DBFOM City Facility Upgrade Status Update
City Council Meeting
June 15, 2021
•
•J
�•.«rwcto. w+cw
DBFOM Option Presented For Council Review On March 15
• On March 15, staff presented an
overview of the Design-Build-Finance-
Operate-Maintain (DBFOM) option .W
for addressing major facility capitalt-
improvements Iy
-City currently operates and maintains
1.75 million so ft.of facilities
- Average age of our City facility buildings
:s between 30—40 years old
•The City has identified several major
facility capital improvement needs -
- New Police Station
-City Hall Improvements
-Lake Fire Station
-Public works Corporate yard
- Lifeguard Headquarters SUPPLEMENTAL
D _ (Q1151��ai
Agends Urn Nlo.� 2 I '/ • 1
• 6/15/2021
DBFOM Project Model Overview
• One reason that DBFOM project model could work in HB is because of existing City real-property assets
- Civic Center facility is large enough to accommodate possible private development
•If parking structure is developed at the Civic Center, additional housing/retail development could be feasible
•Lake Fire station located at the Civic Center as part of planned upgrades?
•Develop existing Lake Fire Station Property
-The City's Public Works Yard is a sizable property that could also be developed
•DBFOM project model opportunities
-Capitalize on private developer expertise
-Leverage value from existing City assets
-Maintenance of new facilities is guaranteed through the project term
- Required City capital outlays are minimal
• DBFOM project challenges
-City loses some flexibility with the facilities through the term of the agreement
-Developer is involved in all future facility upgrades through the agreement term
DBFOM Process Next Steps
• Based on prior City Council review, staff issued an RFQ on April 7, 2021, to identify a development partner
for this overall venture
- Responses were due May 13,2021
- Interviews are being scheduled for late-;une 2021
- Consider approval of an Exclusive Negotiating Agreement to select the identified partner anticipated for August 2021