during Factory Test 0 0 > allow for up to 32 mhrs testing and 1 report 32 4,000 4.ODO f. Assist City during final Inspection/ acceptance 0 0 > allow for 16 mhrs for final inspection, and 16 2,DD0 2,000 preparation of one report. 0 0 0 0 Task 3.3 Record Drawings B Operations and Maintenance 0 0 Manual 0 0 a. Prepare record drawings of constructed facilties 0 0 > Obtain redlined drawings from contractor 0 0 showing all field modifications Sheets 0 0 > Revierw update RTU connection diagrams 44 a 8 2 4 2.282 2,262 > Review update remote site plan drawings and 44 8 8 1,160 1.160 schematics 01 0 PHASE 3 - page 1 16111rsa Task No. Task Name > Update system block diagram > Update central host system plan and schematic b. Assemble the Operations and Manintenance Manual for the components, from material provided by the Contractor. Task 3.4 Project management a. Attend up to four site construction meetings b. Billings �..��r ra:;�s"•r y : `.�_ ,- � "}:,t ':; �qc;` N ,7�;r��, .. t .w. `Staff.Fa dRate Schedule, r•..,w;Y ss� :;� �;> Y.. ri.; .. •4y sQ�ti; "� :`� ? ; is'�.�y an } No. of Trips @ No. of Days @ Other direct costs Task Subtotal Task Cont „fir, Quality SCADA Comms Staff ProjMgr Control ENGR Engr Engr CAD Tech ProjAdmin Clark 220 145 ' ' - Ine1 oDC Mftp Y.a•:w 125 125 85 104 104 60 71 40 10% 1 2 4 410 1 2 4 410 0 0 16 1.360 16 Labor & ODC 1 210 0 48 8 0 24 0 1 0 4 1 6 Subtotal $ 28.250 0 4,080 624 0 1.440 0 0 880 Labor Hour Total 288 Hours Labor Subtotal 32,394 ODCSubtot (1) The spreadsheet automatically adds to the Task Subtotal the Markup to Air/Ground Travel. Cost per Diem and Telephone Cost. (2) The spreadsheet automatically adds to the Task Total the Contingency. Approved By: Project Manager Regional Sales Manager 0 0 0 0 0 2,000 20 22 Task Total 4101 2,167 Project Total $ U,561.00 $ 34,561.00 .wmaxa. P.r3vss• PHASE 3- page 1o/ta/9a QUALIFICATIONS INTRODUCTION Westin has provided consulting engineering services for many water utilities on projects of similar scope to the City of Huntington Beach's Water Operations SCADA system project. Westin's contracts range from the large multi- discipline California State Water Project, which included planning and implementation of the California Aqueduct control systems replacement, to PC based SCADA systems for water districts and municipal water agencies. Metropolitan Water District of Southern California 350 South Grand Avenue Los Angeles, CA 90071 Mr. Richard Avery = (213) - 217-7181 Services provided: Detailed studies for control center design, control consoles, rear projection video systems. Current Westin projects with MWD include preparation of the SCADA specification for the Colorado River Aqueduct (Desert SCADA), engineering drawings for the five pumping plants on the Colorado River Aqueduct, system Factory Test assistance, Operator Display Standards and ongoing project management assistance with MWD's system wide SCADA system. Westin Participants; William Gabris, Alan Carrie City of Pasadena - Water & Power Department 150 S. Los Robles Avenue, Suite 200 Pasadena, CA 91101 Mr. Ronnie Smith - (626) 744-4015 Services provided: Prepared specifications for a PC based Water SCADA system to replace the City's existing telemetry system. The project scope included field site visits, site sketches, field device inventory, I/O definition, selection of new equipment, SCADA system technical bid City of Huntington Beach, SCADA Upgrade specification, and project management. Products selected were Pentium Pro PCs in a dual redundant - automatic failover configuration running Windows NT and Wonderware Intouch v6.0. RTUs consisted of two models of Tesco controllers communicating. in Modbus. This SCADA project is currently in the design and procurement phase. Westin Participants: William Gabris Mesa Consolidated Water District 1965 Placentia Avenue Costa Mesa, CA 92627 Mr. Bill Johnson - (714) 754-1291 Services provided: Specification for a PC based Water SCADA system to replace the District's aging tone telemetry system. The project scope included field site visits, site sketches, field device inventory, I/O point lists, SCADA system bid specification, bid evaluation and vendor selection, and project management. Products selected were Pentium PCs in a dual redundant - automatic failover configuration running Windows 3.11 and Wonderware InTouch v5.0. RTUs consisted of two models of Modicon PLCs communicating in Modbus. This project was completed in August 1995. Westin Participants; William Gabris City of Henderson 240 Water Street Henderson, Nevada 89015 Mr. Michael Morine P.E. - (702) 565-2803 Services provided; Strategic planning, requirements, and preliminary design for the SCADA system upgrade to accommodate the water treatment plant and the expansion of the wastewater treatment plant. Westin Participants; Alan Carrie, Russ Collins, William Gabris 3-1 PROJECT TEAM INTRODUCTION The City of Huntington Beach Water Operations SCADA System upgrade project requires a project team with experience in the following disciplines: • PC Based SCADA • Telecommunications • Local SCADA Vendors. We have assembled a project team of experienced senior engineers. Each team member specializes in one or more of the required skills and has a verifiable record of successful projects. WESTIN Westin Engineering, Inc. is the largest - SCADA specialty engineering firm in the Specialists United States. Our core competencies - Telecom include the economic application of Experience instrumentation..control, - Local Oficc telecommunication, and information - IS09000 systems to the water and wastewater Compliant industries. Westin has managed many recent water SCADA projects in Southern California including: Metropolitan Water District of Southern California • The City of Pasadena • The City of Burbank • Mesa Consolidated Water District. Our project team is knowledgeable in the specific hardware and software of interest to the City including all the PC based SCADA packages. Westin's project strengths directly align with the critical requirements of the City of Huntington Beach's SCADA System project, and we will bring afresh perspective to the project based on our of record of successful projects. City of Huntington Beach, SCADA Upgrade PROJECT ORGANIZATION The Westin project team and their principal project functions are shown in Figure 1. The individuals named are those who will play key roles. They will be -assisted by additional engineers, engineering aides, technicians, drafters and clerical personnel drawn from the project team staff. Each of the team member's selection was evaluated against the following criteria: • Demonstrated competence in the specific area of work assigned • In-depth experience with water system processes and automation systems • A record of successful completions on projects of similar size and scope • Existing workload will allow dedication to the SCADA System project. PROJECT MEMBER -SUMMARIES Project Manager - Mr. William Gabris Mr. William Gabris, a Principal Engineer with Westin Engineering, will be the Project Manager for the SCADA System project. He has over 25 years of experience with information and control systems for both industrial and municipal clients. Backup Project Manager and Quality Control - Mr. Alan Carrie Mr. Alan Carrie, a Principal Engineer with Westin Engineering, will serve as backup Project Manager and will provide Quality Control for the SCADA system project'based on Westin's ISO 9000 Quality Control procedures. Mr. Carrie has over 25 years of experience in the fields of instrumentation, automation, and 4-1 PROJECT TEAM information systems, for both industrial and municipal clients. SCADA Engineer - Mr. Jeff Adler Mr. Adler, the President of Automation Sdrvices, has over 20 years experience in the design and implementation of small to medium sized SCADA control systems, design of microprocessor -based RTUs, project management, project field startup, and demand field service. Mr. Adler was also the major contributor to the City's existing SCADA system. Telecommunications Manager — Mr. Russ Collins Mr. Collins has over 30 years of professional utility experience involving telecommunications. planning, design, engineering. operations, and management. He has hands-on experience in all aspects of telecommunications technologies. RESUMES The project staff resumes follow. City of Huntington Beach, SCADA Upgrade 4-2 PROJECT TEAM CITY OF HUNTINGTON BEACH Water SCADA System CITY OF HUNTINGTON BEACH PROJECT MANAGER WESTIN Project Manager William Gabris WESTI N Quality. Control Alan Carrie Telecommunications SCADAEngineer Russ Collins I I Jeff Adler City of Huntington Beach 3 07/21/98 William Gabris - Principal Engineer Education: Master of Science Business Administration, 1979 University of California, Irvine Graduate Studies, Computer Science, 1974-75 University of California, Irvine Master of Science Electrical Engineering, 1967 Washington University; St. Louis, Missouri Bachelor of Science Electrical Engineering. 1965 Washington University; St. Louis, Missouri Honoraries: Dean's Scholar, Tau Beta Phi, Eta Kappa Nu, Omicron Delta Kappa Professional Activities: American Gas Association ENTELEC Tau Beta Pi Eta Kappa Nu Summary: Mr. Gabris has over 25 years of professional experience in the fields of Control, Information, and Communication Systems for Water Utilities, Gas Utilities, and Electric Utilities in both domestic and international markets. His experience includes requirements analysis, preliminary design, technical specification, bid evaluation, contract negotiation, work statement, system integration and testing, and project management. Mr. Gabris' background includes all aspects of system experience including employment as a user, designer with both small and large system vendors, and employment with consulting firms. He has remained current with new technology through continuing education and technical society activities. Professional Experience Specific projects in which Mr. Gabris has been a principal contributor include: • Metropolitan Water District of Southern California - the largest water distribution utility in the United States. Requirements, Preliminary Design, Specifications, and Technical Support for the modernization and implementation of the control systems for the district's water treatment plants, water distribution system, and aqueduct. City of Pasadena Planning, Requirements, Preliminary Design, Specifications, Bid Evaluation, and Project Management for the implementation of a PC based Water SCADA System. • East Bay Municipal Utilities District - Preliminary Design, Specifications, Bid Evaluation, Contract, Project Management and Technical Support for a three level hierarchical Water Distribution Control system. • City of Henderson - Planning and Requirements Study for the expansion of a Water/Wastewater system. • Imperial Irrigation District - Preparation of a Strategic Information System Master Plan including system pre -design and SCADA System Specification. • Southern California Gas Company - the largest gas distribution company in the United States. Strategic Planning, Requirements, Preliminary Design, Specifications, Bid Evaluation, and Project Management for the implementation of a Gas Energy Management and Information System. • Consumers Power - Requirements Study, Specifications, Bidder Prequalification, Bid Evaluation, Work Statement, and Project Management for a Gas Energy Management System including an on-line transient model. Alan Carrie - Principal Engineer Education: I Bachelor of Science, Electrical Engineering, 1968 Canterbury University; New Zealand Professional Registration Electrical Engineering. California, No. E-13848 New Zealand, No. 5561 Professional Activities: American Water Works Association - AY6VA Controls Committee Member Instrumentation Society of America - ISA Member Institute of Electrical and Electronic Engineers - IEEE Member Summary: Mr. Carrie is a Professional Engineer with over 25 years of experience in the fields of instrumentation, automation, and information systems, for both industrial and municipal clients.. His experience includes project management, requirements analysis, preliminary design. technical specification, bid evaluation, contract negotiation, system integration, testing, and services during construction. Professional Experience Mr. Carrie has been active in the water, wastewater, food and metal industries as a project manager, planner, and designer. for a broad range of projects. Manv have been highly automated computer based plant control systems designed to minimize supervisory staff while maintaining high reliability and control flexibility. The following are representative projects which Mr. Carrie has been either project manager or a major contributor: • County Sanitation Districts of Orange County. Project Manager for the expansion and upgrading of the computerized monitoring and control system for the Districts' major wastewater treatment plants in Fountain Valley and Huntington Beach. West Basin Municipal Water District - Project Manager for the design of the instrumentation and computer based control system for the District's new 20mgd Water Reclamation Treatment Facility in the City of E1 Segundo, California. • The City. of Los Angeles Bureau of Sanitation, Hyperion Plant, El Segundo - Lead instrumentation and control system engineer for the design of the control system upgrade for Ocean Outfall Effluent Pumping Plant (EPP). • The City of Los Angeles Bureau of Sanitation, Tillman Plant. Van Nuvs - Lead instrumentation and control system engineer for a range of wastewater projects for the City. Major projects included a new dechlorination facility and the doubling of the capacity of the plant headworks. . • City of San Buenaventura, California - Design of instrumentation and controls for a new well and groundwater treatment plant. RUSS COLLINS, P.E. — Telecommunications Manager Education Summary: • Prepared business cases for f installation and leaseback of B.S.E.E., Marquette Mr. Collins has over 30 years of Overhead Protective Ground University, 1962 professional experience in Wire (OPGW) on transmission FCC Commercial and electric and gas utilities lines. Amateur Radio involving communications Licenses planning.. design, engineering, Microwave Radio Systems - operations, and management. Professional Registration He. has hands-on experience in • ._ Planned, installed,.and all aspects of operated a200 mile. 300 Registered Professional telecommunications channel analog microwave Engineer, California technologies including fiber radio backbone system for optics, analog and digital transmission.line protection Professional Activities microwave radio, two way and control. trunked and simulcast dispatch Institute of Electrical and radio, data networks, process • Planned, installed, and Electronic Engineers, (IEEE) control systems, voice switching operated several 6 Ghz. DS-3 IEEE Communications systems, and network control digital loop microwave Society center design. He has held systems for enterprise IEEE Computer Society management positions with networking and many 2. 6, and Utilities responsibility for strategic 10 Ghz. spur systems for Telecommunications planning. staffing, organizing, electric and gas applications -- Council (UTC), past budgeting, and operating a president. progressive and successful Dispatch Radio Systems- ; utility telecommunications department. • Planned, installed, and operated both Ericsson and Professional Experience Motorola two-way radio networks including UHF and Mr. Collins has held positions of 800 Megahertz. trunked. Engineer. Supervisor, and simulcast, wide -area systems. Manager at several large electric and gas utilities. During these Voice Systems - assignments, he completed the following typical major • Planned, installed and operated projects: PBX systems. tandem switches, Automatic Call Fiber Optic Systems — Distributors, Voice Mail systems, Interactive Voice • Planned, designed, installed. Response units, dispatch and operated a 75 mile OC- consoles, and predictive 48 SONET fiber optic dialers. net�kork. • Negotiated excess fiber capacity lease agreements with common carriers. Jeff Adler -.SCADA Engineer Summary: Mr. Adler is the President of Automation Services, a . company founded in 1990 and specializing in automation and instrumentation systems for the municipal water and wastewater industry. Mr. Adler's experience dates back to 1978 where he began working for BIF Accutel (later .Leeds &.NorthrupBIF).in the SCADA computer systems group. During his tenure at BIF Accutel, Mr. Adler was responsible for the design and implementation of small to medium sized SCADA control systems, design of microprocessor -based RTUs, project management, project field startup, and demand field service. Mr. Adler.was also the author of several SCADA software packages, several of which are still in use today. As the principal of Automation Services, Mr. Adler provides engineering and programming services to water departments across the country. These services include design of telemetry system upgrades, controls design and programming, technical assistance in the evaluation of the controls portions of construction contracts, operational troubleshooting, and ongoing control system maintenance. Professional Experience Specific projects in which Mr. Adler has been a principal contributor include: • :Pueblo.Board of Water Works - Upgrade to 80 MGD water plant &water distribution SCADA system, ongoing designof.telemetry.system improvements, upgrade of field RTU &.telemetry equipment, automatic station controls. ongoing system maintenance and troubleshooting. • City of Westminster - As the City's technical representative. reviewed engineer's designs, provided technical comments and suggestions in order to :. improve the design of the finished product, and worked with contractors to insure that the.final product met the City's technical requirements. Upgraded the City's telemetry system from unreliable tone equipment to PLC -based RTUs. City of Glendale, AZ - Upgrade of 4 of the City's SCADA control computer systems, installation and programming of water plant backwash controls, design and installation of upgraded telemetry systems. PROJECT SCHEDULE INTRODUCTION Westin is proposing an overall schedule for the Consulting Engineering Services for a Water SCADA System of 17 weeks. Our .proposed schedule is based on the following: • A contract start date of 1 August 1998. • A Phase 1 duration of 7 weeks • A Phase 2 duration of 4 weeks • A Phase 3, duration of 5 weeks. • A SCADA vendor proposal preparation time of 4 weeks. • A contract with the recommended SCADA vendor ready for signature by 30 November 1998. We are committing the project team to the City of Huntington Beach Water Operations SCADA System project to ensure project completion on budget and on schedule. City of Huntington Beach, SCADA Upgrade 5-1 City of Huntington Beach SCADA System 1D I 3 Aug I,'98 Aug 9 Aug Ia, '9a Auq II, '9a Auq ]o, '!! Sep 6, '!! Sep tI, '!! Sep I0,'99 Sep 27..98 004.18 Oct II. -to Oct tt,'99 Oa !a, 7a Nov t,'!t Nov a,'ta Nov 1a,.28 2 9 to 23 30 6 13 70 27 4 1 11 18 1 25 1 1 a 15 Taat Nat1w Duration MOBILIZATION 3d PHASE 1 - MASTER PLAN 30d Review Current System 20d Requirements Workshops 10d Alternatives 5d Analysis 5d --- - -------.... . Master Plan Report 10d PHASE 2 - SPECIFICATIONS 20d 80% Specifications 10d SCADA Database 5d 80% Drawing Submittal 15d Review Workshop 3d Cost Estimate 2d Final Specifications 10d PHASE 3 - BIDDING 25d Pre -Bid Support 20d i VENDOR PROPOSAL PRE 20d Task Summary Rolled Up Progress O Project: GNATT.MPP Date: Mon 7120198 Progress Rolled Up Task Milestone Rolled Up Milestone O A ROUTING SHEET INITIATING DEPARTMENT: Public Works - Water SUBJECT: Ugrading of Water Operations SCADA System COUNCIL MEETING DATE: I November 16, 1998 Ordinance (w/exhibits & legislative draft if applicable) Not Applicable Resolution (w/exhibits & legislative draft if applicable) Not Applicable Tract Map, Location Map and/or other Exhibits Not Applicable Contract/Agreement (w/exhibits if applicable) (Signed in full by the City Attorney) Attached Subleases, Third Party Agreements, etc. (Approved as to form by City Attorney) Not Applicable Certificates of Insurance (Approved by the City Attorney) Attached Financial Impact Statement (Unbudget, over $5,000) Not Applicable Bonds (If applicable) Not Applicable Staff Report (If applicable) Not Applicable Commission, Board or Committee Report (If applicable) Not Applicable Findings/Conditions for Approval and/or Denial Attached RCA Author: Ken Dills , phone extension 5055 1 0 J. 7Lj "te CITY OF HUNTINGTON BEACH 2000 MAIN STREET OFFICE OF THE CITY CLERK CONNIE BROCKWAY CITY CLERK November 19, 1998 Mr. William Gabris, Project Manager Westin Engineering, Inc. 100 Park Center Plaza, Suite 500 San Jose, California 95113 CALIFORNIA 92648 Subject: Contract For Professional Consulting Services For Upgrading Of Water Operations SCADA System Dear Mr. Gabris; The above referenced contract has been approved subject to the West Orange County Water Board approving the selection of Westin Engineering, Inc. and the expenditure of budgeted funds for their share of the project costs. Upon direction from Mr. Robert Beardsley, Public Works Director for the City of Huntington Beach, the Agreement will be executed and a copy provided to your company. Sincerely, 6-x�& 4441--T Connie Brockway City Clerk, CMC CC: Robert Beardsley — Public Works Director Ken Dills — Public Works Department G:follow-up/jc/Westin.doc ( Telephone: 714-536.5227 ) (8) 11/16/98 - Council/Agency Agenda - Page 8 E-7. (City Council) Approval Of Contract For Professional Consulting Services For Upgrading Of Water Operations Supervisory Control And Data Acquisition (SCADA) Systems — Westin Engineering, Inc. — Approve Modification To Insurance Requirements (600.10) —1. Approve the selection of Westin Engineering Inc., Tustin, for the planning, design and installation oversight services for the upgrade of the Water Division's existing SCADA system; and 2. Approve and authorize execution of the attached contract between the City and Westin Engineering, Inc. Professional Services Contract Between The City Of Huntington Beach And Westin Engineering, Inc. To Prepare a SCADA System Master Plan For Upgrading City's System for Water Operations (CC- 1092). Subject to the West Orange County Water Board approving the selection of Westin. Engineering, Inc. and the expenditure of budgeted funds for their share of the project costs; and 3. Approve the Settlement Committee recommendation to modify the Indemnification and Hold Harmless paragraph of the attached agreement with Westin. Submitted by the Public Works Director (Remotely monitors and controls critical components of the water production and distribution and flood control systems located throughout the city) [Approved 7-0] E-8. (City Council) Reject Bids And Request Permission To Re -Advertise The Goldenwest Street Storm Drain — CC-1042 — Approve Authorizing DMC Engineering Proposal And Authorize The Public Works Director To Re -Advertise For Bids In Spring, 1999 (600.10) —1. Reject the five bids submitted for the construction of the Goldenwest Street Storm Drain, and direct the City Treasurer to return all bid bonds; and 2. Approve using DMC Engineering, to make the required modifications to the improvement plans and the contract document so that the Goldenwest Street storm drain project can proceed on its current schedule; and 3. Authorize the Director of Public Works to expend up to $6,000 to cover the cost of DMC Engineering proposal and 4. Authorize the Director of Public Works to re -advertise in spring 1999, for bids with a refined bid package for the construction of the project. Submitted by the Public Works Director [Approved 7-0] E-9. (City Council) Approve The Use Of Budgeted Contract Services Funds Using Existing Contracts With Scott, Fazekos & Associates, Inc. — To Perform Plan Review And Staffing Services (600.10) — Approve and authorize the use of budgeted contract funds in Program CD- 234-390 to provide both professional plan review and staffing services, using existing contracts with SFA, Inc. Submitted by the Building & Safety Director [Approved 7-0] EA0. (City Council) Approve Professional Services Contract With JR Consulting Engineers For Continuing Interim Traffic Engineer Services — (Tom Bronard) (600.10) - Approve and authorize the Mayor and City Clerk to execute the agreement between the City of Huntington Beach and JR Consulting Engineers for Interim City Traffic Engineer Services Professional Services Contract Between The City Of Huntington Beach And JR Consulting Engineers, LTD For Interim City Traffic Engineer Services. Submitted by the Public Works Director [Approved 7-0] E-11. (City Council) Adopt Resolution No. 98-85 Which Adopts Local Coastal Program Amendment No. 98-2 — (Zoning Texts & Map Amendments) (420.85) — Approve Local Coastal Program Amendment No. 98-2 by adopting Resolution No. 98-85 (Attachment No. 1) and forward to the California Coastal Commission for certification. Submitted by the Planning Director (CA 93-5, Carts and Kiosks; ZTA 95-1, Residential In -Fill; ZTA 95-2, Adult Business; ZTA 95-3, Floodplain; ZTA 95-6, Sign Code; ZTA 97-4, Sex Oriented Business; ZTA 97-3 ,General Day Care; ZC 94-1, Island Bay; ZC 94-4, Gill School Site; ZC 96-4, Home Depot; ZMA 94-5, Greystone Homes; ZMA 94-6, Q Zoning/Warner; ZMA 96-2, McDonalds/Warner; ZMA 97-2, Christ Presbyterian; ZMA 97-3, Adult Day Care/Bushard and Urgency Ordinance, Adult Business) [Approved 7-0] vos? aR-pm�rs 2as7s�a ,�, D9f� � December 21, 1998 Mr. Thomas Rulla City of Huntington Beach P.O. Box 190 Huntington Beach, CA 92648 Re: SCADA Project - Westin Engineering Dear Mr. Rulla, �• �y�. sue, XITY OF HUNTINGTON BEACH 2000 Main Street Huntington Beach, California 92648 (714) 536-5527 FAX (714) 847 1067 . Zqd &.dd 4920 Campus Drive, Suite A Newport Beach, California 92660 The purpose of this letter is to officially notify you that at the December 15, 1998, meeting of the West Orange County Water Board the selection of Westin Engineering of Tustin for the SCADA Project was unanimously approved. It is the Board's understanding that one- third of the contract work and subsequent cost applies to Board facilities. There are sufficient funds budgeted in the current fiscal year for this work. Should you have any questions, please contact Senior Analyst Ken Dills at 714-375-5055 Cinnornly DEPT OF PUBLIC R �-) BEG 22 199r HUNTINGTON BEACH, CALIF. cc: West Orange County Board of Directors Kenneth J. Dills, Senior Department Analyst i, je CITY OF HUNTINGTON BEACH 2000 MAIN STREET . CALIFORNIA 92648 OFFICE OF THE CITY CLERK CONNIE BROCKWAY CITY CLERK LETTER OF TRANSMITTAL OF ITEM APPROVED BY THE CITY COUNCIL/ REDEVELOPMENT AGENCY OF THE CITY OF HUNTINGTON BEACH DATE: JQ -Y) L) & TO: YY QSj-Y1 Name Street 0 J"cye , City, State, Zip ATTENTION: /Y / 11 #In 65`4 / .5 DEPARTMENT: II1?� REGARDING:C-d�f See Attached Action Agenda Item _ 7 Date of Approval // IF Enclosed For Your Records Is An Executed Copy Of The Above Referenced Agenda Item. Remarks: Connie Brockway City Clerk Attachments: Action Agenda Page Agreement RCA CC: Secckd-s lecf bpi NNTj De artment L Name Department / Name Bonds Insurance Deed Other �e e,e, RCA Agreemen Insurance Other RCA Agreement Insurance Other Department RCA N e Department y - encio z,� Risk Management Dept. RCA Agreement Insurance Other Agreement Insur a Other Insurance Received by Name - Company Name - Date G:Followup/coverltr (Telephone: 714.5 36-5227 )