HomeMy WebLinkAboutBeach Capital Improvements Program - Study Session - 5/23/94 A+ 410 wAiLb OY
BEACH CAPITAL IMPROVEMENT PROGRAM
CITY COUNCIL PRESENTATION
MAY 23, 1994
1. Summary of Projects Hagan
2. Priorities Hagan
3. Citywide Funded and Unfunded Capital Projects Franz
4. Grants Hagan
5. Project Approval Process Hagan
6. Revenue Estimates Franz
7. Conclusion/Questions
44
BEACH MASTER PLAN: CAPITAL IMPROVEMENTS
COST AND REVENUE PROJECTIONS FUNDING SOURCES FOR PROJECTS BUDGET
PROJECT EST.COST 1994 REVENUE EST.New REV. COPS GRANTS OTHER FUNDED UNFUNDED
South Beach Area
Bike Path Sepeparation $1,200,000 € $200,000 $200,000 1 $1,000,000
Restrooms 800,000 125,000 ;' $125,000 250,000 650,000
Parking Lot Imp's 2,700,000 $1,677,000 € $360,000 2,700,000
Sand Wall 200,000 200,000
Landscape 700,000 700,000
Hq's Improvements 100,000 € 100,000
Jr. Guard Hq's Imp's 200,000 162,000 18,000 200,000
Lighting 750,000 750,000
Signage 50,000 10,000 50,000
Sub total $6,700,000 $1,839,000 $388,000 $325,000 $125,000 $450,000 ' $6,350,000
F
Pier Plaza Area
Pier Plaza $3,385,000 $3,000,000 ' $385,000 $3,385,000
Maxwell's 3,500,000 $250,000 $600,000 3,500,000 $3,500,000
Sub Total $6,885,000 1 $250,000 $600,000 $6,500,000 $385,000 $3,385,000 i $3,500,000
Pier Buildings
Ruby's $1,200,000 $100,000 .. $1,000,000 $306,000 $1,306,000
Tower Zero 125,000 = $125,000
Restrooms 125,000 € 125,000
Snack Bar 150,000 20,000 150,000
Bait Shop 125,000 10,000 : 125,000
Sub total $1,725,000 $130,000 $1,000,000 $306,000 $1,306,000 $525,000
Upper and Lower Bluff Area €
Bike Trail $1,000,000 ' $1,000,000 ' $1,000,000
Ped Trail/Wall 1,500,000 $1,500,000
Parking Lot 1,500,000 $250,000 _ 1,500,000
Sub total $4,000,000 $250,000 $1,000,000 $1,000,000 ' $3,000,000
Total:€ $19,310,000 € $2,089,000 $1,368,000 $7,500,000 $1,325,000 € $816,000 $6,141,000 $13,375,000
BECHFUND.XLS 5/17/94
5 Year Totals
Pub
lic Works
Capital Project
s Fund d : < < > >' ><>': ....
Gas Tax Projects
Measure M Pr : .. 1 ':> >> >< s>': <<>'>< :':<>' >» »
Traffic Impact Pro' :.::. > >< s>s IJ> ` ;`s» ><<'M i>< <
Federal C ede al R.P Projects
Sewer Projects
Drainage ro ects
Pier P r
J :::.>.:::::::: ......::::::.....::......:::.:::::::.::::::::::::::.::.
Water Projects
........................
. .G a Fund Projects : : 1 ............................................................
n mi Development
Eco o c
Main Pier ��..: .. .:::::..:.,:...:::::::::::::::.:
Y r own/L a > ''»>`r'<»'''ss::.:, <" ::::.>,::::.. .:.:....:..
o kt ak : .::.x .:
Hunt
ington on Center
Oakv ew&Talbert/Beach
Park Acquisition&Development <' lI .........
Fire Department
e
Fire n ra 'eOe dos
Telecommunications
XX
:.:..:.....:.:.:.......:.:.:..........;...;..:...::........................:.:.. ::.: :.. .........::.....
Police Department ;. ::: :::::::::::::::.::: . :::.
.........:.:. ..... .. .... . . ...:....:..:.: .....
.. ... ... ...s............
Community Services $ #
<.:<.:..:..:::::::::::.... .:
:::::::::::::::::.
>r s
i Services
HousingSet-Aside Set As de
.......:...
TOTAL
CIPSUM.XLS 5/17/94
4/94
PARKING HISTORY
SOUTH BEACH PARKING AREA
YEAR NUMBER OF AUTOS INCOME
1986 285,736 x $4 $1,142,944
1987 261,332 x $4 $1,045,328
1988 236,930 x $4 $ 947,720
1989 208,022 x $5 $1,040,110
1990 206,126 x $5 $1,030,630
1991 197,870 x $5 $ 989,350
1992 208,620 x $5 $1,043,100
1993 202,110 x $6 $1,21200
BEACH CONCESSION INCOME HISTORY
SOUTH BEACH AREA
YEAR CITY INCOME
1986 $92,460
1987 $90,320
1988 $90,540
1989 $89,210
1990 $82,190
1991 $74,620
1992 $79,840
1993 $68,950
SUNSET VISTA CAMPING INCOME HISTORY
SOUTH BEACH AREA
YEAR CITY INCOME
1986 $129,724
1987 $139,025
1988 $145,591
1989 $143,757
1990 $ 97,834
1991 $ 85,440
1992 $ 88,860
1993 $ 71,220
SOUTH BEACH PARKING IMPROVEMENT AREA
Phase I
Listed in order of priority:
1. Bike Path sepa:ation and pedestrian avenue. $ 610,000.00
Includes:
■ Access to the beach (without concrete columns).
■ Retaining walls and seat walls.
■ Handrail and guardrails.
■ Chain link fence separation between parking and bike trail.
Excludes:
■ Lighting (includes some wiring)
■ Planting
■ Irrigation
2. Plazas around concessions $ 513,000.00
Includes:
■ Hardscape
■ Site furnishing (not to include
tables and chairs; to be furnished
by each concessionaire.)
Excludes:
■ Planting
■ Irrigation
■ Basketball court
■ Lighting
■ Restrooms
3. Restroom buildings $ 615,002.00
Includes:
■ Building Shell
■ All amenities
■ Electricity
■ Showers
■ Demo of old buildings
4. ■ Lifeguard headquarters remodel $ 100,000.00
and addition
5. Parking entrance retrofit at Beach $ 70,000.00
Includes:
■ Demo and redo
■ Re-using old A/C at certain places
and slurry coating
■ Entrance itself and short term parking with
new A/C with base
Excludes:
■ Lighting
■ Short term parking panel
6. Parking entrance retrofit at Huntington $ 107,884.00
Includes and excludes same as above.
7. Parking entrance retrofit at Lake Street $ 260,000.00
Includes same as above.
8. Services:
■ Water service
■ Fire hydrant relocation
■ Sewer
■ Drainage structures $ 40,000.00
9. Electrical $ 245,000.00
■ Include stub-ups for future lighting
10. Sand Wall $ 184,800.00
Sub Total $2,745,686.00
Contingency 10% $ 274,568.60
Total Construction Cost $3,020,254.60
A/E Fee 6.5% of entire project $ 415,847.15
Construction Administration $ 60,405.00
Total of Phase One $3,496,506.75
Professional fees for project staking by the civil engineer of record and participation by
the landscape architect, architect, electrical engineer and soil engineer during the bidding
and construction phase is estimated to be 2% of construction cost. This cost for
construction administration based on a construction budget of $3,020,254.00 is
$60,405.00.
ALTERNATES
PRIORITI-ES
1. Signage (partial) $ 30,000.00
2. Planting and Irrigation
in plazas $ 141,215,00
3. Planting and Irrigation
in general. area $ 124,800.00
4. Junior Lifeguard Station. $ 200,000.00
S. Electrical $ 500,000,00
■ Parking lighting $ 350,000.00
■ Low level lighting $ 150,000.00
6. Redo of remaining parking, $1,478,843.00
Includes demolition
7. Palms $ 595,500.00
Additional palm planting and
palm tree lighting
Sub Total $3,070,358.00
10% Contingency $ 307,035.80
'Dotal $3,377,393,80
Total of Phase I
and Alternates
and A/E Fees $6,873,900.55
Items for each phase can be interchanged. Once priorities are confirmed and approved,
we will proceed with construction documents from which we can prepare more specific
cost estimates.
BLUFF TOP/BOTTOM MASTER PLAN
PROJECTED ANNUAL MAINTENANCE COSTS
Amount
1992/93 Projected
Department Actual after Imp'ts
Public Works- Park, Tree & Landscaping $53,153 $55,000
Public Works $ 5,650 $12,500
Community Services 2,404 5,716
TOTAL $61,207 $73,216
NOTE: Community Services Marine Safety, Police and Fire costs will remain the
same.
CITY OF HUNTINGTON BEACH
INTER-DEPARTMENT COMMUNICATION
HUNTINGTON BEACH
MEMORANDUM
TO: Ron Hagan, Director of Community Services
FROM: Daryl D. Smith, Superintendent of Park, Tree and Landscape Division
DATE: April 14, 1994
SUBJECT: Bluff Top Landscape
Per our meeting of 4/12/94 regarding subject matter and maintenance cost of existing
and proposed landscape from about Ninth (9th) Street to Goldenwest Street, please
find below our estimated costs:
1. Maintenance cost for FYB 1992/93 was $53,153.00 or$6,644.12 per acre.
2. Maintenance cost for the proposed re-landscape/reconstructed area should be
approximately the same as existing say$55,000.00.
Should you have any questions regarding the above please give me a call.
DDS:ss
cc: Louis F. Sandoval, Director of Public Works
James Jones, Supervisor of Park Maintenance
John Van Oeffelen, Supervisor of Tree and Landscape Maintenance
Chuck Davis, Landscape Architect
CITY OF HUNTINGTON BEACH TO : Ron Haga
Community Services Department FROM : Jim Way
DATE : April 1 11 , 199
P
SUBJECT : LOWER BLUFF-TOP
PARKING LOT
MEMORANDUM
The development of the lower bluff-top parking lot would bring the
following extra beach maintenance costs :
Capital Outlay
1 . 4 Park-Ur-Self System IV multi-space
parking machine @ $18, 125 each . . . . . . . . . . . . . . . . . . $72, 500
2. Installation & Lighting @ $5,000 each . . . . . . . . . . . $20,000
TOTAL CAPITAL OUTLAY . . . . . . $92,500
Operational Costs
1 . Sweeping, labor - 200 hours @ $15 per hour . . . . . . $3,000
2. Additional handpicking of trash
150 hours @ $8.11 per hour . . . . . . . . . . . . . . . . . . . . . . $1 ,216
ANNUAL LABOR COST . . . . . . . . . $4,216
Material - paint, bumpers, etc. . . . . . . . . . . . . . . . . . $1 ,500
ANNUAL OPERATIMG COST . . . . . $5,716
J• ` CITY OF HUNTING11"Old araACH
INTER-DEPARTMENT COMMUNICATION
HUNi1NGHNd!EACH
TO: Ron Hagan
Community Services Director
FROM: Don Noble
Maintenance Operations Manager
DATE: April 14, 1994
SUBJECT: BLUFF TOP IMPROVEMENTS - NINTH STREET TO GOLDEN WEST
Here is the information you requested regarding the estimated costs of maintaining the
bluff improvements between Ninth and Golden West Streets.
f.. .: pia+:Sla::;:•:;.;.;:....,:^tbeitk hr' ,. •t •...�eiat>.: !r
,. .. y•,'.r.: '' ,.. ,i �.�, tetoei .1 ::;•,. 1g0
£�•., :, {:. � ' x'� sn:'�' �, ,s, .o- �vo-.Trdnte �.k";..Sor•< <,. s <..� ..x..,•s;F!;?�� ju:},: s ...}o-.`.�,. .Ki fix,;
we:S'•'.:,aab, nr+:x%sµ rij:i.•:::•o-:ty- L'..k'a''.,4�A• •}�+'r4',,N�':^"yFF::yK•[e x•.• Y,['.SS ox�xitb�:.>? •:e :[k•: '.}}�.,<w},>
�+•y:h[..•y..,:C:..a,!..n:r: .�;.,?..r, �.•.. x.ldwW 'r,KiK.'T�'{ 'Y'�?:?�Y�4ir Ski',�`i•� 4:rl,,,t.s:
Paving $2,000 $ 2,000 (1)
Railing 2,200 (2) 500
Lighting 750 5,000
Signing & Stripping .0- 51000
Graffiti 700 should zero out
TOTAL COSTS $59650 $12,500
(1) The cost of maintaining a new parking lot, below the bluffs, should be minimal the
first ten years. Costs will Increase thereafter.
(2) Not a maintenance expenditure. This is the cost of replacing failed railing,
C44
Don Noble-�... ..._ ._�....T....r
Maintenance Operations Manager
DN:bh
f4—I 4 U? 8Pbf F'H
Purkiss Rose-RSI
219 N. I-Iarbor Boulevard
Fullerton, CA 92632
Tel. (714) 871-3638
Fax (714) 872-1188
Job Name: BLUFF TOP NORTH, HUNTINGTON BEACH (93-111)
Date: March 2, 1994
Preliminary Cost Estimate
DESCRIPTION QUANTITY UNIT UNIT COST ITEM COST SUB TOTAL
MOBILIZATION
Trailer 1 L.S. 1, 000.00 1, 000. 00
Temporary fencing 12,964 L.F. 2 .00 25,928 . 00
Toilet 1 L.S. 500.00 500. 00
Phone 1 L.S. 500.00 500. 00
Electrical 1 L.S. 1000.00 1, 000. 00
Project manager 1 L.S. 4000.00 4, 000. 00
32 ,928 . 00 32 ,928 .00
CLEARING/GRUBBING
Clearing/Grubbing 204856 S.F. .15 30,728.40
30,728.40 30,728.40
DEMOLITION
Saw cut 120 L.F. 1.00 120. 00
AC Paving 30140 S.F. .50 15, 070. 00
Wall Removal 1 L.S. 100000.00 100, 000.00
Posts 138 EA. 10.00 1, 380. 00
Conc. Steps 2840 S.F. .50 1, 420. 00
Adjust Utility 19 EA. 50.00 950. 00
Boxes
118, 940. 00 118,940.00
EARTHWORK / GRADING
Finish grading 204856 S.F. . 10 20,485. 60
Imported soil 5550 C.Y. 10.00 55,500. 00
1
Preliminary Cost Estimate
DESCRIPTION QUANTITY UNIT UNIT COST ITEM COST SUB TOTAL
Relocated beach 1486 S.F. 2. 00 2,972 . 00
sand
78, 957. 60 78,957. 60
DRAINAGE
ABS 4" 1500 L.F. 8.50 12,750. 00
ABS 6" 1500 L.F. 10.00 15, 000. 00
8" Area drain 10 EA. 80.00 800. 00
12" Area drain 30 EA. 125. 00 3,750. 00
Conc. drain box 200 L.F. 40.00 8, 000. 00
40, 300. 00 40, 300. 00
HARDSCAPE
Curb 370 L.F. 10. 00 3,700. 00
Curb & Gutter 4086 L.F. 15.00 61,290. 00
Concrete paving 4" 15138 S.F. 2 .00 301,276.00
Concrete step 1187 L.F. 6.50 7,715. 50
Mow strip 86 L.F. 6.00 516. 00
Interlocking 11144 S.F. 6.50 72,436. 00
Pavers
Conc. banding 2154 L.F. 25.00 53,850. 00
Repair & cap 4071 L.F. 20.00 81,420. 00
seawall
Rolled conc. curb 3648 L.F. 12.00 43,776. 00
A.C. paving for 160209 S.F. 4.00 640,836. 00
parking lot
995, 815.50 995,815.50
MASONRY
Retaining wall at 1045 L.F. 33.00 34,485.00
undercrossings
Retaining wallS at 1 L.s. 505050.00 505, 050. 00
pedestrian trail
539,535. 00 539, 535. 00
2
Preliminary Cost Estimate
DESCRIPTION QUANTITY UNIT UNIT COST ITEM COST SUB TOTAL
PARKING LOT
Handicap ramp it EA. 1000.00 11,000.00
Drive approach 2 EA. 2000.00 4, 000. 00
Striping 7435 L.S. 1.00 7,435. 00
AC pedestrian 23515 S.F. 1.50 35, 272 . 50
trail
AC bike trail 17148 S.F. 1.50 25,722 . 00
Bike trail 65516 S.F. .40 26,206.40
resurfacing
109,635.90 109, 635. 90
FENCING AND RAILING
Step handrails 418 L.F. 40.00 16,720. 00
Bridge handrails 267 L.F. 40.00 10, 680. 00
Handrail at 3778 L.F. 30.00 113 , 340. 00
pedestrian trail
140,740. 00 140,740.00
SITE AMENITIES
Concrete benches 6 EA. 450.00 2,700. 00
Drinking fountain 5 EA. 2400.00 12,000.00
Trash receptacles 30 EA. 1000.00 30,000. 00
Conc. bollards 36 EA. 300.00 10,800. 00
Overcrossings 2 EA. 50,000.00 100,000. 00
Bike racks 40 EA. 150.00 6,000. 00
161,500. 00 161, 500.00
BUILDINGS AND STRUCTURES
Portable restroom 3 EA. 15,000.00 45,000.00
facilities
Bus stop shelters 2 EA. 3,500.00 7,000.00
52,000. 00 52,.000.00
ELECTRICAL
3
Preliminary Cost Estimate
DESCRIPTION QUANTITY UNIT UNIT COST ITEM COST SUB TOTAL
Bluff Top North 1 L.S. 292418. 00 292,418 . 00
electrical
PCH Lighting (9th 1 L.S. 180000.00 180, 000. 00
to Goldenwest)
Utility Company 1 L.S. 20, 000. 00 20, 000. 00
charges
Traffic signals at 1 L.S. 120000.00 120, 000. 00
PCH and llth St.
Traffic signal 1 L.S. 40000.00 40, 000.00
renovation at PCH
and Goldwesth Ave.
652 ,418.00 652 ,418 . 00
UTILITIES
Domestic water 2 EA. 1,500.00 3, 000. 00
connection
Electric stubouts 10 EA. 500.00 5, 000. 00
Fire Hydrants 7 EA. 5, 000.00 35,000. 00
4"- Water line 3500 L.F. 2.50 8,750.00
51,750. 00 51,750. 00
PLANTING AND IRRIGATION
Soil preparation 204856 S.F. .30 61,456.80
Groundcover 885 FLATS 15.00 13,275.00
Turf 148274 S.F. .50 74, 137.00
Palms (new) 150 EA. 500.00 75,000. 00
1 Gal shrub 1000 EA. 4.50 4,500. 00
5 Gal shrub 500 EA. 18.00 9, 000. 00
Irrigation system 204856 S.F. .50 102,428.00
90 day maintenance 1 L.S. 6, 500.00 6,500. 00
Relocated palms 41 EA. 400.00 16,400.00
Irrigation pump 1 L.S. 25, 000.00 25, 000.00
387,696.80 387,'696.80
TOTAL 3,392,945.20
4
LANDSCAPE AREA RENOVATION
NORTH OF GOLDENWEST AVENUE
Preliminary Cost Estimate
DESCRIPTION QUANTITY UNIT UNIT COST ITEM COST SUB TOTAL
DEMOLITION
Saw cut 565 L.F. 1. 00 565. 00
Removal A/C paving 8984 S.F. . 50 4, 492 . 00
base included
Relocate bench 1 EA. 550. 00 550. 00
Relocate trash 2 EA. 300. 00 600. 00
receptacles
Relocated palsm 4 EA. 600. 00 2 , 400. 00
8, 607. 00 8 , 607. 00
EARTHWORK / GRADING
Finish grading 91035 S.F. .20 18,207. 00
18 , 207. 00 18, 207 . 00
CONCRETE
Concrete paving at 50 S.F. 2. 00 100. 00
existing telephone
Mow strip 190 L.F. 6.50 1,235. 00
A.C. paving 12930 S.F. 1.50 19, 395. 00
Concrete paving at 700 S.F. 2. 00 1,400. 00
picnic table
22 , 130. 00 22 , 130. 00
GUARDRAILING
Guardrail 42" high 170 L.F 42.00 7, 140. 00
Refinishing the 4000 L.F. 3 .50 14, 000. 00
existing guardrail
21, 140. 00 21, 140. 00
ELECTRICAL
Lighting north of 1 L.S. 171233.00 171, 233 . 00
Goldenwest Ave.
5
Preliminary Cost Estimate
DESCRIPTION QUANTITY I UNIT UNIT COST ITEM COST SUB TOTAL
171, 233 . 00 171, 233 .00
SITE AMENITIES
Picnic tables 9 EA. 1,200. 00 10,800.00
One way traffic 1 EA. 1,200.00 1,200. 00
control device
12 , 000. 00 12, 000. 00
PLANTING AND IRRIGATION
Soil preparation 91,035 S.F. .30 27, 310. 50
Groundcover 220 FLATS 15.00 3,300. 00
Redwood header 1,445 L.F. 3.25 4 , 696. 25
Turf (hydroseeded) 68620 S.F. .50 34, 310. 00
Palms B.T.H. 50 EA. 500.00 25, 000. 00
5 Gal shrub 500 EA. 18.00 9 , 000. 00
Irrigation system 91035 S.F. .50 45,517. 50
149, 134 .25 149, 134 .25
TOTAL 402,451.25
SUB-TOTAL FOR NORTH OF
GOLDENWEST AVE. . . . . . . . . $ 402,451.25
SUB-TOTAL FOR BLUFF TOP
NORTH . . . . . . . . . . . . . $31392 .945.20
SUB-TOTAL . . . . . . . $3,795,396.45
3% INFLATION . . . . . . . . . . . . $ 113,862.00
SUB-TOTAL . . . . . . . . . . . $3,909,258.45
6% INCIDENTALS . . . . . . . . . . . $ 245, 556.00
SUB-TOTAL . . . . . . . . . . . $4,154,814.95
10% CONTIGENCY . . . . . . . . . . $ 415, 481.00
TOTAL . . . . . . . . . $4,570,295.45
6
MINUTES
CITY COUNCIUREDEVELOPMENT AGENCY
Room B-8, Civic Center
Huntington Beach, California
Monday, May 23, 1994
Mayor Moulton-Patterson called the adjourned regular meetings of the City Council and
the Redevelopment Agency to order at 5:30 P.M.
CITY COUNCIUREDEVELOPMENT AGENCY ROLL CALL
PRESENT: Bauer, Robitaille, Moulton-Patterson, Winchell, Leipzig, Sullivan
ABSENT: Silva
CLOSED SESSION
The Mayor called a Closed Session of the City Council pursuant to Government Code
Section 54957.6 to meet with its designated representative William Osness, Director of
Personnel and Daniel Cassidy, Esq., Liebert, Cassidy and Frierson Re: Labor
Relations matters - Meet and Confer regarding the following employee organizations:
Police Officers' Association (POA), Municipal Employees Association (MEA), Marine
Safety Officers' Association (MSOA), Municipal Employees Organization (MEO),
Fireman's Benevolent Association (FBA) and Police Management Association (PMA).
The Mayor called a Closed Session of the City Council pursuant to Government Code.
Section 54957 to consider Personnel Matters - Performance Evaluation of City
Administrator.
RECESS - RECONVENE
The Mayor called a recess of Council at 5:30 P.M. The meeting reconvened at 6:30
P.M. in the Council Chamber.
1994-95 CITY BUDGET- DISCUSSION ITEMS
The City Clerk presented a communication from the Director of Administrative Services
dated May 23, 1994 setting forth discussion items as follows: Budget Concepts,
Estimated Shortfall, State Budget, Public Employees Retirement System (PERS)
Unfunded Liability, Potential Ballot Proposition, Budget Timetable.
Page 2 - Council/Agency Minutes - 05/23/94
Robert Franz, Director of Administrative Services, announced that two documents had
been distributed to the City Council: "Month of May Revision State Budget Slide 10A"
and "Fiscal Policies Slide 2A".
The City Administrator reported on the topics covered in Slide 2A - Expenditures
Supported by Revenues, Maintain 3% to 5% Reserve, No New Capital Improvements
unless all Costs Funded, Enterprise Funds, Enterprise Funds Should Reflect All Costs,
Reserves in Excess of 5% Available for Capital Projects and Phase in Period Required.
The City Administrator reviewed the discussion item topics, including Slides 3 through
17. The topics included Budget Problems; Definitions, City General Fund, Shortfall
Estimates, General Fund Reserves, Fund Balance History, Alternatives Solutions,
Impact of Alternative Solutions, City Shortfall Solutions During the Recession, State
Budget--2 Year Perspective, State Budget Shortfall Estimates, Revenue Losses to the
State During the Recession (5 Years), PERS Unfunded Liability Estimated Costs,
PERS Unfunded Liability 1994-95, Potential Local Ballot Initiative, Budget Timetable
May-June and July-September.
Councilmember Bauer commented on areas he would like addressed including the
feasibility of Enterprise Funds and Profit Centers, Performance Based budgeting, public
expectation of same level services with lowered level of resources. The MSI Study as it
relates to the budget was commented upon by Councilmember Leipzig. The fact that
the City does not yet know the State budget plans was discussed. The City
Administrator commented on regionalization and privatization of city services. Mayor
Moulton-Patterson asked the City Administrator if he would investigate consolidating
with school districts as well as with other cities and the City Administrator stated that he
planned to do so.
BEACH CAPITAL IMPROVEMENT PROGRAM
The City Clerk presented a communication from the Director of Community Services
dated May 23, 1994, entitled, "Beach Capital Improvement Program - City Council
Presentation - May 23, 1994".
Ron Hagan, Community Services Director, reported on the South Beach Master Plan,
Maxwell's Master Plan, Bluff-Top, Bluff Bottom Master Plan. He referred to wall
drawings.
Jim Pickel, Purkiss-Rose Associates, reviewed wall exhibits, including Bluff Top Project,
Pier Plaza. The Community Services Director reported on the financing of the South
Beach Master Plan -- cost and revenue projections and funding sources for projects.
He spoke regarding the Maxwell's operation. The Community Services Director spoke
regarding the importance of separating bike and pedestrians and commented on the
number of claims filed against the city from accidents. A report was made on the
parking history of the South Beach Parking Area.
-2-
Page 3 - Council/Agency Minutes - 05/23/94
The Director of Administrative Services reported on the Maxwell's operation and lease
and the plans for rebuilding Maxwell's. The need for more financial information from a
financial consultant was discussed. The use of Certificates of Participation and the
issuance of new debt was discussed by Councilmember Sullivan and the Director of
Administrative Services. Discussion was held between the Community Services
Director and Councilmember Bauer regarding procedure and process to attain
completion of project, use of Certificates of participation and the parking plan at the
Central Library. Councilmember Robitaille presented questions regarding the priority of
Tower Zero.
YOUTH SPORTS FACILITIES PRESENTATION
The City Clerk presented a communication from the Director of Community Services
dated May 23, 1994 entitled, "Youth Sports Facilities Presentation--City Council.
Ron Hagan, Community Services Director, reported referring to wall drawings. Jim
Engle, Deputy Director/Beach, Recreation & Development, reported on three potential
park or school sites for youth sports complexes.
(1) Huntington Central Park (Old Mushroom Farm Area -- east of Goldenwest Street,
North of Ellis Avenue, sixteen acres west of Goldenwest Street at Talbert Avenue
terminus, southwest of Goldenwest and Gothard Streets)
(2) Park View School/Murdy Park
(3) Peterson School (One block east of Beach Boulevard, south of Indianapolis
Avenue)
Jim Engle presented slides. He reported on proposed uses at Huntington Central Park
stating that roller hockey would also be a proposed sport. He presented the constraints
and opportunities on each site. Mr. Engle also reported on the portion of the report
entitled Other Opportunities For Youth Sports Facilities: Ocean View High School,
Dwyer School, Irby Park, Bolsa Chica Linear Park, Lagenbeck Park, School Fields. He
reported on the status of city efforts for joint projects. The Community Services
Director stated it was planned to set up a Youth Sports Task Force from the community.
Councilmember Sullivan thanked Mr. Hagan and Mr. Engle stating that it was an
outstanding report particularly for pointing out the pros and cons. He congratulated the
Department all the way back to former Recreation and Parks Director Norm Worthy,
who had enormous vision.
Presentation by Chuck Beauregard --Save Our Kids -Youth Sports
Chuck Beauregard, representing Save Our Kids, 5942 Edinger Avenue, Suite 307,
Huntington Beach, was introduced to the Council by staff. Mr. Beauregard presented
written information to the City Council.
He stated that some of the Save Our Kids Board members were present: Board
Members include: (Representing Baseball/Softball) Vicki Czuleger, Past President of
-3 -
r y
Page 4 - Council/Agency Minutes - 05/23/94
Robinwood Little League, Mike Simon, Robinwood Little League, Philip Baumfeld, Past
President of Ocean View Little League, John Ringer, Huntington Beach Girls' Softball,
(Representing Soccer) Tim Phelps - Commissioner of Region 56, Paul McLoed,
Commissioner of Region 143, Bruce Bricks, President South Coast Soccer Club, AYSO
Referee, USSF Referee, Dr. Ann Chlebicki, representing Aquatics and Richard
Henderson representing pre-school sport.
Mr. Beauregard reviewed his communication that was presented on slides. He referred
to a research document, The Benefits of Parks and Recreation produced by the Ontario
Ministry of Tourism and Recreation in 1992, which he'stated he would be glad to
provide to Council. He used a slide to present figures and information from the City
Planning Department outlining the 1993-94 Community Profile. He referred to a
Register Newspaper article dated April 14, 1994, Huntington Considers Sports
Complex. Mr. Beauregard presented other slides showing current use of school parks.
He stated that Save Our Kids had three stated objectives: Save Our Kids wants: (1)
The City to establish its youth as the City's number one priority, (2) The City Council to
pass a resolution that before the City can allow the sale or zoning of a public park or
school land currently being used for a Youth Sport activity, the city must find or develop
a new facility or enhance a current facility to accommodate the displaced activity. Such
replacement facility must be a long term solution (3) The city to establish a defined plan
for satisfying the land, water and facilities needs for the youth of the City of Huntington
Beach for the next 25 years.
The materials referred to by Mr. Beauregard were filed with the City Clerk.
ZONING AND SUBDIVISION ORDINANCE (DIVISION 9 RE-WRITE)
The City Clerk presented a communication from Melanie Fallon, Director of Community
Development dated May 19, 1994 entitled Zoning and Subdivision Ordinance Rewrite.
The Community Development Director presented an overview of the proposed Zoning
and Subdivision Ordinance and the proposed public hearing schedule.
Susan Pierce, Associate Planner, reviewed the current and proposed Title 20 General
Provisions and summaries of Title 24 Administration, Title 22 - Overlay Districts and
Title 25 - Subdivisions.
Request For Opinion Re: Conditional Use Permits
Councilmember Leipzig stated that he would like to see the law where the City Council
can extend conditional use permits. The City Attorney reported. Councilmember
Leipzig stated his desire to see this opinion in writing.
-4-
Page 5 - Council/Ag by Minutes - 05/23/94
ADJOURNMENT-COUNCIUREDEVELOPMENT AGENCY
The Mayor adjourned the adjourned regular meetings of the City Council and the
Redevelopment Agency of the City of Huntington Beach to Monday, June 6, 1994 at 5
p.m., Room B-8, Council Chamber, Civic Center.
Clerk of the Redevelopment Agency and
City Clerk and ex-officio Clerk of the City
Council of the City of Huntington Beach,
California
ATTEST:
City Clerk/Clerk Mayor/Chairman
gninutes\940523am
-5 -