City Council Study Session
Dec. 18, 2017
General Plan: Next Steps
• General Plan Update Adopted on Oct. 2, 2017
• Next Steps
—Zoning Code Update
— Establish Research and Technology (RT) Zone
— Update Local Coastal Program (Coastal Element)
— Update Noise Ordinance
Zoning Code Update
• Typically occurs after a General Plan Update to
implement any changes needed as a result of
the General Plan Update
• Look for ways to create efficiencies in the
planning process
• Modernize the code and delete out of date
standards
• Establish a City Council sub -committee
• Approx. 12 months to process
RT Zone
• Implement the new Research and Technology
General Plan land use designation
• Process concurrently with the zoning code
update
• Conduct extensive outreach with the
stakeholders in the RT areas
• Approx. 8 — 9 months to process
LCP Update
Noise Ordinance Update
• Local Coastal Program Update
— Update Coastal Element of the General Plan
— Approx. 12 — 18 month City process
— Requires Coastal Commission certification
• Noise Ordinance
— Implement the noise standards in the updated
General Plan Noise Element
— Implement mitigation measures adopted for the
Program EIR
— Approx. 7 month process