HomeMy WebLinkAboutSewer Service Fund Performance Audit for Fiscal Year 2014-15 Dept. ID 15-052 Page 1 of 2
Meeting Date: 8/17/2015
Approved 7-0
CITY OF HUNTINGTON BEACH
REQUEST FOR CITY COUNCIL ACTION
MEETING DATE: 8/17/2015
SUBMITTED TO: Honorable Mayor and City Council Members
SUBMITTED BY: Fred A. Wilson, City Manager
PREPARED BY: Travis K. Hopkins, PE, Director of Public Works
SUBJECT: Accept the Sewer Service Fund Performance Audit for Fiscal Year 2014-15 and
suspend the annual Consumer Price Index adjustment of the Sewer Service
Charges for Fiscal Year 2015-16
Statement of Issue:
Section 14.54.060 of the Huntington Beach Municipal Code (HBMC) requires the City Council to
establish sewer service charges by ordinance. Chapter 14.55 of the HBMC establishes the formula
for modifying the charges and codifies an annual increase based on the Consumer Price Index
(CPI) increase available in July. Staff is recommending that the adjustment of charges be
suspended for Fiscal Year 2015-16. The Sewer Service Charge Annual Performance Audit is
presented to the City Council as required by HBMC Section 14.54.070.
Financial Impact:
Sewer Service Fund (511) revenue for Fiscal Year 2015-16 is estimated at $10,937,140 if the CPI
adjustment is made to the Sewer Service Charge and $10,830,000 if the adjustment is suspended
for the fiscal year.
Recommended Action:
A) Accept the Sewer Service Fund Performance Audit for Fiscal Year 2014-15 as presented; and,
B) Suspend the Annual CPI Adjustment of Sewer Service Charges for Fiscal Year 2015-16.
Alternative Action(s):
1. Do not accept the Sewer Service Fund Performance Audit and direct staff to make specific
modifications.
2. Direct staff to prepare an Ordinance to amend the Sewer Service Charge by the percentage
change in the CPI as noted in HBMC Chapter 14.55 for adoption at a later date.
Analysis:
The Sewer Service Fund is designated solely for facilities and resources relating to the
rehabilitation, replacement, repair and maintenance of City-owned sewers and lift-stations. This is
in accordance with California Health and Safety Code Section 5470, and is included as Chapter
14.54 in the HBMC. Section 14.54.070, Annual Program Review, of the HBMC requires an annual
review and performance audit of the Sewer Service Fund by the Public Works Commission. The
audit was presented to the Commission at the July 15, 2015, meeting. Per the Municipal Code, the
City Council shall receive, at a regularly scheduled meeting, the recommendations of the Public
Dept. ID 15-052 Page 2 of 2
Meeting Date: 8/17/2015
Works Commission concerning fees, rates, and charges proposed to be modified or added to the
Sewer Service User Charge.
In accordance with Section 14.55.030, Annual CPIU Adjustments, each Sewer Service User
Charge shall be adjusted to reflect the annual percentage adjustment in the Consumer Price Index
for all Urban Consumers (CPIU) in Los Angeles, Orange and Riverside Counties established by the
U.S. Bureau of Labor Statistics, available as of July 1, 2015. The CPIU reflects an annual increase
of 1.1%.
The estimated reserve for the Sewer Service Fund at the end of the current fiscal year is $23
million, which is above the reserve policy established by the City Council in 2014. If no rate
adjustment is enacted, the proposed budget for Fiscal Year 2015/16 would reduce the surplus by
$1 million, still be above the established reserve policy even with the carry over of Capital
Improvement Projects that are underway. Therefore, Staff is not recommending a rate adjustment
in Fiscal Year 2015/16.
Environmental Status:
Not Applicable
Public Works Commission Action
The Public Works Commission voted 7-0 to recommend to the City Council to approve the report
and to suspend the programmed increase to the Sewer Service User Charge for Fiscal Year
2015/16.
Strategic Plan Goal:
Enhance and maintain infrastructure
Attachmentfs):
1. Annual Sewer Service Fund Performance Audit for Fiscal Year 2014-15
City of Huntington Beach
Public Works Department
Sewer Service Fund Performance Audit
Review of Fiscal Year 2014115
Introduction
On September 4, 2001 , the Huntington Beach City Council adopted a Sewer Service
User Charge and created the Sewer Service Fund. The Sewer Service Fund revenue is
designated solely for the rehabilitation, replacement, repair and maintenance of City-
owned sewers and lift stations. This is in accordance with the California Health and
Safety Code Section 5470, and is included in the ordinance that adds Chapter 14.54 to
the Huntinoton Beach Municipal Code. The ordinance established the Huntington
Beach Public Works Commission as both the oversight committee and the final appeals
board.
The Sewer Service Fund shall be subject to an annual review and performance audit by
the Public Works Commission. The information presented in this report complies with
Section 14.54.070 Annual Program Review. In addition, the City Council shall receive,
at a regularly scheduled meeting, the recommendations of the Public Works
Commission concerning fees, rates and charges proposed to be modified or added to
the sewer service user charge. A public hearing on proposed charges will be held
annually in conjunction with the City's annual budget process and hearing.
Program Overview
➢ Scheduled maintenance projects and minor emergency repairs will be completed
within the allotted budget.
➢ Closed Circuit Television Inspection and cleaning of sewer mains.
➢ Operations and maintenance of the City's 27 sewer lift stations.
➢ Capital improvements including lift station design and construction work and the
sewer lining program.
➢ A Sewer Lateral Program was added effective January 3, 2008, and the sewer
service charge was adjusted to cover the projected expenses. The program
transferred the responsibility to the City for sewer lateral repairs within the City-
owned right-of-way. Initially, the cost of the program exceeded the additional
revenue generated by the adjustment to the sewer service user charge. Costs
for this program have decreased significantly since its inception.
July 2015 - 1 -
➢ The City Council adopted a reserve policy for enterprise funds in FY 14/15. The
reserve policy for the Sewer Service Funds states that the City will maintain a
reserve equal to the sum of the following:
o Operations and Maintenance: Thirty-three percent (33%) of the adopted
annual budget to ensure adequate working capital for operating expenses.
This amount is $2.3 million
o Capital Improvement Program (CIP): One-hundred percent (100%) of the
average annual planned Capital Improvement Program for the following
five years. This amount is $4.1 million.
o Emergency: an amount equal to the estimated cost, as determined by the
City Engineer, to replace one sewer lift station. This amount is $2.1
million.
o The total reserve would amount to $8.5 million.
➢ The Municipal Code states that the Consumer Price Index for Urban Consumers
(CPIU) that is available July 1 shall be used to calculate adjustments to sewer
service rates.
Review of Fiscal Year 2014/15 Budget
Personnel and operating expenditures account for approximately forty-five percent
(45%) of the Fiscal Year 2014/15 Sewer Service Fund budget and are directed toward
preventative and routine maintenance. The budget includes salaries and benefits,
sewer line maintenance, Closed Circuit Television (CCTV), lift station services, manhole
upgrades, the sewer lateral program and cost allocation charges to the City's General
Fund. The balance of the expense budget is earmarked for capital equipment
replacement and capital projects, including slip lining, pipeline rehabilitation, monitoring
of lines, and lift station replacement. In general, the Sewer Maintenance Section of the
Utilities Division expends the operating and equipment replacement budgets, and the
Engineering Division is responsible for the implementation of capital projects.
Warner Avenue Gravity Sewer (WAGS): (CC-1370) Construction of the Warner Avenue
Gravity Sewer (WAGS) project was completed this fiscal year. This resulted in Lift
Station "B" becoming unnecessary and taken out of service.
Lift Stations: Construction of the Trinidad Lift Station was awarded and started this
year. Design of the Edinger Lift Station was also started this fiscal year.
Sewer Linino: A $350,000 sewer lining project was completed this year.
Maintenance Activities : Totals for various maintenance activities are presented below.
CCTV Inspection: The sewer system is inspected through the use of Closed Circuit
Television inspection. A contractor was employed during this last fiscal year to video
July 2015 -2-
inspect portions of the sewer system's main transmission/collection lines located in
the City's arterial and high traffic volume streets. City crews video inspect the
residential and low traffic volume streets.
Sewer Line Maintenance
➢ Routine cleaning of 1,545,537 linear feet of sewer pipe.
➢ Removal of 6,500 pounds of debris/grit during routine cleaning.
➢ Cleaned 225 enhanced cleaning areas (areas of sewer line cleaned from two
times to twelve times per year) for a total of 489,565 linear feet through June.
➢ Applied root control to 25,000 linear feet of sewer line.
➢ Sewer lateral repair program received 216 requests for repair to date.
➢ Inspected via Closed Circuit Television (CCTV) 558,500 linear feet of residential
sewer lines and arterial mains.
Sewer Lift Station Maintenance
➢ Inspected 27 lift stations three times a week and cleaned each station every two
months.
➢ Cleaned 254 check valves
➢ Replaced 3 check valves
➢ Replaced 2 gate valves.
➢ Disassembled and rebuilt 8 sewer pumps.
➢ Replaced 5 transducers.
➢ Cleaned 27 sewer wet wells; projected to be 32 by year's end.
➢ Replaced stainless steel electrical panel at New Britain Lift Station.
Emergency Response
➢ 2 Public Sanitary Sewer Overflows (SSO) to date, 1 reportable Private Lateral
Spill discharge to date.
➢ 307 service requests from the public during business hours.
➢ 72 after hours lift station alarms and failures.
➢ 105 after hours call outs for miscellaneous sewer related problems.
➢ 6 emergency sewer line point repairs.
July 2015 -3 -
Sewer Lateral Program
Under the Sewer Lateral Program, the City assumed responsibility for the repair of all
sewer laterals from the City-owned sewer main through the public right-of-way to the
private property line. The property owner remains responsible for all costs of repair and
maintenance of that portion of the sewer lateral on private property. This program is
response driven as all work orders are generated in response to calls from residents
and businesses. Expenditures on the Sewer Lateral Program have decreased
significantly since the program was initiated in Fiscal Year 2008/09.
Staff had previously budgeted for the Sewer Lateral Program based on the expenditures
in the first two years of the program. However, following reductions in calls after the first
three fiscal years of the program, staff reduced the budget for fiscal year 2013/14.
Demand has leveled off over the past three years.
Sewer Lateral Expenditures
$2,soo,000
$2,000,000
$1500,000
$1,000,000
$500,000
$0
2008/09 2009/10 2010/11 2011/12 2012/13 2013/14 2014/1s
July 2015 -4-
Sewer Service Fund Budget
FY2014115 Projected Expenditures
Personnel Original Budget Revised Budget* Projected
Salaries, Permanent $1 ,962,113 $1,962,113 $1,845,208
Salaries, Temporary $65,000 $65,000 $44,516
Salaries, Overtime $80,000 $80,000 $103,709
Benefits $1,103,930 $1,103,930 $1,034,787
Total Personnel $3,211,043 $3,211,043 $3,028,220
Operating
Utilities $110,000 $110,000 $105,865
Equipment and Supplies $355,350 $355,358 $161,736
Repairs and Maintenance $1 ,543,000 $1,543,000 $1,430,862
Conferences and Training $3,000 $3,000 $3,526
Professional Services $500,000 $538,665 $353,297
Rental Expense $3,500 $3,500 $3,326
Interdepartmental Charges $1 ,282,179 $1,282,179 $1,282,179
Expense Allowance $5,800 $5,800 $5,800
Other Expenses $75,000 $75,000 $15,000
Total Operating $3,877,829 $3,916,502 $3,361,592
Capital
Equipment $585,480 $585,480 $252,306
Vehicles $588,600 $753,609 $748,077
Total Capital $1,174,080 $1,339,089 $1,000,383
CIP
Improvements $2,050,000 $6,632,958 $6,027,908
Total CIP $2,050,000 $6,632,958 $6,027,908
Total $10,312,952 $15,099,592 $13,418,103
*Revised Budget includes funds carried over from prior fiscal year
July 2015 -5 -
Beginning Balance 10/1/2013 $34,834,188
Actual Revenues FY 13/14 $10,903,501
Actual Expenditures FY 13/14 ($19,969,618)
Unreserved Funds Available 10/1/2014 $25,768,071
Beginning Balance 10/1/2014 $25,768,071
Projected Revenues FY 14/15 $11 ,113,142
Proposed Expenditures FY 14/15 _ ($13,418,103)
Projected Beginning Balance 10/1/2015 $23,463,110
Revenue Detail
Source FY 13/14 FY 14/15
Actual Projected
Customer Charges $10,607,679 $10,526,592
Interest $195,883 $25,000
Other $99,939 $561 ,550
Total $10,903,501 $11,113,142
Proposed FY 2015/16 Budget
Sewer Service User Charge Adjustments
In accordance with Section 14.55.030 Annual CPIU Adjustments, each Sewer Service
User Charge shall be adjusted to reflect the annual percentage adjustment in Consumer
Price Index for all Urban Consumers (CPIU) in Los Angeles, Orange and Riverside
Counties established by the U.S. Bureau of Labor Statistics and available as of July 1 of
each year. The purpose for annual adjustment of the rates is to ensure that the
revenues continue to fully fund the needs of the program.
To accommodate the billing system, all service charge rates are calculated to four
decimal places, and charged on a daily factor. The daily factor converts the monthly
charge based on a 365-day year. This is a modification from the initially adopted rate
schedule. The customer's bill reflects a charge based on the number of days between
meter readings. A resolution was adopted by the City Council to authorize the daily rate
methodology.
The percentage adjustment in the CPIU available as of July 1 , 2015 for the month of
May reflects an annual increase of 1 .1%. This percentage adjustment is included as the
recommended adjustment to the Sewer Service User Charge effective October 1, 2015,
pending a Proposition 218 protest hearing in August.
July 2015 -6-
The following table shows the 1 .1% increase. For purposes of comparison, the rates
represent a monthly charge.
Effect of CPI Adjustment on Current Sewer Service Charge
Current With CPI
Customer Category Charge Type Unit Charge Increase
Residential: Single-family & Flat rate for all customers in per unit $10.6923 $10.8099
townhouses with individual category per
meters month
Apartment: All apartments, Flat rate for all customers in per unit $8.8693 $8.9669
mobile homes and townhouses category per
served by common meters month
Regular Flat rate amount per Equivalent per EDU $12.4089 $12.5454
Commercial/Industrial: Most Dwelling Unit (EDU). EDU per
businesses, including private refers to either (1) the capacity of month
schools a customer's water meter in
comparison to a standard 3/4 inch
meter, or (2) the number of
tenant units that receive water
service through the water meter,
whichever is greater
High-Consumption Flat rate per hundred cubic feet per CCF $2.3219 $2.3474
Commercial/Industrial: (CCF) of estimated sewer per year
Businesses with high water discharge
consumption relative to their
meter size
Public Schools: All public K-8 Flat rate per student per year High $3.4150 $3.4526
and high school districts with with a different rate per student School
schools in the City for K-8 and for high schools per ADA
per year
ADA - Average Daily Attendance
K-8 $2.1991 $2.2233
per ADA
per year
July 2015 -7 -
Sewer Service Fund Budget
FY 2015116 Proposed
Personnel
Salaries, Permanent $2,021 ,662
Salaries, Temporary $62,500
Regular Overtime $82,500
Benefits $1,189,953
Total Personnel $3,356,615
Operating
Utilities $110,000
Supplies $348,350
Repairs and Maintenance $1,543,000
Conferences and Training $4,000
Professional Services $1,030,000
Rental Expense $3,500
Cost Allocation $1,320,644
Auto Allowance $5,800
Contingency $75,000
Total Operating $4,440,294
Capital
Equipment $99,360
Vehicles $806,760
Total Capital $906,120
CIP (new)
Lift Station (Edgewater) $2,500,000
Sewer Lining $350,000
Total CIP $2,270,000
TOTAL $11,553,029
Revenue Detail FY 15116
Customer Charges $10,714,000
Other $116,000
Total $10,830,000
July 2015 - 8 -
Sewer Service Fund Projected Balance Sheet
Beginning Balance 10/1/2015 $23,463,110
Projected Revenues FY 15/16 10,830,000
Proposed Expenditures FY 15/16 ($11,553,029)
Projected Beginning Balance 10/1/2016 $22,740,081
Capital Projects FY 2015/16
Lift Stations: Design is planned in 2015 for the Edgewater Lift Station; construction is
estimated to begin in the winter of 2016. Design is scheduled for the Slater Lift Station
in 2016.
Sewer Linino: Sewer lining in the amount of $350,000 is programmed in FY 2015/16. A
lining project is bid once a sufficient number of sewer defects are identified as part of
the CCTV inspection program.
July 2015 -9-