• City owns and maintains 36 bridges
• Majority of HB bridges constructed in the 1960s
• Maintenance and rehabilitation is needed
• Federal grants made available through the Safe,
Accountable, Flexible, Efficient, Transportation
Equity Act: A Legacy for Users (SAFETEA-Lu)
beginning 2005
• A Bridge Preventative Maintenance Plan
(BPMP) is required for grant eligibility
2
/ o - / - Aao 7-
..S7uay
10/01 /07 1
Bridge study included in FY 2006/07 Capital
Improvement Program
In February 2007, City Council authorized LAN
Engineering to complete BPMP
LAN performed review of Caltrans inspections
and visual inspection of current conditions
BPMP completed July 2007
Draft plan presented to the Public Works
Commission in July
Purpose — To maximize service life of bridges
Goals
Preserve bridges in a structurally safe and
serviceable condition
�� Correct minor structural issues
Correct structural maintenance deficiencies
as early and cost effectively as possible
Make efficient use of limited resources
3
4
10/01 /07 2
10/01 /07
All 36 bridges currently structurally sound
4 qualify for rehabilitation/replacement
grants
.d Admiralty
Davenport
Humboldt
Gilbert
All qualify for preventative maintenance
grants
Estimated Preventative
Maintenance Costs $7.5 M
(32 bridges)
• Estimated Replacement Costs $ 9 M
(4 bridges)
• SAFETEA-LU grant funds 88%
• City provides 12% match
• Grant funding is competitive
a
10/01 /07 4
$250,000 from Gas Tax is programmed
in FY 2007/08 to begin
Contract preliminary engineering to
develop costs estimates
o Prepare and submit grant applications
9