ASCON LANDFILL SITE UPDATE SLOPE FAILURE CONCERN
► CURRENT STATUS ►TIMELINE
Clean-up efforts-Stopped since June December 31, 2019-ASCON identified tension cracks on the berm
along Hamilton
ASCON is pursuing tenting/enclosure permits and work plan February 6, 2020-Additional tension cracks identified
approval • Estimated medium to high risk of slope failure
DTSC & ASCON have evaluated tension cracks on the February-April 2020 DTSC and ASCON evaluated options to repair
northwest berm and alleviate slope failure.
April 2, 2020-Online community forum on emergency repair work
Proceeding with emergency repair work as of today April 10, 2020-DTSC provided approval letter for ASCON to proceed
Outlined strict conditions for all repair work to mitigate any impacts to the
community
SLOPE FAILURE CONCERN TENSION CRACKS IDENTIFIED
All
WWI
UI
a i
r
EMERGENCY REPAIR WORK EMERGENCY
REPAIR WORK
► RISK & SAFETY CONCERNS
► If berm cracks are not addressed... ► Moving forward with Managed �,
• Contaminated material could enter Hamilton Avenue Slope Excavation to stabilize and
flatten the berm
• Could result in uncontrolled release of VOCs, odors & dust ► Outreach has included:
r
• Emergency response would be needed ► 10,000 mailed postcards
• Rains increase chances of failure ► Online community forum
► Outreach letter
► Updated website & social media
EMERGENCY REPAIR WORK EMERGENCY REPAIR WORK
► EXCAVATION RATE ► ADDED SAFETY MEASURES
Closely managed by DTSC
Allowing only 50 cubic yards per day to start Limiting daily amount of excavation allowed to be
performed
After 3 days, if there is demonstrated odor control and no issues
arise,the excavation rate can be increased by an additional 25 Added dust and odor controls-Foam suppressants,
yards misting sprays, soil, and plastic covering
This can continue up to a maximum rate of 200 cubic yards / Air monitoring and sampling of the site
day g p g
Rate can also be stopped or decreased if issue arises Must stop excavation if odors cannot be controlled
► IN COMPARISON... DTSC committed to having staff on site at all times during
► Last year's excavation late was 2,000 cubic yards/day when work is conducted
HOW TO STAY INFORMED QUESTIONS OR CONCERNS ?
• HTTPS:�'A4t"�N�f�a,�,t9�,,�;'��. ► DTSC Project Manager
► Safouh Sayed. 714-484 `
• Sign-up for weekly a-mail updates
► DTSC Public Participation Supervisor
E-mail: ► Maya Akula, 714-484-5410,
Public hotline for non-emergency information: (714) 388-1825 ► South Coast Air Quality Monitoring District jSCAQMD)
► Air Quality and Dust Monitoring Questions
Stay Informed
► 1 800 CUT-SMOG (1-800 288 iv64)
Ascon Huntington Beachsubscribe for email updates ► Ascon Project Contacts
A safer,cleaner future for the community
sIc,NMt uv ► Hotline:714-388-1825
► Email: