HomeMy WebLinkAboutFire Station 8 Heil Relocation to city-owned property at Gra CITY OF HUNTINGTON BEACH
INTER-DEPARTMENT COMMUNICATION
To: City Council
Via: Fred A. Wilson, City Administrator
From: Duane Olson, Fire Chief 6AI;. �
Date: September 18, 2009
SUBJECT: Station 8 — Heil Relocation Proposal
Attached for your review, in conjunction with the PowerPoint Presentation on the
Proposal to Relocate Fire Station 8-Heil to City Owned Property at Graham and
Production, are the following:
1) Attachment 1 - Total Project Cost with Contingencies
2) Attachment 2 - Budgeted One-Time Costs
3) Attachment 3 - Budgeted On-Going Costs
If you have any questions, please call me at (714) 745-6444.
S:\FMT\Olson\Correspondence\Memos\2009\Council Via Wilson-Station 8 Relocation.Doc
/,A/ 'V0 7
0o �l �W
,67M�/
PROPOSAL TO OCATE FIRE
STATION ®HEIL TO Ym NE®
PROPERTY AT GRAN N®
PRODUCTI N
1
CONSIDERATIO F RELOCATION OF
FIRE STATI 8-HEIR,
• Points of consideration for the curr ire station
relocation
— 45 Years old
— Contains asbestos throughout ceiling areas
— Apparatus bay does not properly accommodate dern
fire apparatus
— Parking areas are not secure
— Must meet gender accommodations
— Does not meet the city's current response needs in the
northern part of the city
2
CONSI®ERATIO F RELOCATION OF
FIRE STATI 8-HEIL
• The current location will not sustai city's
Insurance Services Office (ISO) Class r ' g,
awarded to the city in September 2004
• A downgrade of ISO Class 1 to 2 may resul in the
following annual insurance premium increase for
Huntington Beach residents and businesses-
- Residential (1% increase): $411,068
— Commercial (5% increase): $764,330
Total Annual Increase - $1,175,398
3
Engine ISO Standard
Existing Station Locations Proposed St.8 at Graham and Production
Existing Existing
Station 8,Heil Station 8 Sta1.
Bon 8,Heil
4z Relocation
o rStl.n
_�`• Station 2,Murdy
�Sion 7, Station 7,arner Warner
�ion 3,Bushard Station 3,Bushard
Station 6,Edwards Station 6,Edwards U y j4
Station 5,Lake \ * / Station 5,Lake
Sfatton 4,Magnolia Station 4,Magnolia �
Truck ISO Standard
Existing Station Locations Proposed St.8 to Graham and Production
Including Fountain Valley Truck Move Murdy Truck to New Heil Station
i Ing
81 Heil nny..
Heil
Station 8 H
Relocation _JStti..2,-W.
rdy
S Station 1,Gothar
Station 7, Station 7,
Warner Warner
Station 3,Bushard!: # Station 3,Elmhardl
Station li,Edwards' Station 6,Edwards
Station 5,Lake Station 5 Lake
Station 4,Magnolia ~� Station 4,
Magnolia �
CONSIDERATIO F RELOCATION OF
FIRE STATI 8-HEIL
9 FIRE STATION 8-Heil
Benefits of relocation:
4, Improved structural fire response city-wi e and
specifically to northern part of the city and
Huntington Harbor(improved response city-w e)
6
Engine Fire Response
Existing Station Locations Proposed St.8 to Graham and Production
-�-" i Existing Exisfing
Station 8,Heil -�- Station 8,Heil
Station 8
_t Relocation'`
!Station 2,Murdyj _ Station 2,Murdy
i - Station 1,Gothard I Station 1,Gothard
Station 7,. Station 7,
Wamer - Wamer
Station 3,Bushard
i � j
Station 6,Edwards , - ,, (Station 6,Edwards d
Station 5,Lake"
Staff\4,Magnolia Station 4,Magnaha �h
Average Response Time in Minutes
Citvwide Emeraencv Response: Citywide Emeraencv Response:
1st Engine on Scene Average: 4:50 ❑ Under 5:00 El Between 5:00 and 6:00 1st Engine on Scene Average: 4:48
1 st Engine on Scene Percentage:65% ❑ Over 6:00 1 st Engine on Scene Percentage:68%
❑ Over 6:30
Information:MetroNet 1/01/08to 12/31/08
Truck Fire Response
Existing Station Locations Proposed St.8 to Graham and Production
Existing IExisting
statlon 8,Hell Station 8,Hell
Station 8
Relowtlon
..Statio �Statlon 2,Murdy
Z _
" j- � °-' "Station 1,Gothard� � Station 1,Gethard
Station-1 �` - Station 7,
Warner Warner*-i Station 3,Bushard Bushar
i
Station 6,Edwards Station 6,Edwards r
Station 5,Lake t, 1 Station 5,Lake
Station 4,Magnolia( ' Station 4,Magnolia
Average Response Time in Minutes
Citvwide Emergency Response: Citvwide Emergency Response:
1 st Truck on Scene Average: 6:29 ❑ Under 8:00 1 st Truck on Scene Average: 5:50
❑ Between 8:00 and 9:00
1st Truck on Scene Percentage:95% ❑ Over 9:00 1 st Truck on Scene Percentage:98%
❑ Over 10:00
Information:MetroNet 1/01/08 to 12/31/08
CONSI®ERATI® F RELOCATION OF
FIRE STATI 8-HEIL
® FIRE STATION 8-Heil
— Benefits of relocation:
O Improved advance life support to norther area a
Huntington Harbor, creating a better balance or
advanced life support city-wide
9
Advanced Life Support Response
Existing Station Locations Proposed St.8 to Graham and Production
-__ Existing Existing
Station 8,Heil --Station 8 Station 8,Hsit
Relocation
Station 2,Murdy Station 2,Murdy
Station 1,Gothard
Station 1,Gothard
Station 7 (Station 7, �
Warner
Wamer
Station 3,Buaherd
\ Station 3,Bushard
a
k
Station 6,Edwards r r :
Station 6,Lake �/ (Station 6 Lake
Station 4,Magnolia — — - -
' 1 Station 4,Magnolia iv
.. r
Average Response Time in Minutes
Citywide Emeraencv Response: � Ciriwide Emereenev Response:
1 st Unit on S ❑ Under 5:00 1 st Unit on Scene cene Average: 5:12 Average: 5:13
El Between 5:00 and 6:00
1 st Unit on Scene Percentage:53% ❑ Over 6:00 1 st Unit on Scene Percentage:52%
❑ Over 6:30
Infonnation:MetroNet 1/01108 to 12/31/08
CONSIDERATlo F RELOCATION of
FIRE S°TAT1 8-HEIL
• FIRE STATION 8-Heil
— Benefits of relocation:
o Better distribution of paramedic engines and fire cks ci -
wide—ensuring the maintenance of city's ISO Class fire
rating
. Will not contain asbestos
. Will properly accommodate one engine and one truck
. Entire property will be secure
. Will meet all current gender accommodation standards
11
�' Public Safe Facilities Plan
Huntington Beach Strategic
i
rfr-orpmos
edNew St.8i—aintenance of
ISO Class 1
Ir
0 ozsas 15 2
`.u.
*Fire Stations
Proposed New St.8 \ - �
—Street Centerlines
---City Boundary ?1 r a^n J,
12
im cu
CONSI®ERATIO F RELOCATION OF
FIRE STATI &HEIL
• The relocation plan would include:
— Sale of the current fire station site at Spri and
Heil
— Use of the sale funding to construct a tempora station
at city-owned fire station site at Graham and Pro uction
— Relocate the existing fire engine from Fire Station -
Heil to Graham and Production
— Relocate the existing fire truck from Station 2-Murd
to a temporary station at Graham and Production
. Fire Station 2-Murdy remains open with a fire engine and a
city ambulance
13
CONSI®ERATIO F RELOCATION OF
FIRE STATONQ&HEIL
• The relocation plan will be sho in three
phases:
— Phase I — Funding and Costs with City ounce
Approval
— Phase II — Future Improvements
— Phase III — Funding, Finance, and Constructi n
14
CONSI®ERATIO F RELOCATION OF
FIRE STATI 8-HEIL
• Phase I - Funding and Cost with cil approval
— Funding:
. August 2009 Appraisal value of Fire Station 8- il:
— $500,000
- Cost:
. Phase I total project cost with contingencies(see
Attachment I):
— Low-$438,831
— High-$488,831
— Includes: design, site preparation, paving temporary
apparatus structure, modular housing, landscaping an
drainage, security, and utilities
15
CONSI®ERATIO F RELOCATION OF
FIRE STATI &HEIL
• Phase I — Funding and Cost (c ued)
- Additional budgeted one time costs ee
Attachment II)
• Communications - $25,000
• Furniture - $8,000410,000
- Additional budgeted on-going costs (see
Attachment III):
• Rental - $24,000 annually
• Communications - $3,600 annually
16
CONSI®ERATI® F RELOCATION OF
FIRE STATI 8-HEIL
• Phase I —Next Steps
1. Conditional Use Permit(CUP) approv
2. Entitlements
3. Approval to dispose of station as surplus pr erty
4. Sale of fire station property
5. Initiate construction design elements
6. Request for Proposal (RFP)process for station
construction
7. Construct temporary station
Estimated time for construction: 9 months from approval
17
. � 7,
f
A 3
t
� jqpl,
, 'tom, it �j
d 41� 3i1� J 1 t„
®,M
Cin 011, ii—Beorh Fire
Der-,-Proposed Location of New Heil SLN8 wa:eL1f184
CAUTION:When Using This Map `r es
oaelP - • ayd-
18
GINEERED DRAWINGS
PRODUCTION DRIVE a„_ss.. SIfE LEGEND
Yom
--.- , ET
J
�Q'�i p.vvmw+rv.ui
roc....
rtM
mama
47
All
IS
Al 7z
r
i
/ k &
- IN
CONSIDERATI® F RELOCATION OF
FIRE STATI 8-HEIL
® Phase II Future Improvements
Years 3-5
— Driveway aprons —widen and improve
— Add left turn pockets on Graham Street
— Install Curb and Gutter
22
CONSI®ERATIO F RELOCATION OF
FIRE STATI 8-HEIL
• Phase III — Funding, Finance and truction
Years 5-7
Funding
— Finalize funding sources
— Brightwater Development Annexation
— Property Tax Transfer Rates Forecasted
— Representing Orange County Fire Authority's
Structural Fire Fund revenue generated by the tax area
projected at a rate of 11.4%
23
CONSI®ERATIO F RELOCATION OF
FIRE STATI 8-HEIL
• Phase III —Funding, Finance and ruction
(continued)
Funding
. Year 1 -$68,863 (development year 6)
. Year 2-$386,320(development year 7)
e Year 3 -$716,447(development year 8)
® Year 4-$730,776(development year 9)
. Year 5 -$745,392(development year 10)
. Year 6-$760,300(development year 11)
. Year 7-$775,506(development year 12)
24
CONSIDERATIO F RELOCATION OF
FIRE STATI 8-HEIL
• Phase III — Funding, Finance a
Construction
Finance
— Develop and finalize financial plan
— Hard construction cost
— Design, construction management
— Engineered drawings
— Construction
25
CONSIDERATIO F RELOCATION OF
FIRE STATOWJ&HEIL
• Phase III — Funding, Finance a
Construction
Debt Service Financing
— $5,100,000 Fire Station
— Financed over 20 years
— 5% Interest Rate
* Annually $403,893
26
CONSI®ERATIO F RELOCATION OF
FIRE STATI 8-HEIL
® City Council Recommendations fo location of
Fire Station 8-Heil
— Approve the relocation and construction of e
temporary fire station to be located at Graham d
Production as presented
. Cost not to exceed$500,000
. Plus budgeted on-going costs
— Approve Fire Station 8-Heil being placed on the mar et
as a commercial property as recommended by Park
Center Reality Advisor's appraisal for maximum
property value
27
PROPOSAL TO OCATE FIRE
STATION 8-HEIL TO Y-OWNED
PROPERTY AT GRAN N®
PRODUCTION
28
la,
aOv 1�
CITY OF HUNTINGTON BEACH
Heil Street #8 Temporary Fire Facility
Planning Stage Opinion of Probable Cost Estimate
Item No. Description Unit Unit Cost Quantity Total Cost
1 Site Preparation, Clearing and Grubbing sq. ft. $0.15 49800 $7,470
2 Site Grading cu. yd $5.45 1244 $6,780
3 Asphalt Paving sq. yd $25.00 3300 $82,500
4 Driveway Approaches lump sum $10,000.00 1 $10,000
5 Foundation for Tent Apparatus lump sum $22,000.00 1 $22,000
6 Tent Apparatus-Supply and Install each $40,000.00 1 $40,000
7 Portable Trailers-Supply and Install each $18,000.00 2 $36,000
8 Storage Building 8'xl2'-Supply and Install each $3,500.00 2 $7,000
9 ILandscaping sq. ft. $10.00 4150 $41,500
10 Trees at 45' Intervals each $500.00 8 $4,000
11 8' Chainlink Fence with Automatic Rolling Gates linearfooti $35.00 1 300 1 $10,500
AECOM 9/15/2009
CITY OF HUNTINGTON BEACH
Heil Street#8 Temporary Fire Facility
Planning Stage Opinion of Probable Cost Estimate
Item No. F Description Unit Unit Cost Quantity Total Cost
Tie-in to existing water line, water service meter,
12 supply water to applicable locations lump sum $10,000.00 1 $10,000
Tie-in to existing storm drain, site catch basins,
13 piping, and appurtenances lump sum $15,000.00 1 $15,000
Tie-in to existing sewer, establish sewer to
14 applicable locations lump sum $15,000.00 1 $15,000
Utility includes site lighting, transformer,
15 hookup, conduit, etc lump sum $40,000.00 1 $4000
Hard Construction Items-Subtotal $347,750
Mobilization/Demobilization (7.5%) $26,081
Total Construction Cost $373,831
Design, Construction Management, Supplementals $65,000
Total Project Cost $438,831
Contingency $50,000
Total Project Cost with Contingency $488,831
Total Estimated Project Cost $438,831 - $488,831
AECOM 9/15/2009
OR'
u �9
a"
ASK cc "wr
E-!N�v
Not-
IS
ry br 7 � is
CITY OF HUNTINGTON BEACH
Fire Station 8-Heil Temporary Fire Facility
Budgeted One Time Costs
Item NOT Description Unit Unit Cost Quantit Total Cost
1 Relocate 4.9 GHz wireless equipment each $15,000 1 $15,000
2 Install computer, network and related equipment each $5,000 1 $5,000
3 Install computer and network cabling each $5,000 1 $5,000
4 Furniture each $8,000410,000 $8,000-$10,000
Total One Time Costs $33,000-$35,000
lie
T d
xs n
yEl
CITY OF HUNTINGTON BEACH
Fire Station 8-Herd Temporary Fire Facility
BUDGETED ONGOING COSTS
Item No. Description Unit Unit Cost Annual Cost Total 5-Year Cost
1 T-1 communication lines month $300 $3,600 $18,000
2 Modular trailers for personnel month $2,000 $24,000 $120,000
Annual On Going Costs $27,600
Total 5-Year On Going! Costs $138,000